Maritana Minerals hits “significant” Black Swan approval milestone
By Ben Cartwright.
Maritana Minerals has reached a key development milestone at its Black Swan processing hub (BSPH) in Western Australia, with all statutory approvals for the processing plant now in place and early works extended with GR Engineering Services.
The Native Vegetation Clearing Permit (NVCP) was granted by the Western Australian Department of Local Government, Industry Regulation and Safety (LGIRS) in September, completing the approvals required for earthworks and construction of the new section of the 2.5 million tonnes per annum processing facility.
The Black Swan processing hub is located approximately 50km north-east of Kalgoorlie in Western Australia’s Goldfields.
Maritana has also extended its early works agreement with GR Engineering Services to October 2027, adding a further $6.5 million in committed expenditure to the existing $25 million commitment.
The extension will maintain continuity of engineering, procurement, site delivery, demolition and bulk earthworks while the engineering, procurement and construction (EPC) contract for the processing plant is finalised.
Maritana managing director and chief executive officer Grant Haywood said securing the NVCP represented an important step towards the development of the processing hub.
“The NVCP was the last statutory approval required for the full processing plant; this is a significant milestone for Maritana and the development of the Black Swan Processing Hub in preparation for first gold in the second half of 2027 [H2 CY2027],” Haywood said.
“Extending the early works agreement with GR Engineering to 31 October 2027 keeps the engineering, long-lead procurement, on-site works and construction activities running while the EPC contract is being finalised.”
Long-lead procurement is continuing under the extended early works agreement, including elution columns, carbon-in-leach (CIL) bolted tanks, intertank screens and platework packages.
Previous approvals secured for the project include approval of the mining development and closure proposal for the processing facility by the Department of Mines, Petroleum and Exploration (DMPE) on July 27 and the Works Approval for the carbon-in-leach circuit by the Department of Water and Environmental Regulation (DWER) on August 5.
Maritana said mining restart at Boorara remains targeted for mid-2027, with a 60,000m resource conversion campaign continuing across the Maritana Kalgoorlie project area.