Amended Rose Hill Resource and Maiden Ore Reserve Update
Released
Released
Announcement PDF
Maritana Minerals Limited | ABN 88 007 761 186 | maritanaminerals.com.au
PO Box 1064, West Perth WA 6872 | +61 8 9386 9534 | info@maritanaminerals.com.au
ASX: MRT
ASX ANNOUNCEMENT
3 November 2026
REPLACEMENT ANNOUNCEMENT - ROSE HILL MINERAL
RESOURCE AND MAIDEN ORE RESERVE UPDATE
Maritana Minerals Limited (ASX: MRT) (Maritana or the Company) has today released a replacement of its
announcement "Rose Hill Mineral Resource and Maiden Ore Reserve Update" dated 31 August 2026
(Announcement) to amend the Competent Person statements and to correct minor drafting errors.
The Announcement re-reported the Rose Hill Mineral Resource estimate, prepared by Ms Christine Shore in
November 2020, at a revised underground cut-off grade. The re-reporting was undertaken by Mr Stephen
Godfrey, Resource Development Manager. The Announcement erroneously stated Ms Shore as the
Competent Person, including that she consented to the inclusion of her information and was an employee of
Entech Pty Ltd.
The Announcement is amended to correct this and attribute Mr Godfrey as the Competent Person for the Rose
Hill Mineral Resource estimate. Mr Godfrey, Mr Stephen Guy and Ms Adrianna Skok-Muir have each given
prior written consent to the inclusion of the matters based on their information in the form and context in which
they appear.
There have been no changes to the reported Mineral Resources and Ore Reserves.
This announcement has been authorised for release by the Board of Directors.
For further information, please contact:
Isabel Macchia, Company Secretary isabel.macchia@maritanaminerals.com.au | +61 8 9386 9534
Maritana Minerals Limited | ABN 88 007 761 186 | maritanaminerals.com.au
PO Box 1064, West Perth WA 6872 | +61 8 9386 9534 | info@maritanaminerals.com.au
ASX: MRT
ASX: MRT
ASX ANNOUNCEMENT
3 November 2026
ROSE HILL MINERAL RESOURCE AND MAIDEN ORE
RESERVE UPDATE - AMENDED
Maritana Minerals Limited (ASX: MRT) (“Maritana” or “the Company”) is pleased to announce an updated
Mineral Resource and Maiden Ore Reserve for the Rose Hill Project, near Coolgardie, Western Australia.
HIGHLIGHTS
• Maiden Ore Reserve for the Rose Hill Underground of 420 kt at 2.34 g/t Au for 31,600 ounces of gold
(Proved and Probable, 1.3 g/t Au cut-off grade)
• Maritana Group Ore Reserves1
increase by 31,600 ounces to 235.6 kilo ounces of gold
• Rose Hill Mineral Resource1
re-reported at lower cut-off grades – underground 524 kt at 4.49 g/t Au
for 76,000 ounces (1.0 g/t Au cut-off); open pit unchanged at 287 kt at 1.99 g/t Au for 18,000 ounces
(0.5 g/t Au cut-off)
• Inferred Mineral Resource1
of 194 kt at 4.53 g/t Au for 28,000 ounces was excluded from the Ore
Reserve and offers upside at depth
• Ore to be hauled to Black Swan Processing Hub where the conversion of the plant to gold processing
is currently underway, with first gold planned for H2 CY27
Managing Director and CEO Mr Grant Haywood commented:
“Declaring a maiden Ore Reserve for the Rose Hill Underground is a significant milestone for Maritana and
lifts our Ore Reserve inventory to 236 koz. It confirms that Rose Hill stands up economically and moves the
Project a meaningful step closer to development.”
“A stronger gold price, combined with the outcomes of our optimisation studies, has allowed us to re-report the
underground Mineral Resource at a lower 1.0 g/t Au cut-off, returning 524 kt at 4.49 g/t Au for 75,570 ounces.
Rose Hill's position near Coolgardie, within reach of established processing infrastructure, remains a real
advantage for the Project.”
“Importantly, the deposit remains open at depth and the Inferred Mineral Resource points to further upside.
We see genuine scope to grow this inventory with additional drilling.”
Maiden Ore Reserve
The Rose Hill underground Mineral Reserve has been re-reported at a 1.3 g/t Au cut-off and returns 420 kt at
2.34 g/t Au for 31,600 ounces of gold. The PFS report underpinning the Rose Hill Ore Reserve was completed
1
Refer to ASX Announcement “Annual Mineral Resources and Ore Reserves Statement” dated 20 August 2026
maritanaminerals.com.au Page | 2
by Mining Plus in July 2026 and provides the technical justification and economic assessment that underpin
and support the outcomes of the mining study.
Table 1 - Rose Hill UG – Ore Reserves (COG 1.3g/t)
Category Tonnes (Mt) Au Grade (g/t) Au Metal (koz)
Proved 0.07 2.14 4.7
Probable 0.35 2.37 26.8
Total 0.42 2.34 31.6
Mineral Resource
With the increase in gold price and recent results from optimisation studies, the Rose Hill Mineral Resource is
proven to be economic at a lower cut off grade than previously reported.
The Rose Hill underground Mineral Resource has been re-reported at a 1.0 g/t Au cut-off and returns 524 kt
at 4.49 g/t Au for 75,570 ounces of gold.
The Open pit resource remains the same at 287 kt at 1.99 g/t Au for 18,000 ounces of gold.
Table 2 - Rose Hill Mineral Resource (Open Pit COG 0.5 g/t; Underground COG 1.0 g/t)
Category Tonnes (Mt) Au Grade (g/t) Au Metal (koz)
Open Pit – Measured 0.19 1.96 12
Open Pit – Indicated 0.09 2.05 6
Open Pit Total 0.29 1.99 18
Underground – Indicated 0.33 4.46 47
Underground – Inferred 0.19 4.53 28
Underground Total 0.52 4.49 76
Total Mineral Resource 0.81 3.61 94
Tonnages are dry metric tonnes. Minor discrepancies may occur due to rounding
Competent Persons Statements
Exploration and Sampling Results
The information in this announcement that relates to exploration results, geology and data compilation is based
on information compiled under the supervision and review of Mr Stephen Guy, a Competent Person who is a
Member of The Australian Institute of Geoscientists (8203). Mr Guy is the Chief Geologist for Maritana Minerals
Limited, is a full-time employee of the Company and holds shares and options in the Company. Mr Guy has
sufficient experience which is relevant to the style of mineralisation and type of deposit under consideration
and to the activity which he is undertaking to qualify as a Competent Person as defined in the 2012 Edition of
the “Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves”. Mr Guy
consents to the inclusion in the announcement of the matters based on his information in the form and context
in which it appears.
maritanaminerals.com.au Page | 3
Mineral Resource
The information in this announcement that relates to the estimation and reporting of Mineral Resources is
based on information compiled by Mr Stephen Godfrey, a Competent Person who is a Fellow of The
Australasian Institute of Mining and Metallurgy (FAusIMM #110542) and a Member of The Australian Institute
of Geoscientists (MAIB #3993). Mr Godfrey is the Resource Development Manager and a full-time employee
of the Maritana Minerals Ltd and does not hold shares or options in the Company. Mr Godfrey has sufficient
experience relevant to the style of mineralisation and type of deposit under consideration and to the activity
being undertaken to qualify as a Competent Person as defined in the 2012 Edition of the “Australasian Code
for Reporting of Exploration Results, Mineral Resources and Ore Reserves”. Mr Godfrey consents to the
inclusion in the announcement of the matters based on his information in the form and context in which it
appears.
Mr Godfrey has undertaken several site visit to the Rose Hill Project since 2021. Areas visited included the
Rose Hill Open Pit and surrounds, and the Nimbus core yard. No material issues or risks pertaining to the
resource update were identified, observed or documented during the visits.
Ore Reserve
The mining specific information in this report that relates to Ore Reserves is based on information compiled by
Adrianna Skok-Muir (Mining), who is a Member of The Australasian Institute of Mining and
Metallurgy (MAusIMM # 205109) . Adrianna Skok-Muir is employed full time by Maritana Minerals and has
sufficient experience which is relevant to the style of mineralisation and type of deposit under consideration
and to the activity which she is undertaking to qualify as a Competent Person as defined in the 2012 Edition
of the ‘Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves'.
Adrianna Skok-Muir consents to the inclusion in the report of the matters based on her information in the form
and context in which it appears.
Authorised for release by the Board of Directors.
For further information, please contact:
Grant Haywood Michael Vaughan
Managing Director and CEO Investor and Media Relations – Fivemark
grant.haywood@maritanaminerals.com.au michael.vaughan@fivemark.com.au
+61 8 9386 9534 +61 422 602 720
JOIN MARITANA MINERALS INTERACTIVE HUB
Visit https://maritanaminerals.com.au/auth/signup
for Maritana Minerals’ Interactive InvestorHub
MARITANA MINERALS
Email: info@maritanaminerals.com.au
maritanaminerals.com.au Page | 4
Forward Looking and Cautionary Statements
Some statements in this report regarding estimates or future events are forward looking statements. They
include indications of, and guidance on, future earnings, cash flow, costs and financial performance. Forward
looking statements include, but are not limited to, statements preceded by words such as “planned”,
“expected”, “projected”, “estimated”, “may”, “scheduled”, “intends”, “anticipates”, “believes”, “potential”, “could”,
“nominal”, “conceptual” and similar expressions. Forward looking statements, opinions and estimates included
in this announcement are based on assumptions and contingencies which are subject to change without notice,
as are statements about market and industry trends, which are based on interpretations of current market
conditions. Forward looking statements are provided as a general guide only and should not be relied on as a
guarantee of future performance. Forward looking statements may be affected by a range of variables that
could cause actual results to differ from estimated results, and may cause the Company’s actual performance
and financial results in future periods to materially differ from any projections of future performance or results
expressed or implied by such forward looking statements. These risks and uncertainties include but are not
limited to liabilities inherent in mine development and production, geological, mining and processing technical
problems, the inability to obtain any additional mine licenses, permits and other regulatory approvals required
in connection with mining and third party processing operations, competition for among other things, capital,
acquisition of reserves, undeveloped lands and skilled personnel, incorrect assessments of the value of
acquisitions, changes in commodity prices and exchange rate, currency and interest fluctuations, various
events which could disrupt operations and/or the transportation of mineral products, including labour stoppages
and severe weather conditions, the demand for and availability of transportation services, the ability to secure
adequate financing and management’s ability to anticipate and manage the foregoing factors and risks. There
can be no assurance that forward looking statements will prove to be correct.
Statements regarding plans with respect to the Company’s mineral properties may contain forward looking
statements in relation to future matters that can only be made where the Company has a reasonable basis for
making those statements.
This announcement has been prepared in compliance with the JORC Code (2012) and the current ASX Listing
Rules.
The Company believes that it has a reasonable basis for making the forward looking statements in the
announcement, including with respect to any production targets and financial estimates, based on the
information contained in this and previous ASX announcements.
Cautionary statement
Statements in this report relating to the Life of Mine (LOM) pertain to the Company’s Scoping Studies which
were originally released to the ASX on 17 February 2026 and are preliminary in nature. The Scoping Studies
include Indicated and Inferred Mineral Resources and are based on low-level technical and economic
assessments, which are insufficient to support estimation of Ore Reserves. There is no certainty that the study
outcomes, including production targets and financial assumptions, will be realised. All material assumptions
and technical parameters underpinning the Scoping Study production targets and financial information
continue to apply and have not materially changed since that announcement.
maritanaminerals.com.au Page | 5
Table of Contents
1. PROJECT LOCATION............................................................................................................................. 6
2. PROJECT HISTORY AND HISTORICAL MINERAL RESOURCES....................................................... 7
3. GEOLOGY............................................................................................................................................... 8
4. DRILLING TECHNIQUES ....................................................................................................................... 9
5. SAMPLING.............................................................................................................................................. 9
6. SAMPLE ANALYSIS.............................................................................................................................. 10
7. MINERAL RESOURCE ESTIMATION .................................................................................................. 10
8. MINERAL RESOURCE CUT-OFF GRADE............................................................................................11
9. MINERAL RESOURCE ..........................................................................................................................11
10. MINERAL RESOURCE CLASSIFICATION........................................................................................... 12
11. ASSESSMENT OF REASONABLE PROSPECTS FOR EVENTUAL ECONOMIC EXTRACTION ..... 13
12. RELIANCE ON OTHER EXPERTS....................................................................................................... 15
13. GEOTECHNICAL .................................................................................................................................. 15
14. INTRODUCTION................................................................................................................................... 15
15. GEOTECHNICAL RECOMMENDATIONS............................................................................................ 15
16. MINE DESIGN PARAMETERS............................................................................................................. 16
16.1 Mining Method Analysis and Cut-off Grade Calculation........................................................... 16
16.2 Mining Method .......................................................................................................................... 24
16.3 Ore and Waste Determination .................................................................................................. 26
16.4 Mine Production Design ........................................................................................................... 26
16.5 MSO Parameters...................................................................................................................... 27
16.6 Stope Design ............................................................................................................................ 28
16.7 Mine Development Design ....................................................................................................... 31
16.8 Decline...................................................................................................................................... 32
16.9 Level Access............................................................................................................................. 33
16.10 Ore Drives................................................................................................................................. 34
16.11 Vertical Development Design ................................................................................................... 34
16.12 Mine Design – LOM.................................................................................................................. 34
17. METALLURGY AND PROCESS DEVELOPMENT............................................................................... 38
17.1 Mine Design – PFS Reserve Estimate..................................................................................... 40
18. VENTILATION ....................................................................................................................................... 44
19. MINING EQUIPMENT........................................................................................................................... 45
19.1 Mining Equipment Selection..................................................................................................... 45
20. PROJECT INFRASTRUCTURE AND MINE SERVICES...................................................................... 47
20.1 Mine Schedule.......................................................................................................................... 48
20.2 Schedule Assumptions ............................................................................................................. 48
maritanaminerals.com.au Page | 6
20.3 LOM Schedule.......................................................................................................................... 50
20.4 Cost Estimate ........................................................................................................................... 52
21. EVALUATION OUTCOMES...................................................................................................... 54
21.1 Case Description ...................................................................................................................... 54
21.2 Modelling Outcomes................................................................................................................. 54
21.3 Summary of Findings................................................................................................................ 56
21.4 Sensitivities............................................................................................................................... 57
21.5 Ore Reserves............................................................................................................................ 57
22. COMPETENT PERSONS STATEMENTS ............................................................................................ 58
23. MARITANA MINERALS GLOBAL MINERAL RESOURCE INVENTORY............................................. 59
24. MARITANA MINERALS GLOBAL ORE RESOURCES......................................................................... 60
Listing Rule 5.8 Disclosures
Pursuant to ASX listing rule 5.8.1, and in addition to the information contained in the attached JORC Code
tables, the Company provides the following details in respect of the mineral resources listed above.
1. PROJECT LOCATION
Rose Hill is located 0.5 kilometres southeast of Coolgardie and 35 kilometres west of Kalgoorlie-Boulder in the
Western Australian Goldfields. Maritana’s Black Swan Processing Facility is 85 km from Rose Hill. Rose Hill
was acquired as part of an asset swap completed with Northern Star Resources Ltd. The project location is
shown in Figure 1 and Figure 2.
Figure 1 - Rose Hill Project Location (Western Australia)
maritanaminerals.com.au Page | 7
Figure 2 - Rose Hill Project Location – Proximity to Coolgardie, Kalgoorlie and Black Swan Plant
ROSE HILL MINERAL RESOURCE
2. PROJECT HISTORY AND HISTORICAL MINERAL RESOURCES
The Rose Hill tenement has an exploration and production history going back to 1893, approximately four
months after the discovery of gold in Coolgardie in September 1892. The lease area was covered/intersected
by 15 different mining leases through to 1973 when the area of M 15/652 was pegged as GML 15/6195 by
Premier Gold NL.
The Rose Hill Project was purchased by Copperfield Gold (subsequently renamed New Hampton Goldfields
NL in Sept 1996) from W. Powell. By 2005 the Rose Hill deposit is 100% owned by South Kal Mines Pty Ltd,
maritanaminerals.com.au Page | 8
a wholly owned subsidiary of Harmony (Australia) Ltd. Harmony declared a Mineral Resource Estimation of
1,134,175t @ 2.84g/t for 103,559oz at a 1.0g/t cutoff.
In 2007 the Rose Hill Project was sold to Dioro Exploration NL. Avoca acquired Dioro in 2010. Avoca
Resources merged with Anatolia Minerals Development Ltd to form Alacer Gold in 2011. In 2013 Alacer sold
their Australian gold assets to Metals X which in 2016 demerged their gold assets into Westgold Resources.
Production records to 1983 show 4,855 tonnes mined recovering 1477 ounces of gold giving an average grade
of 9.4g/t. Most of the current open pit was mined between 1984 and 2005. No production records are
available.
Horizon Minerals Ltd acquired the Rose Hill deposit from Northern Star Resources Ltd (NST) in 2019 and first
reported an updated Mineral Resource as announced to the ASX on 4 February 2020, comprising 1.2 Mt at
2.49 g/t Au for 95,200 ounces (at a 0.7 g/t Au cut-off grade)2
.
In April 2024, Horizon Minerals was renamed Maritana Minerals.
3. GEOLOGY
The Rose Hill deposit lies on the western margin of the Archaean Norseman – Menzies Greenstone Belt. Host
rocks at Rose Hill are a sequence of Archaean Basalts and Ultramafics, which have been intruded by a suite
of porphyry dykes (also described as diorites). The porphyries host the bulk of the mineralisation, occurring in
two orientations, steeply dipping (70°- 80°) with an average width of three to five metres, or flatter dipping
(20°- 40°) with widths of up to two metres. Mineralisation consists of a stock work of quartz / sulphide micro-
veining and albitic alteration of the porphyry. The Porphyry is truncated by two NE trending faults that are
associated with higher grades.
Interpretations of domain continuity were initially undertaken within Leapfrog3DTM software, with
mineralisation intercepts correlating to individual domains manually selected prior to creation of a vein model.
Interpretation was a collaborative process with MRT Geologists to ensure modelling appropriately represented
site-based observations and current understanding of geology and mineralisation controls. Following this, a
total of three Halo and nine high grade mineralisation sub-domains were delineated at Rose Hill.
Mineralisation volume domains were delineated using a combination of:
• Geological information comprising: Lithology, veining and sulphides;
• Halo Domains utilised a nominal lower grade minimum cut-off of 0.3 g/t gold;
• High Grade (HG) sub-domains utilised a nominal 1.5 g/t gold within the higher grade internal sub-
domains. This value was based on exploratory data analysis of mineralisation sample population as
well as visual review of the mineralisation tenor and strike, and dip continuity.
For instances where the intercept gold value was below the nominal cut-off however mineralisation continuity
was supported by veining and alteration, the intercept was included within the domain due to the commodity
and the style of deposit.
2
Refer to ASX Announcement “High Grade Drill Results and Resource Update for Rose Hill”) dated 4 February 2020
maritanaminerals.com.au Page | 9
Figure 3 - Hill Deposit Oblique Section (Azimuth 044˚). Presenting drillhole traces, Mineralised
Domains, weathering, topography and underground depletion area.
4. DRILLING TECHNIQUES
A total of 22,080 m of drilling from 284 drill holes was available for this MRE. Mineralisation interpretations
were informed by Reverse Circulation drilling (281 drill holes of which 187 intersect the resource), with
Diamond Drilling (3 drill holes inclusive of diamond tails of which 3 intersect the resource) for 3,041 m of drilling
intersecting MRE.
Recent RC drilling (2019-2020) was completed with a 5¼ inch face sampling hammer bit.
Diamond tail drilling was carried out by using HQ triple tube.
The historical drilling comprises Reverse Circulation and Diamond Core undertaken during the 1990’s. Limited
detail of historical drilling techniques was available to the company, therefore a key focus of the 2020 drilling
was to twin and infill drill areas of the MRE informed by historical drill information. All areas of the MRE are
now sufficiently supported by this recent drill information.
5. SAMPLING
For the recent drilling, 1m Reverse Circulation (RC) samples were obtained by cone splitter (1.5 kg – 2.0 kg)
and were utilised for lithology logging and assaying. Samples collected in mineralisation were all dry.
maritanaminerals.com.au Page | 10
For recent diamond drilling (DD), core was utilised for geotechnical and bulk density measurements as well as
lithology logging and assaying. Half of the core was sampled with the remainder of the core transferred to
permanent storage. The core was predominantly sampled at 1.0m intervals within the diorite, except where
mineralisation was noted outside of these areas, with some sampling on geological intervals from 0.2 m to
1.0 m.
Database checks were completed and included checking for:
• Checking for duplicate drill hole names and duplicate coordinates in the collar table.
• Checking for missing drill holes in the collar, survey, assay and geology tables based on drill hole
names.
• Checking for survey inconsistencies including dips and azimuths <0°, dips >90°, azimuths >360°,
negative depth values.
• Checking for inconsistencies in the “From” and “To” fields of the assay and geology tables. The
inconsistency checks included the identification of negative values, overlapping intervals, duplicate
intervals, gaps and intervals where the “From” value is greater than “To” value.
Database checks were conducted within Microsoft Excel, Access and Micromine and Surpac Mining Software.
Data has been validated against WAMEX data, but no checks have been made against hardcopy data.
6. SAMPLE ANALYSIS
All gold assaying was completed by external commercial laboratories with samples dried, crushed to 10 mm,
and then pulverised to 85% passing 75 μm and assayed using a 50 g charge for fire assay analysis with AAS
finish. Commercially prepared, predominantly matrix-matched low, medium & high value certified reference
Quality Assurance and Quality Control (QAQC) standards were inserted at a rate of 1 in 20 into the sample
stream. These techniques are industry standard for gold and considered appropriate.
Historical sample analysis included in house laboratory QAQC checks and standards, plus company inserted
standards, duplicates and blanks were regularly used and deemed acceptable. A lot of the historical work was
prepared by crushing and pulverised (90% passing -75 um) and split to either a 30 g or 50 g charge weight for
fire assaying (AAS finish) to 0.01 ppm Au detection limit.
7. MINERAL RESOURCE ESTIMATION
Sample data within mineralisation domains was composited into one metre downhole lengths using a best fit
methodology and 0.5 m minimum threshold on inclusions. Composites that marginally failed the threshold
criteria but proved significant spatially to the interpolation were included in the estimate. All other residuals
were excluded from the MRE.
Exploratory Data Analysis (EDA) of the de-clustered composited gold variable within the mineralised domains
was undertaken within SupervisorTM software. Analysis for sample bias, domain homogeneity and top capping
was undertaken.
Evidence for further sub-domaining of composite data by weathering or hole type, for the purposes of
interpolation, was not supported by statistical and spatial analysis.
Assessment and application of top-capping for the estimate was undertaken on the gold variable within
individual domains. Top caps were applied on a domain by domain basis, as outlined below:
• High Grade Domain 201. Top Cap = 33 g/t Au and 0.88% metal reduction,
• High Grade Domain 202. Top Cap = 28 g/t Au and 0.64% metal reduction.
Variography was undertaken on the capped, de-clustered gold variable within individual and grouped
mineralisation domains. Robust variogram models were delineated and utilised for Qualitative Kriging
maritanaminerals.com.au Page | 11
Neighbourhood Analysis (QKNA) to determine parent cell estimation size and optimise search
neighbourhoods.
Interpolation was undertaken utilising Dynamic Anisotropic (DA) Ordinary Kriging (OK) in Geovia SurpacTM
within parent cell block dimensions of Y: 10 mN, X: 5 mE, Z: 5 mZ. Blocks were sub celled to Y: 0.312 mN, X:
0.625 mE, Z: 0.312 mZ to provide appropriate volume definition of wireframe geometry. Dynamic anisotropy
interpolation takes into consideration the local variation of the domain orientation into the block estimation.
Considerations relating to selection of appropriate block size include: drill hole data spacing, mining method
SMU (Selective Mining Units), variogram continuity ranges and search neighbourhood optimisations (QKNA).
Domain boundaries represented hard boundaries, whereby composite samples within that domain were used
to estimate blocks within the domain.
Global and local validation of the gold variable estimated outcomes was undertaken with statistical analysis,
swath plots and visual comparison (cross and long section) against input data.
A 3D volume model of historical workings was created in Leapfrog DTM software by correlating surface
subsidence occurrences, drill intercepted void locations and lengths and historical production records of tonnes
and ounces. The 3D block model was then coded with density, depletions, weathering and classification prior
to evaluation for Mineral Resource reporting.
8. MINERAL RESOURCE CUT-OFF GRADE
The previous Mineral Re