Binding 1.4MT Ore Sale Agreement Boorara Production H2 2024
Released
Released
Announcement PDF
ASX: HRZ
ASX ANNOUNCEMENT
6 MAY 2024
BINDING 1.4MT ORE SALE AGREEMENT FOR BOORARA
ENABLES GOLD PRODUCTION TO RESUME IN H2 2024
Horizon Minerals Limited (ASX: HRZ) (“Horizon” or “the Company”) is pleased to announce that it
has entered into a binding Ore Sale Agreement (“OSA”) with Paddington Gold Pty Ltd to treat 1.4Mt
of Horizon ore from the Boorara Gold Project.
HIGHLIGHTS
•
Binding OSA has been executed with Paddington Gold Pty Ltd, a wholly owned subsidiary of
Norton Gold Fields Ltd
•
Horizon will arrange contract mining and hauling of ore from Boorara for ore processing at
Norton’s 3.8Mtpa Paddington Mill, located ~56km by road from Boorara
•
An agreed 1.4Mt (“Agreed Amount”) will be processed over a period of 22 months,
commencing in the September 2024 Quarter
•
The OSA contains competitive ore treatment rates with the payment structure as follows:
o
Within 5 days of delivering ore to the Paddington ROM pad, Paddington to pay
Horizon 50% of gross revenue less estimated processing costs and royalties, based
on the determined grade for each stockpile
o
Gross revenue calculated based on the Perth Mint spot price on the date of gold pours
o
Within 5 days of Paddington fully treating the stockpile, a final revenue calculation
shall be made based on the determined grade, moisture and metallurgical recovery,
less agreed costs for processing and state gold royalty payments, to calculate a final
payment to Horizon
o
Stockpiles to be between 10,000t – 50,000t from a combination of oxide, transitional
and fresh sources, with Paddington having the right to reject any stockpile that does
not meet specifications
o
Agreed Amount represents less then 15% of the current Boorara Mineral Resource
of 11Mt @ 1.26g/t Au for 448,240oz
o
Agreed Amount can be increased or decreased by mutual agreement
o
Conditions precedent include Paddington receiving JORC clause 12 modifying
factors for an Ore Reserve from Horizon, and Horizon demonstrating all mining
permits, approvals, mining and haulage contracts in place within 45 business days
•
An Ore Reserve for Boorara based on the tonnage going to Paddington, including forecast
economics for the ore processing agreement, will be estimated in the current June Quarter
•
Boorara is fully environmentally permitted (with last mining in 2020) and ready for
development which is expected to commence within the current June Quarter
163 Stirling Hwy
Nedlands WA 6009
PO Box 1104
Nedlands WA 6909
T: +61 8 9386 9534
E: info@horizonminerals.com.au
horizonminerals.com.au
ACN 007 761 186
ABN 88 007 761 186
ASX ANNOUNCEMENT
Commenting on the return to gold production, Chief Executive Officer Mr Grant Haywood said: 1
“This is a great opportunity for Horizon to generate strong cashflows in this high gold price
environment and takes us further down our pathway to sustained gold production. We continue to
work on our other projects to bring additional near-term cashflow into the production pipeline, along
with the additional resources and optionality of projects to come through our proposed merger with
Greenstone Resources.”
Figure 1: Horizon’s project locations, regional geology and surrounding infrastructure
1
See Forward Looking and Cautionary Statements on Page 6.
Page 2 of 6
ASX ANNOUNCEMENT
Figure 2: Horizon’s Boorara Project initial pit optimisations
Next Steps 1
•
AMC Consultants has been engaged and undertaken preliminary work on Boorara and will
progress Boorara into an Ore Reserve study under the JORC (2012) code for release in the
June 2024 Quarter
•
Continue engagement with mining and haulage contractors to finalise tenders for Boorara
and award contracts in the June 2024 Quarter
•
Finalise the 200,000 tonne mill allocation with FMR Investments’ Greenfields mill with an
executed Toll Milling Contract to support mining at the Cannon Gold Project
•
Complete the proposed merger with Greenstone Resources to enhance the long-term
production profile with development ready high-grade projects
Authorised for release by the Board of Directors
For further information, please contact:
Grant Haywood
Chief Executive Officer
Tel: +61 8 9386 9534
grant.haywood@horizonminerals.com.au
1
Michael Vaughan
Media Relations – Fivemark Partners
Tel: +61 422 602 720
michael.vaughan@fivemark.com.au
See Forward Looking and Cautionary Statements on Page 6.
Page 3 of 6
ASX ANNOUNCEMENT
Horizon Minerals Limited – Summary of Gold Mineral Resources
Project
Cutoff
Measured
Indicated
Inferred
Total
Au g/t
Mt
Au g/t
Oz
Mt
Au g/t
Oz
Mt
Au g/t
Oz
Mt
Au g/t
Oz
Boorara OP
0.5
1.28
1.23
50,630
7.19
1.27
294,140
2.6
1.3
103,470
11.03
1.26
448,240
Golden Ridge
1.0
0.47
1.83
27,920
0.1
1.7
2,800
0.52
1.82
30,720
Golden Ridge
North
0.8
0.65
1.15
24,260
0.77
1.30
32,340
1.42
1.23
56,600
Cannon UG
1.0
0.19
4.80
28,620
0.1
2.3
3,450
0.23
4.29
32,070
Monument
0.8
0.39
1.97
25,000
0.39
1.97
25,000
Pennys Find
1.5
0.20
5.45
35,000
0.1
3.6
8,000
0.27
4.99
43,000
Kalpini
0.8
1.40
2.43
108,000
0.5
2.0
31,000
1.87
2.33
139,000
Rose Hill UG
2.0
0.33
4.50
47,100
0.2
4.8
27,800
0.51
4.60
74,900
Rose Hill OP
0.5
0.09
2.00
6,100
0.29
2.00
18,400
Jacques-Peyes
0.8
0.97
2.59
81,000
0.8
2.0
49,000
1.74
2.32
130,000
Teal
1.0
1.01
1.96
63,680
0.8
2.5
64,460
1.81
2.20
128,140
Crake
0.8
1.33
1.47
63,150
0.1
1.3
3,300
1.42
1.46
66,450
Coote
1.0
0.4
1.5
21,000
0.42
1.54
21,000
Capricorn
0.5
0.7
1.2
25,500
0.70
1.20
25,500
Baden Powell
0.5
0.6
1.2
23,000
0.60
1.20
23,000
8.16
1.60
420,120
23.22
1.69
1,262,000
Total
0.19
1.47
2.00
1.33
12,300
62,930
13.83
1.75
779,000
Confirmation
The information in this report that relates to Horizon’s Mineral Resources estimates is extracted
from and was originally reported in Horizon’s ASX announcements “Intermin’s Resources Grow
to over 667,000 Ounces” dated 12 March 2019, “Rose Hill firms as quality high grade open pit
and underground gold project” dated 8 December 2020, “Updated Boorara Mineral Resource
Delivers a 34% Increase In Gold Grade” dated 27 April 2021, “Penny’s Find JV Resource Update”
dated 14 July 2021, “Updated Crake Resource improves in quality” dated 7 September 2021,
“Jacques Find- Peyes Farm Mineral Resource update” dated 15 September 2021 and “Kalpini
Gold Project Mineral Resource Update” dated 28 September 2021, each of which is available at
www.asx.com.au. The Company confirms that it is not aware of any new information or data that
materially affects the information included in the original market announcements and that all
material assumptions and technical parameters underpinning the estimates in those
announcements continue to apply and have not materially changed. The Company confirms that
the form and context of the Competent Person’s findings in relation to those Mineral Resources
estimates or Ore Reserves estimates have not been materially modified from the original market
announcements.
Page 4 of 6
ASX ANNOUNCEMENT
Horizon Minerals Limited – Summary of Silver / Zinc Mineral Resources
Nimbus All Lodes (bottom cuts 12g/t Ag, 0.5% Zn, 0.3g/t Au)
Category
Tonnes
Grade
Grade
Grade
Ounces
Ounces
Tonnes
Zn ('000t)
Mt
Ag (g/t)
Au (g/t)
Zn (%)
Ag (Moz)
Au
('000oz)
Measured Resource
3.62
102
0.09
1.2
11.9
10
45
Indicated Resource
3.18
48
0.21
1.0
4.9
21
30
Inferred Resource
5.28
20
0.27
0.5
3.4
46
29
Total Resource
12.08
52
0.20
0.9
20.2
77
104
Nimbus high grade silver zinc resource (500g/t Ag bottom cut and 2800g/t Ag top cut)
Category
Tonnes
Grade
Grade
Ounces
Tonnes
Mt
Ag (g/t)
Zn (%)
Ag (Moz)
Zn (‘000t)
Measured Resource
0
0
0
0
0
Indicated Resource
0.17
762
12.8
4.2
22
Inferred Resource
0.09
797
13.0
2.2
11
Total Resource
0.26
774
12.8
6.4
33
Confirmation
The information is this report that relates to Horizon’s Mineral Resources estimates on the
Nimbus Silver Zinc Project is extracted from and was originally reported in Intermin’s and
MacPhersons’ ASX Announcement “Intermin and MacPhersons Agree to Merge – Creation of a
New Gold Company Horizon Minerals Ltd” dated 11 December 2018 and in MacPhersons’ ASX
announcements “Quarterly Activities Report” dated 25 October 2018, “New High Grade Nimbus
Silver Core Averaging 968 g/t Ag” dated 10th May 2016 and “Nimbus Increases Resources”
dated 30th April 2015, each of which is available at www.asx.com.au. The Company confirms
that it is not aware of any new information or data that materially affects the information included
in the original market announcements and that all material assumptions and technical
parameters underpinning the estimates in those announcements continue to apply and have not
materially changed. The Company confirms that the form and context of the Competent
Person’s findings in relation to those Mineral Resources estimates have not been materially
modified from the original market announcements.
Page 5 of 6
ASX ANNOUNCEMENT
Forward Looking and Cautionary Statements
Some statements in this report regarding estimates or future events are forward looking
statements. They include indications of, and guidance on, future earnings, cash flow, costs and
financial performance. Forward looking statements include, but are not limited to, statements
preceded by words such as “planned”, “expected”, “projected”, “estimated”, “may”, “scheduled”,
“intends”, “anticipates”, “believes”, “potential”, “could”, “nominal”, “conceptual” and similar
expressions. Forward looking statements, opinions and estimates included in this announcement
are based on assumptions and contingencies which are subject to change without notice, as are
statements about market and industry trends, which are based on interpretations of current market
conditions. Forward looking statements are provided as a general guide only and should not be
relied on as a guarantee of future performance. Forward looking statements may be affected by
a range of variables that could cause actual results to differ from estimated results and may cause
the Company’s actual performance and financial results in future periods to materially differ from
any projections of future performance or results expressed or implied by such forward looking
statements. These risks and uncertainties include but are not limited to liabilities inherent in mine
development and production, geological, mining and processing technical problems, the inability
to obtain any additional mine licenses, permits and other regulatory approvals required in
connection with mining and third party processing operations, competition for among other things,
capital, acquisition of reserves, undeveloped lands and skilled personnel, incorrect assessments
of the value of acquisitions, changes in commodity prices and exchange rate, currency and
interest fluctuations, various events which could disrupt operations and/or the transportation of
mineral products, including labour stoppages and severe weather conditions, the demand for and
availability of transportation services, the ability to secure adequate financing and management’s
ability to anticipate and manage the foregoing factors and risks. There can be no assurance that
forward looking statements will prove to be correct.
Statements regarding plans with respect to the Company’s mineral properties may contain
forward looking statements in relation to future matters that can only be made where the Company
has a reasonable basis for making those statements.
This announcement has been prepared in compliance with the JORC Code (2012) where
applicable and the current ASX Listing Rules.
The Company believes that it has a reasonable basis for making the forward-looking statements
in the announcement, including with respect to any production targets and financial estimates,
based on the information contained in this and previous ASX announcements.