BSPH Project Update Increases Capacity to 2.5MT per annum
Released
Released
Announcement PDF
Maritana Minerals Limited | ABN 88 007 761 186 | maritanaminerals.com.au
PO Box 1064, West Perth WA 6872 | +61 8 9386 9534 | info@maritanaminerals.com.au
ASX: MRT
ASX ANNOUNCEMENT
8 June 2026
BLACK SWAN PROCESSING HUB UPDATE
CAPACITY INCREASED TO 2.5MTPA
Maritana Minerals Limited (ASX: MRT) (Maritana or the Company) is pleased to provide shareholders with a
comprehensive update on progress at its Black Swan Processing Hub (BSPH or the Project) project located
approximately 50km from Kalgoorlie, Western Australia. The Company continues to advance the Project on
multiple fronts, with construction targeted to commence in mid-2026.
HIGHLIGHTS
• Black Swan Processing Hub – Pre-development Advancement
o FEED Studies - increased nameplate throughput from 2.2 Mtpa to 2.5 Mtpa enhancing the
Project’s production capacity
o Capital - process plant capex is likely to increase in line with the throughput uplift and
inflationary pressures. Capex remains under review focusing on cost deferral opportunities
and alternative financing arrangements for certain items
o Mine Haulage - enlarged run-of-mine (ROM) pad design finalised to accommodate quad side-
tipping road trains and to support ore blending
o Approvals - key regulatory approvals (works approvals, MDCPs and native vegetation
clearing permits) lodged and progressing
o Project Delivery - Zeal Engineering appointed as Owner’s Engineer to strengthen technical
oversight and project delivery
o Site Supervision and Management - site mobilisation accelerated with Site Senior
Executives and OHS Manager appointed
o Mill Refurbishment - SAG mill removal scheduled to commence June 2026
o Accommodation - accommodation strategy advanced, including permanent 60-room
(scalable to 120-room) camp design at BSPH and acquisition of property in central Kalgoorlie
with ~50-room camp development approval
o Power Supply - grid power studies underway and diesel backup power station design
completed
o Water Supply - studies and bore field refurbishment planning progressed with specialist
consultants engaged
o Site Survey - comprehensive LiDAR survey completed and accurate as-built digital model
created, significantly de-risking brownfield construction
o Site Preparation - sterilisation and geotechnical drilling commenced across new
infrastructure areas
• Mining Operations – Operational Readiness
o Mine Development - experienced Mine Build Global appointed
o Contract - contract tendering for open pit, underground and haulage services commenced
• Corporate
o Key Management Appointment - COO Elizabeth Jones appointed, commencing 26 August
2026
o Funding - strong funding position with $229M cash balance and ~$11M of listed investments
maritanaminerals.com.au Page | 2
Managing Director and CEO Mr Grant Haywood commented:
“We are delighted with the substantial progress made at the Black Swan Processing Hub. The completion of
the FEED study, together with the increase in nameplate throughput above 2.2 Mtpa, materially improves the
Project’s production capacity. Site activity is ramping up quickly and key approvals are advancing.
These activities, combined with our other de-risking initiatives across infrastructure, accommodation and
power, position us well for construction commencement in mid-2026 and first production from multiple ore
sources in H2 2027. The entire team is executing strongly and we look forward to delivering the Black Swan
Processing Hub as a cornerstone asset for Maritana Minerals”.
SUMMARY
Engineering and Design
The Front-End Engineering Design (FEED) phase has been completed, with the FEED report prepared by GR
Engineering Services (GRES) now submitted for review.
The Scoping Study released on 17 February 2026 was based on a processing throughput of 2.2 Mtpa1
. The
subsequent FEED study has identified a throughput increase to 2.5 Mtpa based on further assessment of ore
sources and the capability of existing crushing and grinding infrastructure at BSPH. This uplift could
meaningfully enhance the Project’s production capacity subject to further technical and economic studies and
supports the Company’s target of becoming a 100koz Au per annum producer.
Capital Cost
The capital cost implications of the throughput increase are currently being assessed as part of the ongoing
FEED review process. An update will be provided to the market in due course, including any revised capital
estimates and the impact on the Project's mine plan.
The Company is reviewing all capital cost items to identify potential to reduce costs, defer expenditure beyond
first gold production and/or enter separate financing options for certain capital items.
Site Survey and Digital Modelling
A comprehensive Light Detection and Ranging (LiDAR) survey of the Black Swan site has been completed.
The resulting point-cloud data has been used to create an accurate as-built digital representation of the existing
brownfield infrastructure. This significantly de-risks detailed engineering design and reduces the potential for
clashes between new and existing infrastructure.
ROM Pad Design
Maritana has completed the design of an enlarged Run-of-Mine (ROM) pad. The expanded design
accommodates ore delivery from quad side-tipping road trains and provides significantly increased stockpiling
capacity to support ore blending and optimise mill feed.
Approvals and Permitting
The Company is progressing works under existing approvals granted through mining leases and the previous
feasibility study completed during 2022 by Poseidon Nickel Limited.
Outside existing approvals, regulatory approvals required to support construction of new areas of the
processing facilities and infrastructure continue to progress. Works approvals, Mine Development and Closure
1
Refer to ASX Announcement 17 February 2026 “Studies Support Standalone Development in WA Goldfields”.
maritanaminerals.com.au Page | 3
Proposals (MDCPs), and native vegetation clearing permits have been lodged and are advancing through
assessment for activities.
Owner’s Engineer
Zeal Engineering has been appointed as Owner’s Engineer for the project. Zeal is a Western Australian-based
firm with extensive experience developing greenfield and brownfield mining projects. This appointment
strengthens project delivery and technical oversight through the construction phase.
Site Mobilisation
Site activity has ramped up significantly with the appointment of two Site Senior Executives (SSEs) and a
Occupational, Health & Safety (OHS) Manager. Site preparation works are underway, including clean-up
activities and removal of legacy equipment. Preparations for the removal of the Semi-Autogenous Grinding
(SAG) mill for refurbishment or potential replacement are advancing, with the lift scheduled for June 2026.
Accommodation
The accommodation strategy has been reviewed, with suitable options identified to support the hub-and-spoke
model. Design of a permanent 60-room camp at the BSPH is underway. A temporary camp will support
construction until the permanent facility is operational, with clearing and earthworks for the temporary camp
underway.
Concurrently, Maritana is acquiring a property in central Kalgoorlie with existing development approval for
approximately 50 rooms. Settlement is expected in the June 2026 quarter. This camp will support mining
operations at sites proximal to Kalgoorlie, reducing travel times. Hotel accommodation in Kalgoorlie has been
secured in the interim for drilling and operational readiness activities.
Power
The BSPH is supported by sufficient grid power capacity. Western Power has commenced project studies for
grid connection, with approvals expected in the coming quarter. The diesel backup power station design has
been completed and right-sized to provide appropriate redundancy and operational resilience.
Water Supply
Maritana has engaged Western Groundwater and Flow Water Services to undertake water studies and support
the refurbishment and construction of the project’s bore fields.
Drilling Programs
Sterilisation and geotechnical drilling has commenced across the new infrastructure areas, including the
Carbon-in-Leach (CIL) circuit, power station and tailings storage facility, to support detailed design and final
siting.
Mining Operational Readiness
Maritana has appointed an experienced and highly credentialled MineBuild Global to oversee the
establishment and restart of the Boorara Open Pit, Coote and Crake Open Pits, and the development of the
Cannon underground mine. These operations represent the first three key ore sources for the BSPH.
Contract tendering for Open Pit, Underground and Haulage contracts has commenced, with awards targeted
for late H2 2026, to support commencement of mining operations during early 2027. Key technical studies for
mine readiness at these initial operations have been completed, while technical studies on the Burbanks Open
Pit and Underground are currently underway.
maritanaminerals.com.au Page | 4
Next Steps
Maritana is focused on the following key activities as the project advances toward construction and initial
mining operations:
• EPC Contract and FID - finalising the EPC and reimbursable contract arrangements with GRES,
including completion of the capital cost review and ongoing optimisation work.
• Approvals - progressing the lodged regulatory approvals (works approvals, MDCPs and clearing
permits) through to grant.
• Mill Refurbishment - completing removal of the SAG mill and confirming the refurbishment or
replacement pathway.
• Accommodation - advancing accommodation construction works, site earthworks and ongoing site
preparation.
• Water Supply - finalising the project water strategy with Western Groundwater and Flow Water
Services.
• Mill Construction and Commissioning - progressing toward full construction commencement,
targeted for ore commissioning H1 FY28.
• Mine Operations - advancing mining operational readiness, including contract awards for Open Pit,
Underground and Haulage services targeted for late 2026.
Authorised for release by the Board of Directors.
For further information, please contact:
Grant Haywood Michael Vaughan
Managing Director and CEO Investor and Media Relations – Fivemark
grant.haywood@maritanaminerals.com.au michael.vaughan@fivemark.com.au
+61 8 9386 9534 +61 422 602 720
JOIN MARITANA MINERALS INTERACTIVE HUB
Visit https://maritanaminerals.com.au/auth/signup for
Maritana Minerals’ Interactive InvestorHub
MARITANA MINERALS
Email: info@maritanaminerals.com.au
maritanaminerals.com.au Page | 5
Forward Looking and Cautionary Statements
Some statements in this report regarding estimates or future events are forward looking statements. They
include indications of, and guidance on, future earnings, cash flow, costs and financial performance. Forward
looking statements include, but are not limited to, statements preceded by words such as “planned”,
“expected”, “projected”, “estimated”, “may”, “scheduled”, “intends”, “anticipates”, “believes”, “potential”, “could”,
“nominal”, “conceptual” and similar expressions. Forward looking statements, opinions and estimates included
in this announcement are based on assumptions and contingencies which are subject to change without notice,
as are statements about market and industry trends, which are based on interpretations of current market
conditions. Forward looking statements are provided as a general guide only and should not be relied on as a
guarantee of future performance. Forward looking statements may be affected by a range of variables that
could cause actual results to differ from estimated results and may cause the Company’s actual performance
and financial results in future periods to materially differ from any projections of future performance or results
expressed or implied by such forward looking statements. These risks and uncertainties include but are not
limited to liabilities inherent in mine development and production, geological, mining and processing technical
problems, the inability to obtain any additional mine licenses, permits and other regulatory approvals required
in connection with mining and third party processing operations, competition for among other things, capital,
acquisition of reserves, undeveloped lands and skilled personnel, incorrect assessments of the value of
acquisitions, changes in commodity prices and exchange rate, currency and interest fluctuations, various
events which could disrupt operations and/or the transportation of mineral products, including labour stoppages
and severe weather conditions, the demand for and availability of transportation services, the ability to secure
adequate financing and management’s ability to anticipate and manage the foregoing factors and risks. There
can be no assurance that forward looking statements will prove to be correct.
Statements regarding plans with respect to the Company’s mineral properties may contain forward looking
statements in relation to future matters that can only be made where the Company has a reasonable basis for
making those statements.
This announcement has been prepared in compliance with the JORC Code (2012) and the current ASX Listing
Rules.
The Company believes that it has a reasonable basis for making the forward-looking statements in the
announcement, including with respect to any production targets and financial estimates, based on the
information contained in this and previous ASX announcements.
Cautionary statement
Statements in this report relating to the Scoping Studies were originally released to the ASX on 17 February
2026 and are preliminary in nature. The Scoping Studies include Indicated and Inferred Mineral Resources
and are based on low-level technical and economic assessments, which are insufficient to support estimation
of Ore Reserves. There is no certainty that the study outcomes, including production targets and financial
assumptions, will be realised. All material assumptions and technical parameters underpinning the Scoping
Study production targets and financial information continue to apply and have not materially changed since
that announcement.
Aspirational Statement
The Company’s vision to be a ~100kozpa producer are aspirational statements (and not production targets)
and the Company does not have reasonable grounds to believe this can be achieved. These statements are
of an aspiration nature as the vision to be a ~100kozpa producer is dependent on several factors including the
exploration success, ore reserves and mineral resources definition, feasibility studies and development of an
extended mine plan.
maritanaminerals.com.au Page | 6
Production Targets
This Announcement contains production targets underpinned by 17% Inferred and 73% Measured and
Indicated Mineral Resources as detailed in the ASX Announcement "ASX Announcement “Studies Support
Standalone Gold Development in WA Goldfields’” dated 17 February 2026. There is a low level of geological
confidence associated with Inferred Mineral Resources and there is no certainty that further exploration work
will result in the determination of Indicated Mineral Resources or that the production target itself will be realised.
The stated production targets are based on the Company's current expectations of future results or events and
should not be solely relied upon by investors when making investment decisions. Further evaluation work and
appropriate studies are required to establish sufficient confidence that targets can be achieved. The Company
confirms that it is not aware of any new information or data that materially affects the information included in
the ASX announcements relating to the Company’s published production targets. All material assumptions and
technical parameters underpinning the production targets or forecast financial information derived from
production targets (as applicable) in the relevant ASX announcement continue to apply and have not materially
changed.