ASX ANNOUNCEMENT
13 March 2026
BOORARA MINED ORE STOCKPILES SUPPORT RAMP UP OF
BLACK SWAN PROCESSING HUB
Horizon Minerals Limited (ASX: HRZ) (“Horizon” or “the Company”) is pleased to provide an update on the
Boorara (“Boorara”) Gold Project.
• The current phase of mining was completed at Horizon’s Boorara Project in December 2025.
• Effective 11 February 2026, the Ore Purchase Agreement with the Paddington Gold Mine has been
mutually terminated.
• Significant gold ore stockpiles of 460,000t (14.2koz Au) remain in situ at the Boorara Project.
• The stockpiled material will be utilised as a primary source of ore for the commissioning of the Black
Swan Processing Hub in mid-2027.
• Utilising the stockpiled ore de-risks the mill startup providing a consistent supply of ore during this
critical milestone stage.
• Pre-production planning and operational readiness activities have commenced at Boorara to facilitate
a seamless re-start of the next phase of production activity early in 2027.
• Long lead items ordered to fast track the gold conversion of the Black Swan Processing Hub.
Managing Director and CEO Mr Grant Haywood commented:
“With the mutual resolution of the haulage contract for the remaining Boorara ore, Horizon Minerals will utilise
the 14.2koz Au stockpile as the initial ore source for the commissioning of the Black Swan Processing Hub in
mid-2027.
To further de-risk the startup we have already begun planning and preparation work at Boorara so the next
phase of mining can restart smoothly early in 2027.
Boorara remains a key part of our plan, and we remain on track to become the next standalone mid-tier gold
producer in the Western Australian Goldfields”.
Authorised for release by the Board of Directors.
For further information, please contact:
Grant Haywood Michael Vaughan
Managing Director and CEO Investor and Media Relations – Fivemark
grant.haywood@horizonminerals.com.au michael.vaughan@fivemark.com.au
+61 8 9386 9534 +61 422 602 720
horizonminerals.com.au Page | 2
JOIN HORIZON MINERALS INTERACTIVE HUB
Visit https://investors.horizonminerals.com.au/auth/signup for
Horizon Minerals’ Interactive InvestorHub
Horizon Minerals
Email: info@horizonminerals.com.au
Forward Looking and Cautionary Statements
Some statements in this report regarding estimates or future events are forward looking statements. They
include indications of, and guidance on, future earnings, cash flow, costs and financial performance. Forward
looking statements include, but are not limited to, statements preceded by words such as “planned”,
“expected”, “projected”, “estimated”, “may”, “scheduled”, “intends”, “anticipates”, “believes”, “potential”, “could”,
“nominal”, “conceptual” and similar expressions. Forward looking statements, opinions and estimates included
in this announcement are based on assumptions and contingencies which are subject to change without notice,
as are statements about market and industry trends, which are based on interpretations of current market
conditions. Forward looking statements are provided as a general guide only and should not be relied on as a
guarantee of future performance. Forward looking statements may be affected by a range of variables that
could cause actual results to differ from estimated results, and may cause the Company’s actual performance
and financial results in future periods to materially differ from any projections of future performance or results
expressed or implied by such forward looking statements. These risks and uncertainties include but are not
limited to liabilities inherent in mine development and production, geological, mining and processing technical
problems, the inability to obtain any additional mine licenses, permits and other regulatory approvals required
in connection with mining and third party processing operations, competition for among other things, capital,
acquisition of reserves, undeveloped lands and skilled personnel, incorrect assessments of the value of
acquisitions, changes in commodity prices and exchange rate, currency and interest fluctuations, various
events which could disrupt operations and/or the transportation of mineral products, including labour stoppages
and severe weather conditions, the demand for and availability of transportation services, the ability to secure
adequate financing and management’s ability to anticipate and manage the foregoing factors and risks. There
can be no assurance that forward looking statements will prove to be correct.
Statements regarding plans with respect to the Company’s mineral properties may contain forward looking
statements in relation to future matters that can only be made where the Company has a reasonable basis for
making those statements.
This announcement has been prepared in compliance with the JORC Code (2012) and the current ASX Listing
Rules.
The Company believes that it has a reasonable basis for making the forward looking statements in the
announcement, including with respect to any production targets and financial estimates, based on the
information contained in this and previous ASX announcements.
Share your feedback
Discover