Mining Americas Forum Presentation
Released
Released
Announcement PDF
The Western
Australian
Goldfields Next
Standalone Gold
Producer
Mining Americas Forum
Investor Presentation
28 September 2026
Important disclaimers
Nature of Document
This Presentation is provided on the basis that neither the Company nor its respective officers, shareholders,
related bodies, corporate, partners, affiliates, employees, representatives or advisers, make any
representation or warranty (express or implied) as to the accuracy, reliability, relevance or completeness of the
material it contains. Nothing contained in the Presentation is, or may be relied upon, as a promise,
representation or warranty, whether as to the past or the future, and the Company hereby excludes all
warranties that can be excluded by law.
The Presentation
The presentation contains ‘forward-looking statements’. By their nature, forward-looking statements involve
known and unknown risks, uncertainties and other factors because they relate to events and depend on
circumstances that may or may not occur in the future, and assumptions which may or may not prove to be
correct (and may be beyond the Company’s ability to control or predict), any (or all) of which may cause the
actual results or performance of the Company to be materially different from the results or performance
expressed or implied by such forward-looking statements.
No representation is made that any forward-looking statement will come to pass, that any forecast result will
be achieved, or that any assumption on which a forward-looking statement is based is reasonable. Forward-
looking statements are made as at the date of this Presentation, and the Company disclaims any obligation or
undertaking to release any update of, or revision to, any forward-looking statement contained in this
Presentation.
Summary Information
The material contained in this Presentation is a summary and for information purposes only. The information in
this Presentation is general in nature and does not purport to be accurate nor complete, nor does it contain all
of the information that an investor may require in evaluating a possible investment in the Company, nor does it
contain all the information which would be required in a disclosure document or prospectus prepared in
accordance with the requirements of the Corporations Act 2001 (Cth) (Corporations Act). It has been
prepared by the Company with due care but no representation or warranty, express or implied, is provided in
relation to the accuracy, reliability, fairness or completeness of the information, opinions or conclusions in this
Presentation by the Company or any other party involved in its preparation. Reliance should not be placed on
information or opinions contained in this Presentation and, the Company does not have any obligation to
finalise, correct or update the content of this Presentation. Certain data used in this Presentation may have
been obtained from research, surveys or studies conducted by third parties, including industry or general
publications.
To the maximum extent permitted by law, the Company is not responsible for updating, nor undertakes to
update, this Presentation. It should be read in conjunction with the Company’s other periodic and continuous
disclosure announcements lodged with the ASX, which are available at
www.maritanaminerals.com.au/announcements/.
Not an offer
The information contained in the Presentation is for information purposes only. The Presentation does not
comprise a prospectus, product disclosure statement or other offering document under Australian law (and will
not be lodged with the Australian Securities and Investments Commission) or any other law. The Presentation
also does not constitute or form part of any invitation, offer for sale or subscription or any solicitation for any
offer to buy or subscribe for any securities nor shall they or any part of them form the basis of or be relied
upon in connection therewith or act as any inducement to enter into any contract or commitment with respect
to securities. In particular, the Presentation does not constitute an offer to sell or a solicitation to buy, securities
in the United States of America.
Not investment advice
The information contained in the Presentation is not investment or financial product advice and is not intended
to be used as the basis for making an investment decision. Please note that, in providing the Presentation, the
Company has not considered the objectives, financial position or needs of any particular recipient. The
information contained in the Presentation is not a substitute for detailed investigation or analysis of any
particular issue and does not purport to be all of the information that a person would need to make an
assessment of the Company or its assets. Current and potential investors should seek independent advice
before making any investment decisions in regard to the Company or its activities.
JORC Code
It is a requirement of the ASX Listing Rules that the reporting of ore reserves and mineral resources in
Australia comply with the Joint Ore Reserves Committee’s Australasian Code for Reporting of Mineral
Resources and Ore Reserves (JORC Code). Investors outside Australia should note that while Ore Reserve
and Mineral Resource estimates of the Company in this presentation comply with the JORC Code (such
JORC Code-compliant ore reserves and mineral resources being "Ore Reserves" and "Mineral Resources"
respectively), they may not comply with the relevant guidelines in other countries and, in particular, do not
comply with (i) National Instrument 43-101 (Standards of Disclosure for Mineral Projects) of the Canadian
Securities Administrators (the "Canadian NI 43-101 Standards"); or (ii) Item 1300 of Regulation S-K, which
governs disclosures of mineral reserves in registration statements filed with the US Securities and Exchange
Commission. Information contained in this document describing mineral deposits may not be comparable to
similar information made public by companies subject to the reporting and disclosure requirements of
Canadian or US securities laws. You should not assume that quantities reported as “resources” will be
converted to reserves under the JORC Code or any other reporting regime or that the Company will be able to
legally and economically extract them.
Authorised for release to the ASX by the Board of Directors of Maritana Minerals Ltd.
2
Important disclaimers
Forward Looking and Cautionary Statement
As noted above, some statements in this Presentation regarding estimates or future events are forward looking statements.
They include indications of, and guidance on, future earnings, cash flow, costs and financial performance. Forward looking statements include, but are not limited to, statements preceded by words such as “planned”, “expected”, “projected”, “estimated”,
“may”, “scheduled”, “intends”, “anticipates”, “believes”, “potential”, “could”, “nominal”, “conceptual” and similar expressions.
Forward looking statements, opinions and estimates included in this Presentation are based on assumptions and contingencies which are subject to change without notice, as are statements about market and industry trends, which are based on
interpretations of current market conditions. Forward looking statements are provided as a general guide only and should not be relied on as a guarantee of future performance. Forward looking statements may be affected by a range of variables that could
cause actual results to differ from estimated results, and may cause the Company’s actual performance and financial results in future periods to materially differ from any projections of future performance or results expressed or implied by such forward
looking statements. These risks and uncertainties include but are not limited to liabilities inherent in mine development and production, geological, mining and processing technical problems, the inability to obtain any additional mine licenses, permits and
other regulatory approvals required in connection with mining and third party processing operations, competition for among other things, capital, acquisition of reserves, undeveloped lands and skilled personnel, incorrect assessments of the value of
acquisitions, changes in commodity prices and exchange rate, currency and interest fluctuations, various events which could disrupt operations and/or the transportation of mineral products, including labour stoppages and severe weather conditions, the
demand for and availability of transportation services, the ability to secure adequate financing and management’s ability to anticipate and manage the foregoing factors and risks. There can be no assurance that forward looking statements will prove to be
correct.
Statements regarding plans with respect to the Company’s mineral properties may contain forward looking statements in relation to future matters that can only be made where the Company has a reasonable basis for making those statements. The
forward looking statements in this Presentation are based on current expectations, estimates, forecasts and projections about the Company and the industry in which it operates. They do, however, relate to future matters and are subject to various inherent
risks and uncertainties. Actual events or results may differ materially from the events or results expressed or implied by any forward looking statements. The past performance of the Company is no guarantee of future performance. You are cautioned not to
place undue reliance on any forward looking statement. The forward looking statements in this Presentation reflect views held only as at the date of this Presentation.
None of Maritana Minerals Limited or its directors, officers, employees, agents or contractors makes any representation or warranty (either expressed or implied) as to the accuracy or likelihood of fulfilment of any future looking statement, or any events or
results expressed or implied in any forward looking statement, except to the extent required by law. The Company believes that it has a reasonable basis for making the forward looking statements in the Presentation, including with respect to any
production targets and financial estimates, based on the information contained in this and previous ASX announcements.
Aspirational Statement
The Company’s vision to be a ~100kozpa producer in this presentation are aspirational statements (and not a production targets) and the Company does not have reasonable grounds to believe this can be achieved. These statements are of an aspiration
nature as the vision to be a ~100kozpa producer is dependent on several factors including the exploration success, ore reserves and mineral resources definition, feasibility studies and development of an extended mine plan.
Mineral Resources and Ore Reserves
This Presentation contains estimates of the Company's Mineral Resources and Ore Reserves. Refer to Slide 24 to 26. The information in this Presentation that relates to the Company’s Mineral Resources and Ore Reserves has been extracted from the
Company's previous ASX announcements including: 1. ASX Announcement “Gold Mineral Resources Update” dated 13 February 2026 and 2. ASX announcement “Gold Ore Reserve Update” dated 17 February 2026. Copies of these announcements are
available at www .asx.com.au or maritanaminerals.com.au/announcements. The Company confirms that it is not aware of any new information or data that materially affects the information included in those announcements and, in relation to the estimates
of the Company’s Mineral Resources and Ore Reserves, that all material assumptions and technical parameters underpinning the estimates in the announcements continue to apply and have not materially changed. The Company confirms that the form
and context in which the Competent Person's findings are presented have not been materially modified from those announcements.
Production Targets
This Presentation contains production targets and forecast financial information derived from those production targets (including in respect of all-in sustaining costs and capital costs). The information in this Presentation is underpinned by 17% Inferred and
73% Measured and Indicated Mineral Resources as detailed in the ASX Announcement "ASX Announcement “Studies Support Standalone Gold Development in WA Goldfields’” dated 17 February 2026. There is a low level of geological confidence
associated with Inferred Mineral Resources and there is no certainty that further exploration work will result in the determination of Indicated Mineral Resources or that the production target itself will be realised. The stated production targets are based on
the Company's current expectations of future results or events and should not be solely relied upon by investors when making investment decisions. Further evaluation work and appropriate studies are required to establish sufficient confidence that targets
can be achieved. The Company confirms that it is not aware of any new information or data that materially affects the information included in the ASX announcements relating to the Company’s published production targets. All material assumptions and
technical parameters underpinning the production targets or forecast financial information derived from production targets (as applicable) in the relevant ASX announcement continue to apply and have not materially changed.
3
Investment proposition
Well funded with $229m cash4 - creating +300 full time jobs in the
Western Australian goldfields region
An attractively priced West Australian gold
developer with near-term growth
Esperance
Albany
Geraldton
Perth
Black Swan Processing Hub
2.5Mtpa (Early Works Underway) with
pathway to refurbish / convert to gold
processing
Mineral Resource Estimate1
2.15Moz: 41.8Mt @ 1.6g/t Au
Regional Landholding
+1,300km²
Projects
20.2Moz Ag 104kt Zn
Carnarvon
Strategy to produce +100koz p.a. over current 5-
year LOM1 from the refurbished Black Swan
Processing Hub – increased to 2.5Mtpa2
Targeting start of commencement of plant construction in
Q3 CY2026 and first gold production starting in H2 CY2027
2.15Moz3 gold MRE with major drilling program underway –
definition & extension of mineable ounces & testing new regional targets
Kalgoorlie
1. Refer ASX Announcement “Studies Support Standalone Gold Development in WA Goldfields’” dated 17 February 2026
2. Refer ASX Announcement “BSPH Project Update Increases Capacity to 2.5MT per annum” dated 9 June 2026
3. Refer ASX Announcements “Gold Mineral Resources & Reserves Update” dated 21 August 2026 and “Rose Hill Mineral Resource and Maiden Ore Reserve Update” dated 31 August 2026 and
“Burbanks Resource Model Update” dated 11 September 2026
4. Refer ASX Announcement “Quarterly Activities Report 30 June 2026” dated 22 June 2026
4
Maritana Minerals – at a glance
An attractively priced West Australian gold developer with near-term growth potential
Directors and Management
Institutions
Golden Crane/Add New Energy
HNW, Retail and Others
Capital structure Units Current
Share price A$/sh 0.77(1)
Ordinary shares M 372.9(1)
Options and performance rights M 4.7(1)
Market capitalisation A$M 280
Cash and cash equivalents A$M 229(2)
Debt A$M Nil(2)
EV A$M 51
1. At 25 September 2026
2. At 30 June 2026. Excludes listed investments with a value of ~$6.5M
Indicative Share Register
Research Coverage
Adjusted to match share structure and volume post 15-to-1 capital consolidation effective 9 December 2025
Share Trading & Price
5
Maritana Minerals – Board and Management
Key experience in operations and value delivery
Ashok Parekh
Non-Executive Chair
Grant Haywood
Managing Director
Rob Waugh
Non-Executive Director
Warren Hallam
Non-Executive Director
Christian Price
GM Corporate
Development
Brendan Shalders
CFO & Joint CoSec
Stephen Guy
Chief Geologist
Adrianna Skok-Muir
Group Mining Engineer
Isabel Macchia
Company Secretary
6
Doug Flanagan
Project Director
Elizabeth Jones
Chief Operating
Officer
Project portfolio
• Large +1,300km2 land package within 100km of
Kalgoorlie
• 2.15Moz Group Mineral Resource1 (41.8Mt @
1.6g/t Au)
• Majority of known deposits remain open with
potential for resource growth
• 2.5Mtpa Black Swan process plant being
refurbished for gold production
• Hub-and-spoke operating model
• Additional multi-commodity optionality from the
high-grade Nimbus Silver-Zinc deposit (20.2Moz
Ag, 104kt Zn, and 77koz Au) 44km from Black
Swan
Strategically constructed gold portfolio centered around major geological structures and infrastructure
1. Refer ASX Announcement “Gold Mineral Resources & Reserves Update” dated 21 August 2026 and “Burbanks Resource Model
Update” dated 11 September 2026
2. Refer ASX Announcement “BSPH Project Update Increases Capacity to 2.5MT per annum” dated 9 June 2026 7
Hub and Spoke Model producing 546koz in 5 years
8
Multiple ore sources feeding into the Black Swan Processing Hub1
Years 1 – 4 106.6koz
BOORARA S/P & OPEN PIT
Years 3 – 5 212.1koz
OTHER OPEN PIT AND U/G
Years 2 – 5 51.5koz
COOTE AND CRAKE OPEN PITS
Years 2 – 5 128.8koz
BURBANKS OPEN PIT
CANNON AND PENNYS U/G
64km 110km
48 - 80km 42 - 110km
90km
BLACK SWAN PROCESSING HUB
Years 1 – 4 47.4koz
1. Refer ASX Announcement “Studies Support Standalone Gold Development in WA Goldfields’” dated 17 February 2026
Black Swan Processing Hub1
• ~50km northeast of Kalgoorlie
• Comminution circuit suitable for gold processing
after refurbishment and addition of a carbon in
leach (CIL) circuit
• Updated FEED Study1 fully utilises existing
2.5Mtpa processing capacity
• Estimated replacement value of +A$250M
• Plant construction risk reduced with key permits
and approvals in place
• Provides a platform for potential regional
consolidation and unlocking stranded assets
• Early works underway2
• Upcoming Milestones - Final approvals, EPC
award and construction commencement
Facilitates hub and spoke operating model
1. Refer ASX Announcement “BSPH Project Update Increases Capacity to 2.5MT per annum” dated 9 June 2026
2. Refer ASX Announcement “Early Works Commence at Black Swan Processing Hub” dated 20 June 2026
PROCESSING
9
Black Swan Processing Hub
Early Works and Demolition – Ongoing
10
Black Swan Processing Hub
Exiting Sulphide Floatation Circuit to be retained for potential future ore processing
11
Black Swan Processing Hub
Refurbishment Phase – Underway Early Works1
12
1. Refer ASX Announcement “Early Works Commence at Black Swan Processing Hub” dated 20 June 2026
Black Swan Processing Hub
Construction Phase – Early Works1 Underway – Long lead items ordered
13
1. Refer ASX Announcement “Early Works Commence at Black Swan Processing Hub” dated 20 June 2026
Black Swan Processing Hub
Final Plant Arrangement – Gold CIL processing circuit with floatation ore processing optionality
14
Black Swan Processing Hub
NPI and Approvals – Progress Update1
15
• Early Works2 – $25M Early works
contract underway with GRES
Approvals – Mining Development
and Closure Proposal (MDCP)
approved by DMPE late July 2026
and Works Approval for the new
Carbon-in-Leach also approved in
early August 2026
• Accommodation Update – 57 room
fly camp complete
• Demolition – Contract awarded to
Focus Demolition and underway
• Site establishment – Clearing
underway
• Process water – A $2.1M bore fields
refurbishment and upgrade program
of BSPH bores is underway
1. Refer ASX Announcement “BSBP Approvals & Non-Process Infrastructure Advancing” dated 12 August 2026
2. Refer ASX “Early Works Commence at Black Swan Processing Hub” dated 20 July 2026
Production ramp-up
• Boorara stockpile 460kt (14.2koz) – a de-
risked startup
• Baseload open pit feed with supplementary
high grade underground sources
• Early mine plan underpinned by high
confidence Mineral Resources and Ore
Reserves – 60,000m of drilling underway1
Cash flow and future baseload open pit feed
PRODUCTION
16
1. Refer ASX Announcement “Maritana Commences Resources Conversion Drilling” dated 25 June 2026
Boorara Project1
Overview – Initial baseload feed for the Black Swan Processing Hub
17
1. Refer ASX Announcement “Studies Support Standalone Gold Development in WA Goldfields’” dated 17 February 2026
Cannon Project1
Overview – Supplementary underground high grade ore feed
18
1. Refer ASX Announcement “Studies Support Standalone Gold Development in WA Goldfields’” dated 17 February 2026
Burbanks Project1
Overview – Second open pit base load feed
19
1. Refer ASX Announcement “Studies Support Standalone Gold Development in WA Goldfields’” dated 17 February 2026
Burbanks MRE Update1
Phase 1 drilling increases resource by 62% to +750koz
20
1. Refer ASX Announcement “High-Grade Burbanks Deposit Increases 62% to 750koz’” dated 11 September 2026
Black Swan exploration potential
• Previous exploration largely targeting nickel
sulphide mineralisation – only 5% of drill assays
have tested for gold
• Target areas adjacent to the Mt Monger fault
which is associated with several regional gold
mining operations
• Gold prospectivity of the Black Swan area
demonstrated with prior drill intersections grading
up to 6.41g/t Au1
• Numerous gold nuggets located1
• Identified a new 6.5km-long gold trend around
Black Swan
• Initial aircore +5,000m drill program
completed August 20262
• Assays due in October 2026
Untested gold anomalies emerging adjacent to the process plant infrastructure
1. Refer ASX announcement (ASX:POS) "Gold Potential Builds at Black Swan" dated 24 September 2024
2. Refer ASX announcement (ASX:MRT) “Commencement of Drilling at the Wilsons Prospect" dated 7 August 2026
21
Key Milestones and Timing
22
Pathway to gold production from Black Swan Processing Hub
Area Work Streams and Deliverables
CY 2026 CY 2027
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
Corporate
Lake Johnston Sale and Phillips Find Mining Cash
Equity Raise - A$175M + SPP
Development
& Growth
Burbanks MRE Update
Resource Extension & Grade Control drilling
Mining &
Operations
Open Pit Boorara Ore Stockpiling & Mining
Underground Mobilisation & Development
Underground High-Grade Ore Production
Black Swan
Processing
Hub
Black Swan Plant 2.2Mtpa Studies Complete
FEED Increase to 2.5Mtpa – Early Works Commenced
Final Approvals
EPC Contract Award
Black Swan Accommodation Construction
Black Swan Plant Construction
Black Swan Plant Commissioning
Black Swan Plant Gold Production
Martiana Minerals - An Emerging Standalone Gold Producer
Drilling now
extending and
enhancing a
robust initial five
year mine plan
Combination of
2.15Moz of Mineral
Resource1 and
processing
infrastructure
Well funded
pathway to
standalone gold
production by H2
CY2027
Highly experienced
Board and
Management with
strong Goldfields
regional expertise
1. Refer ASX Announcement “Gold Mineral Resources & Reserves Update” dated 21 August 2026 and “Burbanks Resource Model Update” dated 11 September 2026 23
Contact Us
Grant Haywood
Managing Director and CEO
+61 (08) 9386 9534
info@maritanaminerals.com.au
maritanaminerals.com.au
PO Box 1064 West Perth WA 6872
Appendix
Mineral Resource1 Estimate
1. Refer ASX Announcements “Gold Mineral Resources & Reserves Update” dated 21 August 2026, “Rose Hill Mineral Resource and Maiden Ore Reserve Update” dated 31 August 2026 and “High-
Grade Burbanks Deposit Increases 62% to 750koz” dated 11 September 2026
Gold projects
.
Project Measured Indicated Inferred Total
kt Au (g/t) koz kt Au (g/t) koz kt Au (g/t) koz kt Au (g/t) koz
Baden Powell 596 1.20 23 596 1.20 23
Boorara 498 1.12 18 6,231 1.27 254 2,547 1.26 103 9,276 1.26 375
Boorara SP 463 0.95 14 463 0.95 14
Burbanks OP 3,329 1.49 160 7,306 1.43 336 10,636 1.45 496
Burbanks UG 357 3.04 35 2,710 2.57 224 3,067 2.63 259
Cannon 185 4.80 29 47 2.28 3 232 4.29 32
Capricorn 659 1.20 25 659 1.20 25
Coote 2,321 0.86 64 2,321 0.86 64
Crake 1,699 1.29 70 123 1.08 4 1,822 1.28 75
Golden Ridge 476 1.82 28 52 1.71 3 527 1.81 31
Golden Ridge North 1,511 0.86 42 1,021 1.14 37 2,532 0.97 79
Gordons Dam 693 1.24 28 693 1.24 28
Jacques/Peyes 996 2.54 81 856 1.85 51 1,852 2.22 132
Monument 919 1.11 33 919 1.11 33
Phillips Find OP 325 2.41 25 180 2.11 12 505 2.30 37
Phillips Find UG 3 2.27 0.2 3 2.27 0.2
Rosehill (OP) 194 1.96 12 92 2.05 6 287 1.99 18
Rosehill (UG) 330 4.46 47 194 4.53 28 524 4.49 76
Pinner 64 1.02 2 267 1.25 11 330 1.21 13
Kalpini 1,768 2.04 116 591 1.72 33 2,359 1.96 149
Pennys Find 305 5.19 51 123 3.02 12 429 4.57 63
Teal 1,009 1.96 64 801 2.50 64 1,811 2.20 128
Grand Total 1,156 1.20 44 18,679 1.68 1,010 22,011 1.55 1,096 41,846 1.60 2,150
Tonnages are dry metric tonnes. Minor discrepancies may occur due to rounding. Burbanks OP and UG per the Burbanks Resource Model Update (September 2026), reported at 0.5g/t Au cut-off above
180mRL and 1.0g/t Au below; Burbanks OP includes Galaxias (265kt @ 1.14g/t Au for 10koz Inferred).
26
Ore Reserve1 Estimate
1. Refer ASX announcements “Gold Ore Reserve Update” dated 17 February 2026 and “Rose Hill Mineral Resource and Maiden Ore Reserve Update” dated 31 August 2026. Rose Hill UG cut-off 1.3 g/t
Au (AUD $4,500/oz gold price).
Gold projects
MARITANA MINERALS GOLD ORE RESERVE SUMMARY
Project Cutoff Proven Probable Total
Au ppm kt Au g/t Koz kt Au g/t Koz kt Au g/t Koz
Boorara 0.5 247 1.10 9.1 1,445 1.40 62.7 1,691 1.36 71.8
Cannon UG 1.0 135 4.10 17.7 135 4.10 17.7
Pennys Find UG 1.5 328 3.20 33.4 328 3.20 33.4
Kalpini 0.5 867 1.69 47.2 867 1.69 47.2
Crake 0.5 870 1.23 34.4 870 1.23 34.4
Rose Hill UG 1.3 70 2.14 4.7 350 2.37 26.8 420 2.34 31.6
TOTAL 316 1.33 13.7 3,994 1.75 221.9 4,310 1.72 235.6
27
Mineral Resource1 Estimate
1. Refer ASX Announcement “Group Mineral Resources Statement – Amended” dated 1 August 2024
Nimbus silver-zinc project
Nimbus All Lodes (bottom cuts 12 g/t Ag, 0.5% Zn, 0.3g/t Au)
Category Mt Ag (g/t) Au (g/t) Zn (%) Ag (Moz) Au (kt) Zn (kt)
Measured Resource 3.62 102 0.09 1.2 11.9 10 45
Indicated Resource 3.18 48 0.21 1.0 4.9 21 30
Inferred Resource 5.28 20 0.27 0.5 3.4 46 29
Total Resource 12.08 52 0.20 0.9 20.2 77 104
Nimbus high grade silver zinc resource (500g/t Ag bottom cut and 2,800g/t Ag top cut)
Category Mt Ag (g/t) Zn (%) Ag (Moz) Zn (kt)
Measured Resource - - - - -
Indicated Resource 0.17 762 12.8 4.2 22
Inferred Resource 0.09 797 13.0 2.2 11
Total Resource 0.26 774 12.8 6.4 33
28