BSBP Approvals & Non-Process Infrastructure Advancing
Released
Released
Announcement PDF
Maritana Minerals Limited | ABN 88 007 761 186 | maritanaminerals.com.au
PO Box 1064, West Perth WA 6872 | +61 8 9386 9534 | info@maritanaminerals.com.au
ASX: MRT
ASX ANNOUNCEMENT
12 August 2026
BLACK SWAN PROCESSING HUB – APPROVALS ADVANCE
AND NON-PROCESS INFRASTRUCTURE PROGESSING
Maritana Minerals Limited (ASX: MRT) (“Maritana” or “the Company”) is pleased to provide an update on
approvals and non-process infrastructure (NPI) workstreams for the Black Swan Processing Hub (“BSPH”).
Key regulatory submissions are now progressing through the assessment process with the Department of
Mines, Petroleum and Exploration (DMPE), while early NPI works across power, water, roads and
communications continue in parallel. These NPI works and approvals ensure the BSPH remains on track to
produce first gold production in H2 CY2027.
HIGHLIGHTS
• Site Establishment – Early site establishment works are advancing in parallel with the approvals and
NPI workstreams
• Approvals Pathway – Mining Development and Closure Proposal (MDCP) approved by DMPE late
July 2026 and Works Approval for the new Carbon-in-Leach also approved in early August 2026
• Clearing Permit – Application submitted and progressing to assessment
• Power Supply – Options assessment underway across grid, diesel, gas and hybrid renewable
solutions, with the BSPH having access to two existing grid connection lines
• Construction Water – A $1.3 million bore fields refurbishment and upgrade program of BSPH bores
is underway, bringing them back into service to supply construction water
• Potable & Process Water – Sites identified for expansion of the existing bore field to meet operational
water requirements
• Site Access & Security – Traffic Management, access and security detailed assessments and
planning underway
• Yarri Road – Initial assessments indicate the Yarri Road upgrade will not require bitumen sealing of
the 18km unsealed section to the BSPH, significantly reducing the cost of upgrade
• Communications – Various upgrades to site communications infrastructure are either underway or
being finalised
• Accommodation – First stage construction camp operational from 3 August 2026. Procurement
underway for the permanent 60 room camp, scalable to 120 rooms, expected to be operational from
January 2027
Managing Director and CEO Mr Grant Haywood commented:
“The MDCP approval for the BSPH, followed by DWER’s Works Approval, are key milestones that keep our
approvals pathway on track. With these approvals now in place, our Clearing Permit application is progressing
through the DMPE assessment against a 30-day target.”
“At the same time, we are methodically reducing the risks across the non-process infrastructure needed to
support construction and operations at the BSPH. The borefield upgrade is considered to be a practical near-
term early works investment, while our power supply study is focused on securing reliable, cost-effective power
in light of outages experienced by other operators in the region.”
maritanaminerals.com.au Page | 2
“With the key approvals granted, site establishment and water infrastructure works underway, and road and
communications requirements being less extensive than expected, the BSPH continues to gain momentum
toward development.”
Site Establishment
Site establishment works are progressing alongside the approvals and NPI workstreams, supporting BSPH’s
transition into a fully functioning construction site. Procurement of temporary power generation and self-bunded
fuel storage for early works is nearing completion. Administration facilities have been cleared, cleaned and
upgraded with new air conditioning and additional offices being allocated to the GR Engineering construction
team. Dry-hire tenders for the initial mobile equipment fleet have also been evaluated and awarded. Together,
these activities position the BSPH for an efficient start to the main construction program.
Approvals – Mining Development and Closure Proposal
On 27 July 2026 the Mining Development and Closure Proposal (MDCP) for the BSPH was approved by the
DMPE. The MDCP allows for works to commence on the existing processing facility, including demolition and
refurbishment. A further MDCP covering the tailings storage facility (TSF) is being prepared, with submission
scheduled for later in 2026.
Approvals – Works Approval
On 5 August 2026 the Department Water and Environment Regulation (DWER) approved the Works Approval.
Works approval allows for the commencement of construction of the Carbon in Leach (CIL) circuit, pending
the Clearing Permit approval.
Approvals - Clearing Permit
A Clearing Permit application has been lodged with DMPE targeting a 30-day assessment. This will facilitate
the commencement of clearing for the construction of the CIL circuit.
Power Supply
The BSPH has access to two power lines connecting to the grid. The Company is aware of issues other miners
in the region have experienced operating on the Eastern Goldfields Load Permissive Scheme (ELPS) scheme,
which can result in significant power outages. To ensure a secure and cost-effective supply, the Company has
engaged various consultants to assess power supply options including grid, gas and hybrid renewable
solutions. The various options and funding arrangements are under consideration.
The Company has identified short-term power supply options which can be installed at the BSPH in time for
the targeted first processing during 2H 2027, including rental of diesel fired power generation units.
Construction Water
The Company has engaged Flow Water Services (FWS) to complete borefield upgrades on Maritana leases
to the value of $1.3 million, which will support early works and BSPH development. This involves the supply
and installation of bore equipment covering pumps, piping, gensets and communications equipment.
Potable & Process Water
Nearby locations north of the site have been identified as potential potable water supply sources, while
locations south of the existing borefields have been identified by Ground Water Services as viable options to
increase process water supply. These locations are now under further investigation by Resource Potentials.
The additional bores are expected to support the BSPH’s operational water requirements.
maritanaminerals.com.au Page | 3
Site Access & Security
Planning for the permanent BSPH entrance and security facilities is progressing, including controlled site
access, gatehouse facilities and traffic management arrangements for construction and operational vehicles.
The design is being developed to provide safe separation and efficient movement of light vehicles, heavy
vehicles and contractor traffic as activity at the BSPH increases.
Yarri Road
Initial assessments indicate that upgrading the Yarri Road to support operations will not require bitumen sealing
of the 18km unsealed section to the BSPH, reducing the scope and cost of road works ahead of development.
Discussions are underway with the City of Kalgoorlie Boulder in reference to other road users and potential
contractors to optimise the upgrade solutions and minimise the risk of road closures during severe weather
events.
Communications
The ESN Group is reviewing site communications requirements as the BSPH progresses the design of an
integrated network to support the processing plant, administration facilities, accommodation village and
construction activities. The scope includes upgrades to existing microwave communications infrastructure, site
data networks, wireless connectivity and operational radio communications.
The proposed architecture is designed to provide reliable site-wide connectivity, with redundancy and future
operational requirements built into the design.
Figure 1 – BSPH – Non-Process Infrastructure Aerial Image
maritanaminerals.com.au Page | 4
Figure 2 – BSPH – Access roads and Accommodation Village
Accommodation Update
Mobilisation and installation of the construction camp is underway with delivering of accommodation units to
site ongoing (Figure 3). The first stage construction camp was operational from 3 of August 2026.
Figure 3 – BSHP Construction Camp Stage 1
maritanaminerals.com.au Page | 5
Procurement of modules for the permanent 60 room BSPH camp, scalable to 120 rooms, is progressing with
long lead items, such as the kitchen ordered and scheduled for delivery during November 2026. The Company
is engaging with the preferred construction provider, and the camp is expected to be operational from January
2027.
The combined construction and permanent camp accommodation supports the required manning for the plant
development schedule.
Authorised for release by the Board of Directors.
For further information, please contact:
Grant Haywood Michael Vaughan
Managing Director and CEO Investor and Media Relations – Fivemark
grant.haywood@maritanaminerals.com.au michael.vaughan@fivemark.com.au
+61 8 9386 9534 +61 422 602 720
JOIN MARITANA MINERALS INTERACTIVE HUB
Visit https://maritanaminerals.com.au/auth/signup for
Maritana Minerals’ Interactive InvestorHub
MARITANA MINERALS
Email: info@maritanaminerals.com.au
maritanaminerals.com.au Page | 6
Figure 4 - Maritana Minerals Regional Tenement Holding
maritanaminerals.com.au Page | 7
Forward Looking Statements
Some statements in this report regarding estimates or future events are forward looking statements. They
include indications of, and guidance on, future earnings, cash flow, costs and financial performance. Forward
looking statements include, but are not limited to, statements preceded by words such as “planned”,
“expected”, “projected”, “estimated”, “may”, “scheduled”, “intends”, “anticipates”, “believes”, “potential”, “could”,
“nominal”, “conceptual” and similar expressions. Forward looking statements, opinions and estimates included
in this announcement are based on assumptions and contingencies which are subject to change without notice,
as are statements about market and industry trends, which are based on interpretations of current market
conditions. Forward looking statements are provided as a general guide only and should not be relied on as a
guarantee of future performance. Forward looking statements may be affected by a range of variables that
could cause actual results to differ from estimated results and may cause the Company’s actual performance
and financial results in future periods to materially differ from any projections of future performance or results
expressed or implied by such forward looking statements. These risks and uncertainties include but are not
limited to liabilities inherent in mine development and production, geological, mining and processing technical
problems, the inability to obtain any additional mine licenses, permits and other regulatory approvals required
in connection with mining and third party processing operations, competition for among other things, capital,
acquisition of reserves, undeveloped lands and skilled personnel, incorrect assessments of the value of
acquisitions, changes in commodity prices and exchange rate, currency and interest fluctuations, various
events which could disrupt operations and/or the transportation of mineral products, including labour stoppages
and severe weather conditions, the demand for and availability of transportation services, the ability to secure
adequate financing and management’s ability to anticipate and manage the foregoing factors and risks. There
can be no assurance that forward looking statements will prove to be correct.
Statements regarding plans with respect to the Company’s mineral properties may contain forward looking
statements in relation to future matters that can only be made where the Company has a reasonable basis for
making those statements.
This announcement has been prepared in compliance with the JORC Code (2012) and the current ASX Listing
Rules.
The Company believes that it has a reasonable basis for making the forward-looking statements in the
announcement, including with respect to any production targets and financial estimates, based on the
information contained in this and previous ASX announcements.