Quarterly Activities Report 30 June 2023
Released
Released
Announcement PDF
ASX: HRZ
ASX ANNOUNCEMENT
26 JULY 2023
QUARTERLY ACTIVITIES REPORT FOR THE
PERIOD ENDED 30 JUNE 2023
HIGHLIGHTS
•
Horizon continues to progress its goal to become a gold producer from a sequence of
mine developments under a contract / JV model 1
•
First development is the proposed Cannon underground gold mine, with significant
milestones achieved during the quarter including: 2
•
o
Cannon project fully funded via drawdown of the tranche 2 Nebari loan facility of
US$3.0m
o
Cannon project fully approved, with Works Approval, discharge licence,
groundwater licence, Mining Proposal and Mine Closure Plan approved
Cannon Feasibility Study shows a positive economic return. 3
o
Reserves total 135kt @ 4.1g/t Au for 17,680oz for production of 15,900oz at 90%
recovery with milling allocation in place
o
$4.3m upfront capex with development from a portal within the exiting open pit,
and generates ~$10m cash at $2,600/oz gold price and AISC of $1,873/oz
•
Strike and depth extension drilling completed at Penny’s Find to confirm the newly
discovered lode system to the north, and current resource still open at depth 4
•
Exploration reconnaissance and geological review continued at the Pinner and Monument
gold prospects within the Greater Boorara – Cannon project area and at Lakewood
•
Horizon’s total Mineral Resource Estimate (MRE) stands at:
o
22.6Mt grading 1.71g/t Au for 1.24 million ounces at various cut-off grades 5
•
Successful Placement completed to advance Cannon and drill Penny’s Find 6
•
Cash at bank of A$5.8 million and listed investments totalling A$8.2 million
SEPTEMBER QUARTER ACTIVITIES 1
•
Advancing the high-grade Cannon underground mine scheduled for H2 CY2023
•
Release of resource updates for Penny’s Find, Golden Ridge, and Monument
•
Exploration and Infill program continuation at Cannon North, Monument and Pinner
(Cannon), Honeyeater and Kestrel (Binduli), Kanowna South and Penny’s Find
•
Continuing to pursue value accretive consolidation and divestment opportunities
See Forward Looking and Cautionary Statements on Page 37.2 As announced to the ASX on 14 June 2023. 3 As announced to the ASX
on 29 March 2022, see also Tables and confirmations on Page 35. 4 As announced to the ASX on 31 May 2023. 5 As announced to the
ASX on 28 September 2022, see also Tables and confirmations on Page 35. 6 As announced to the ASX on 30 March 2023.
1
163 Stirling Hwy
Nedlands WA 6009
PO Box 1104
Nedlands WA 6909
T: +61 8 9386 9534
E: info@horizonminerals.com.au
horizonminerals.com.au
ACN 007 761 186
ABN 88 007 761 186
ASX ANNOUNCEMENT
Horizon Minerals Limited (ASX: HRZ) (Horizon or the Company) is pleased to provide the June
2023 Quarterly Activities Report. Horizon is an exploration and production company within the
Kalgoorlie and Coolgardie regions of Western Australia (Figure 1).
A key focus for the Company is on near term production and exploration upside within our
1,100km2 tenement package with multiple drill rigs operating as part of the large-scale new
discovery and project generation exploration program. Horizon holds numerous multi commodity assets including listed investments in the world class 1.8Bt Richmond vanadium
project in northwest Queensland (Figure 16). 1
Figure 1: Horizon’s project locations, regional geology and surrounding infrastructure
Primary activities during the Quarter included growth drilling at Penny’s Find along strike and at
depth, and drill planning for resource programs at Monument and Pinner (Cannon), Kestrel and
Honeyeater (Binduli) and follow up at Penny’s Find. New discovery drilling programs were also
developed for Kanowna South and Lakewood. Exploration field work at the core Greater Boorara
– Cannon – Golden Ridge project area and Lakewood continued.
In addition, the Company has continued to advance the high-grade Cannon, Penny’s Find and
Rose Hill underground developments, statutory approval work, joint venture assessment and
review of further consolidation and divestment opportunities.
During the Quarter, funding and mining approval was received for the Cannon underground
development, with Penny’s Find already approved for potential sequential mining and production.
1
As announced to the ASX on 13 December 2022, see also Cautionary and Forward-Looking Statements on
Page 37.
Page 2 of 37
ASX ANNOUNCEMENT
MINE DEVELOPMENT AND OPERATIONS
During the Quarter, the Company prioritised development studies on the high-grade low tonnage
underground projects at Cannon, Penny’s Find and Rose Hill under a contract / JV mining and
milling model.
The advanced Cannon gold project is located 30km east-southeast of Kalgoorlie-Boulder (Figure
1) and 15km east of Boorara on existing roads.
Regionally, Cannon is in the western part of the Bulong ultramafic complex in the Boorara
Domain. The Bulong complex consists of 5km thick sequence of komatiitic lava flows made up
of a thick serpentinised peridotite in the centre of the complex, flanked by thin spinifex‐textured
komatiitic flows at the top of the sequence. High‐Mg basalts and interflow sediments are
intercalated with the thin flow facies komatiites. Komatiitic basalt and high‐Mg basalts have a
variety of textures which include pillowed, pyroxene spinifex textured and variolitic textured.
The Cannon mineralisation is structurally controlled and strikes north‐easterly, dipping steeply to
the north‐west; higher grade zones within the mineralised envelope appear to have a steep
northerly plunge. Gold‐related alteration consists of biotite‐calcite‐chlorite‐pyrite alteration with
an inner core of albite‐silica‐carbonate‐biotite‐pyrite‐gold replacement of the high Mg basalt and
intermediate intrusions. The Cannon gold deposit is hosted within a sequence of ultramafic and
high‐Mg basaltic rocks intruded by a mafic‐intermediate suite of lamprophyre dykes, and rarer
dacitic dykes.
Open pit mining was completed in June 2017 with 576,400t mined at 2.98g/t for 55,143 ounces,
almost a 100% reconciliation back to the resource. An adit at Cannon was mined in the east pit
wall below the ramp to recover a parcel of ore that became inaccessible via open pit mining.
Development of the adit began in May 2017 and production was completed in June 2017.
A total of 10,640 tonnes at 9.15g/t Au for 3,131 ounces were recovered; a significant
improvement on the reserve figures of 13,313 tonnes at 6.92 g/t for 2,962 ounces.
The Company acquired the project in 2021 and completed a detailed review of all geological
information enabling compilation of an updated Mineral resource estimate for the underground
deposit immediately beneath the existing open pit.
The Mineral Resource estimate (JORC 2012) for Cannon is shown below 1:
Resource category
Indicated
Inferred
Total
Cannon at 1.0g/t Au lower cut-off grade
Tonnes (t)
Grade (g/t Au)
176,000
51,000
226,000
5.10
2.30
4.40
Gold metal (oz)
28,580
3,750
32,330
In the March Quarter 2022, the Company released the results of the Pre-Feasibility Study (PFS)
comprising underground decline development from a portal within the historic open pit under a
contract and toll milling model.
As announced to the ASX on 29 March 2022, the key outcomes of the study are summarised in
the table below:
1
As announced to the ASX on 29 March 2022, see also Tables and Confirmations on Page 35.
Page 3 of 37
ASX ANNOUNCEMENT
Measure
PFS Outcome
Lateral Development (m)
1,264
Vertical Development (m)
131
Development Ore (kt)
15.0
Stoping Ore (kt)
120
Total Mined Ore (kt)
135
Gold grade (g/t)
4.1
Stope Mining Recovery
95%
Milling Recovery (%)
90%
Recovered Gold (oz)
15,910
Capital Costs (incl development) (A$m)
4.3
C1 Costs (A$/oz)
1,644
All in Sustaining Costs (A$/oz)
1,873
Free Cashflow at A$2,600/oz Au Price (A$m)
10.1
Significant potential exists for resource growth down plunge (Figure 2) and along strike on the
Cannon shear zone with further drilling planned from both surface and underground drilling
locations during the mining sequence. 1
The mine plan is being reviewed to determine whether the mine can be derisked via extracting
the higher grade veins in the hangingwall, in the better ground, and look at either leaving the
lower grade ore zones in the poorer ground conditions adjacent to the footwall ultramafics insitu,
or extract them later in the mining sequence. 1
All development approvals for Cannon were received during the Quarter with current work
focussed on contractor / JV partner negotiations for underground mining and milling. Funding for
Cannon was also secured during the quarter, with capital and development costs secured via the
US$3m second tranche of the company’s Nebari loan facility being able to be drawn upon from
16 June 2023. 2 For more information, see below under Corporate / Finance section.
Figure 2: The Cannon open pit looking northeast.
See Forward-looking and Cautionary Statement on Page 37. 2 As announced to the ASX on 14 June 2023 and 19
October 2022.
1
Page 4 of 37
ASX ANNOUNCEMENT
EXPLORATION AND EVALUATION
During the Quarter, the Company completed drilling at Penny’s Find to aim to grow the resource
at depth and also further test mineralisation to the north on the back of a successful drilling
campaign in 2021. Drilling results were released during the quarter. Further drilling is planned at
Penny’s Find in the northern domain, with an update of the MRE expected in the September
2023 quarter.
Planning activities for further drilling programs were developed for Monument, Pinner, Kestrel
and Honeyeater for resource growth and definition and new discovery drilling at Kanowna South
and Lakewood.
Extensive field work as part of the CY2022-23 new discovery and resource growth exploration
program. The program included reconnaissance and geological review at the Pinner and
Monument gold prospects within the Greater Boorara – Cannon project area and at Lakewood
continued.
Greater Boorara – Cannon project area
The Boorara Gold Project is located 15km east of Kalgoorlie-Boulder (Figure 1) adjacent to the
Super Pit and 1km southwest of the Nimbus Silver-Zinc Project site where established offices
are connected to mains power and existing water supplies.
The deposit is hosted in a quartz dolerite comprising a sheeted quartz vein array system with
bounding shear zones and late-stage cross faults. Mineralisation occurs as northwest dipping
sheeted and stockwork quartz-carbonate vein arrays within the quartz dolerite host rocks, and
steeply dipping zones along sheared geological contacts trending to the north-northwest.
The Mineral Resource estimate (JORC 2012) for Boorara is shown below 2:
Resource category
Measured
Indicated
Inferred
Total
Boorara at 0.5 g/t Au lower cut-off grade
Tonnes (Mt)
Grade (g/t Au)
1.28
1.23
7.19
1.27
2.56
1.26
11.03
1.26
Gold metal (koz)
51
294
103
448
The Cannon project area has demonstrated potential to be a significant future mining hub with
several historic prospects located within a 1km radius of the open cut mine.2 Three of the more
advanced prospects, Monument, Pinner and Homerton, were recently drilled to both validate
historic drilling and test for potential strike and depth extensions. There is also historical drilling
to the north of Cannon, Cannon North, which has not been followed up with drilling to test this
area in the September 2023 quarter. 1
At Monument (Figures 3 and 4), assay results were previously released from 14 RC holes
totalling 2,156m. 3
Mineralisation has now been defined along 700m of strike length and remains open to the north,
south and at depth. Follow up drilling has now been assessed and will commence in the
September Quarter 2023. 1
1
3
See Forward-looking and Cautionary Statement on Page 37. 2 See Tables and Confirmations on Page 35.
As announced to the ASX on 16 August 2022.
Page 5 of 37
ASX ANNOUNCEMENT
Figure 3: Monument and Homerton locations and drilling highlights 1
Figure 4: Monument cross section (see Figure 3 for location) 1
1
See Forward-looking and Cautionary Statement on Page 37 and Tables and Confirmations on Page 35.
Page 6 of 37
ASX ANNOUNCEMENT
Penny’s Find gold project
The 100% owned Penny’s Find gold project is located 50km northeast of Kalgoorlie-Boulder in
the heart of the Western Australian goldfields (Figure 1 and 5).
The high-grade gold mineralisation at Penny’s Find is hosted in thin quartz veins at the contact
between footwall sediments including black shale and siltstone and a hanging wall basalt. The
quartz veins dip about 60° to the northeast and collectively average 1m to 5m true width.
Open cut mining to 85m (242m RL) was completed by Empire Resources in 2018 with toll
treatment processing at Lakewood (Kalgoorlie) and Burbanks (Coolgardie). Production from the
open pit totalled 18,300oz at 4.47g/t Au (as announced to the ASX by Empire (ASX: ERL) on 25
July 2018).
Metallurgical test work and toll milling data from open pit ore processing has shown fresh
mineralisation to be free milling with a high gravity recoverable gold component and a total gold
recovery which exceeded 90%.
The current MRE (JORC 2012) for Penny’s Find is shown below 1:
Resource category
Indicated
Inferred
Total
Penny’s Find at 1.5g/t Au lower cut-off grade
Tonnes (t)
Grade (g/t Au)
203,000
67,000
270,000
Gold metal (oz)
5.45
3.60
4.99
35,000
8,000
43,000
An internal review and results from drilling in 2022 highlighted the potential to grow the production
profile with infill drilling to convert the Inferred material to Indicated in the current resource (Figure
5) and extension drilling along strike to the north and, particularly at depth below the current
resource envelope.3
During the Quarter, the planned infill and extension drilling was completed via an eight hole
RC/diamond program for 2,552.4m with the following highlights: 2
•
1.45m @ 2.61g/t Au from 314.75m and 3.2m @ 4.19g/t Au from 318.3m (PFRCD23003)
•
1.05m @ 6.36g/t Au from 355.5m (PFRCD23001)
•
1.0m @ 7.49g/t Au from 363.9m (PFRCD23002)
•
2.90m @ 1.73g/t Au from 292.0m (PFRCD23007)
•
0.78m @ 12.85g/t Au from 331.48m (PFRCD23006)
PFRCD23003 confirms the northern high grade plunge which indicates Penny’s is open at depth,
providing potential for additional resources. A small two hole RC program is planned early in the
September quarter to further infill the mineralisation to the north to ensure sufficient density to
classify that area of the resource as Indicated resource category, so that is can be converted into
an Ore Reserve. 3
An updated resource model will be complied enabling updated mine optimisation and design
studies to be completed for generation of Ore Reserves in H2 CY2023. 3
1
See Tables and Confirmations on Page 35. 2 As announced to the ASX on 31 May 2023. 3 See Forwardlooking and Cautionary Statement on Page 37.
Page 7 of 37
ASX ANNOUNCEMENT
Figure 5: Penny’s Find project drilling results to date 2
Horizon is focussed on developing a sequence of underground mines with Penny’s Find planned
to follow the proposed Cannon gold mine development which is scheduled for commencement
in H2 CY2023. The Rose Hill mine is planned for development following Penny’s Find. 3
Rose Hill gold project
Rose Hill is located 0.5km southeast of Coolgardie and lies on the western margin of the Archean
Norseman-Menzies Greenstone Belt. Mineralisation is hosted within the main Rose Hill diorite
(porphyry), adjacent to the hanging wall ultramafic and an eastern porphyry unit alongside the
Greenmount Sill (Figures 6 and 7). It is part of the same mafic-ultramafic package that includes
Brilliant, Tindals and Dreadnought to the south and Queen of Sheba immediately to the north.
During the Quarter, mine evaluation and review of surface infrastructure requirements continued,
along with liaising with key stakeholders.
The current strategy for Rose Hill is to develop an open pit (box cut) mining out the oxide and
transitional material to establish a portal location within fresh rock. Underground development
and mining would then commence to extract the underground resource and test depth extensions
from underground cuddy locations.
The Mineral Resource estimate (JORC 2012) for Rose Hill open pit is shown below1:
1
As announced to the ASX on 9 December 2020, see also Tables and Confirmations on Page 35. 2 As
announced to the ASX on 31 May 2023. 3 See Forward-looking and Cautionary Statement on Page 37.
Page 8 of 37
ASX ANNOUNCEMENT
Rose Hill Open Pit at 0.5 g/t Au lower cut-off grade
Resource category
Tonnes (Mt)
Grade (g/t Au)
Gold metal (koz)
Measured
0.19
2.00
12,300
Indicated
0.09
2.00
6,100
Inferred
Total
0.29
2.00
18,400
The Mineral Resource estimate (JORC 2012) for Rose Hill underground is shown below1:
Rose Hill Underground at 2.0 g/t Au lower cut-off grade
Resource category
Tonnes (Mt)
Grade (g/t Au)
Gold metal (koz)
Indicated
Inferred
Total
0.33
0.18
0.51
4.50
4.80
4.60
47,100
27,800
74,900
A maiden Ore Reserve for Rose Hill is expected in the December Quarter 2023. 2
Figure 6: Rose Hill drill hole 2020 collar plan and cross section locations
1
As announced to the ASX on 9 December 2020, see also Tables and Confirmations on Page 35.
See Forward-looking and Cautionary Statement on Page 37.
2
Page 9 of 37
ASX ANNOUNCEMENT
Figure 7: Rose Hill deposit cross section E - E’ (see Figure 8 for location).
Binduli gold project area
The Binduli area is located 9km west of Kalgoorlie - Boulder and is accessible by existing sealed
and unsealed roads (Figures 1, 8 and 9). The project area contains the core satellite Crake and
Coote projects in the south of the tenement package and Honeyeater and Kestrel prospects to
the north.
The geology at Binduli is dominated by the Black Flag Group – a sequence of intermediate and
felsic volcanics, sedimentary rocks and porphyry intrusives. Typically, the area is covered by
major North North-West (NNW) shear zones cutting across the historic Binduli goldfield. Close
to West Kalgoorlie are the Crake and Coote deposits which are similar to the nearby 390,000oz
Janet Ivy open pit, located 1.5km south, where the gold is hosted in a structurally controlled pink
Page 10 of 37
ASX ANNOUNCEMENT
feldspar porphyry. At the nearby Fort William and Fort Scott open pits, where over 100,000oz
have been produced to date, gold is hosted within sheared units of volcanics and clastic
sediments.
The Mineral Resource estimate (JORC 2012) for the advanced Crake deposit is shown below 1:
Resource category
Indicated
Inferred
Total
Crake at 0.8 g/t Au lower cut-off grade
Tonnes (Mt)
Grade (g/t Au)
1.33
0.46
1.42
1.47
1.27
1.46
Gold metal (koz)
63,150
3,300
66,500
During the Quarter, the Company assessed all recent assay results from resource extension
drilling at Coote and Crake (Figure 8) and planned the follow up extensional programs in the
Binduli camp 2.
Figure 8: Magnetic Image with drilling highlights at Coote and Crake
The Mineral Resource estimate (JORC 2012) for the Coote deposit is shown below 1:
Resource category
Inferred
Total
Coote at 1.0 g/t Au lower cut-off grade
Tonnes (Mt)
Grade (g/t Au)
0.43
1.54
0.43
1.54
Gold metal (koz)
21,000
21,000
During the Quarter, all recent assay results were reviewed from the Honeyeater and Black Flag
gold prospects in the northern Binduli project area.
The local geology at Honeyeater and Black Flag is dominated by the Black Flag Group – a NNW
trending sequence of intermediate and felsic volcanics, sedimentary rocks and porphyry
1
As announced to the ASX on 28 September 2022, see also Tables and Confirmations on Page 35.
See Forward-looking and Cautionary Statement on Page 37.
2
Page 11 of 37
ASX ANNOUNCEMENT
intrusives. The regional Janet Ivy Shear Zone meanders and gently cuts across the stratigraphy
to the N-NW of Honeyeater. Late-stage NE faults have created significant offsets and form
important structures for the gold mineralisation.
The gold mineralisation is typically found in a shear zone with quartz veins, minor pyrite, and
various amounts of silica-carbonate-sericite-chlorite alteration. The saline environment and
strong weathering profile at Honeyeater has resulted in a 25m depletion zone from the surface.
At the Honeyeater prospect (Figure 9), drilling comprised 13 RC holes for 1,063m with significant
new high-grade mineralisation intercepted.2 The mineralisation at Honeyeater spans a 200m
strike length and remains open to the north, south and at depth.
Follow up drilling at Kestrel and Honeyeater have been scheduled for a 2,600m program of AC
and RC drilling at Kestrel and Honeyeater for the September 2023 quarter. 3
Figure 9: Honeyeater prospect geology and drilling highlights
Teal project area
At the Teal Project area (Figures 1 and 10), 12km northwest of Kalgoorlie, previous drilling has
focussed on the oxide and transitional ore (30-80m depth) at Jacques Find and Peyes Farm.
Similar ore from Teal was proven to be highly amenable to conventional CIP/CIL treatment in
2017 where 21,836oz was produced by the Company from 229,000t @ 3.2g/t Au at a gold
recovery of 94.7%.
The Jacques Find – Peyes Farm gold deposits comprise a well-defined supergene blanket
located above shears and quartz within structurally controlled felsic schists, tuffs, sediments and
porphyry rocks at depth. Mineralisation is strongly influenced by cross cutting structures and
stratigraphy to the north to northwest striking shear zone which trend parallel to the regional NNW
geological trend of the Abattoir Shear.
Gold mineralisation is developed in a flat lying oxide supergene deposit located between 20-80
metres vertical depth and in primary mineralisation within a sub-vertical shear zone. In the deeper
1
As announced to the ASX on 28 September 2022, see Tables and Confirmations on Page 35. 2 As
announced to the ASX on 23 August 2022. 3 See Forward-looking and Cautionary Statement on Page 37.
Page 12 of 37
ASX ANNOUNCEMENT
primary sulphide mineralisation, typically below 80m depth, the metallurgy of the ore is semirefractory and requires pre-oxidation through roasting or ultra-fine grinding to achieve acceptable
recoveries, or be floated as a concentrate. The mineralisation lies on the same trend as Teal and
collectively the strike length is greater than 1500 metres.
Successful drilling campaigns in 2020 / 2021 (Figure 10) enabled the compilation of an updated
Mineral Resource estimate with mineralisation remaining open along strike and at depth.
For details on the drilling and resource updates, we refer you to the ASX announcement “Jacques
Find – Peyes Farm Resource Update” dated 15 September 2021 on the Company’s website.
The Mineral Resource estimate (JORC 2012) for Teal – Jacques – Peyes is shown below 1:
Teal – Jacques Find – Peyes Farm at 0.8 – 1.0g/t Au lower cut-off grade
Resource category
Tonnes (Mt)
Grade (g/t Au)
Gold metal (koz)
Indicated
Inferred
Total
1.98
1.57
3.55
2.27
2.25
2.26
144,680
113,460
258,140
During the Quarter, the Company progressed internal mine optimisation, design and economic
evaluation work on the upper supergene ore within the current resource envelope for
conventional milling.
In addition, an assessment of the deeper sulphide mineralisation is being undertaken in
conjunction with the Nimbus Silver-Zinc Project 20km to the east. The aim of this assessment is
to evaluate the potential to treat the deeper Teal ore and generate a gold concentrate for sale to
potential offtake partners along with a sliver and zinc concentrate from Nimbus utilising the same
concentrate plant.
For further information on the Study, we refer you to the ASX announcement “Nimbus Silver –
Zinc Project Update” dated 24 March 2022.
1
As announced to the ASX on 28 September 2022, see Tables and Confirmations on Page 35.
Page 13 of 37
ASX ANNOUNCEMENT
Figure 10: Jacques Find – Peyes Farm project drilling results to date
Kalpini gold project
Kalpini is located approximately 65km northeast of Kalgoorlie in the Eastern Goldfields of
Western Australia (Figures 1 and 11) and 50km by existing roads to the 100% owned Boorara
Gold Project. The project comprises granted mining lease M27/485 and miscellaneous lease
L27/88 and covers approximately 585 hectares. The main ore deposits within the project are
Gambia, Atlas and Camelia (Figure 11).
Stage 1 of the open pit was completed in 2019 and produced approximately 39,000oz with a mill
reconciled grade of 2.62g/t Au and calculated gold recovery of 95.1%.
Page 14 of 37
ASX ANNOUNCEMENT
Figure 11: Kalpini project drilling results to date 1
Gold mineralisation along the Gambia-Camelia trend has been defined over a 900m strike length
and confined to multiple stacked narrow (0.5-3m) high grade flat dipping lodes hosted within
gabbro. The lodes are characterised by arsenopyrite-sericite-carbonate quartz breccias that have
a limited leucoxene-chlorite-carbonate alteration halo in the host gabbro. Arsenopyrite content is
variable but in the high-grade lodes can be in the range 1-3%.
1
As announced to the ASX on 28 September 2021, see also Tables and Confirmations on Page 35.
Page 15 of 37
ASX ANNOUNCEMENT
Importantly, all drilling along the Gambia-Camelia trend has focussed on the flat dipping lodes
which are located on the central portion of the gabbro, with no drilling targeting the contact with
the intermediate volcanoclastic rocks. Both the hanging and footwall contacts of the gabbro may
provide the locus for shear hosted gold mineralisation, the flat narrow high-grade lodes being
perhaps brittle link lodes.
The Mineral Resource estimate (JORC 2012) for Kalpini is shown below 1:
Resource category
Indicated
Inferred
Total
Kalpini at 0.8g/t Au lower cut-off grade
Tonnes (Mt)
Grade (g/t Au)
1.40
0.47
1.87
2.43
2.04
2.33
Gold metal (koz)
108,000
31,000
139,000
During the Quarter, an internal review of the geological model and recent drilling results have
highlighted both the open pit and underground potential of the deposit and work continued on
compiling a new resource model on this basis.
Planning work also commenced on a potential drill program in the Atas area (Figure 11) for the
potential of defining an open pit resource for future mining.
An updated MRE for Kalpini shall be undertaken, and mine optimisation, design and economic
analysis will then follow for Ore Reserve generation in the in H1 2024. 2
Yarmany project area
The Yarmany project area is located 25km northwest of Coolgardie and 65km west of Kalgoorlie
– Boulder in Western Australia (Figures 1 and 12).
The geology at the Yarmany Project area is dominated by tholeiitic and high MgO basalts, felsic
and pelitic schists after felsic volcanic rocks and/or sediments with less common lithologies
including komatiitic ultramafics and granitoid intrusives, including pegmatites. The largest of
these granitoids, which occur in the southern parts of Yarmany is the Silt Dam Monzogranite,
interpreted to be a post-regional folding granitoid. The region has variable metamorphic grade,
but generally varies between low to high amphibolite facies typical for this western part of the
Kalgoorlie Terrane.
The western margin of the Yarmany project is bounded by the 500km long, northerly trending Ida
Fault, a crustal scale, east dipping, listric fault extending to greater than 15 km below surface.
The Yarmany drilling campaign completed in the March Quarter 2022 was the Company’s first
program at this underexplored project. The drilling was completed in two phases, namely RC and
Air Core (AC) drilling. AC drilling is typically used as a lower cost alternative to RC drilling,
especially during the early exploration stage while covering a larger testing area. It is, however,
often limited to drilling within the softer, more weathered rocks. A total of 47 RC holes for 4,413m
and 72 Air Core holes for 2,617m were completed (Figure 12).
1
2
As announced to the ASX on 28 September 2021, see also Tables and Confirmations on Page 35.
See Forward-looking and Cautionary Statement on Page 37.
Page 16 of 37
ASX ANNOUNCEMENT
Figure 12: Regional Magnetic Image with the 2021 Yarmany Exploration Highlights
Lakewood project area
The Lakewood project is located 20km southeast of Kalgoorlie - Boulder in the heart of the
Western Australian goldfields and immediately south of the Superpit (Figures 1 and 13).
The Lakewood project is extensively covered by Playa Lake sediments, aeolian deposits derived
from desiccated playas and other transported Cainozoic material. Only a small portion of the
Project area is covered by in-situ soils, and there is virtually no outcrop. Lakewood typically
comprises a thin veneer of soils overlying plastic clays that vary in thickness from 2m - 40m.
Below this are unconsolidated clays and sands and then bedrock. Sandy grey clay filled
paleochannels exist within the central Project area, some of which host small amounts of alluvial
gold. There has been no mining activity on the tenure.
The interpreted geology of the Lakewood project is a late-stage sedimentary basin dominated by
metamorphosed sedimentary rocks and felsic volcanic/intrusive rocks of the Black Flag
Formation, together with a sequence of sediments, basalts, mafic and ultramafic intrusives on
the eastern edge.
Recent interpretative gravity work in 2021 by an external consultant has shown that this linear
zone of mafic/ultramafic intrusives is located on a regional scale (~10mGal), deep seated
(+1,600m) NNW trending, vertical dipping litho-boundary. This could potentially be a key driver
as many of the Ni and Platinum Group Metals (PGM) occurrences in the Eastern Goldfields are
sited close to deep crustal structures.
Page 17 of 37
ASX ANNOUNCEMENT
During 2021, the Company completed a first pass reconnaissance program comprising 59 AC
holes for 3,002m testing four priority targets for nickel-cobalt and platinum group metals over a
mafic/ultramafic intrusives and sediments1. Further research and assessment are underway.