BLACK SWAN PROCESSING HUB – PROGRESS UPDATE
Maritana Minerals Limited (ASX: MRT) (“Maritana” or “the Company”) is pleased to provide an update on
project execution, approvals and non-process infrastructure workstreams for the Black Swan Processing Hub
(“BSPH”). Early Works activities are progressing with activities supporting the Company’s target for first gold
production in H2 CY2027.
HIGHLIGHTS
• Project Execution – Early Works are progressing across demolition, earthworks, detailed
engineering, long-lead procurement, mill refurbishment and enabling infrastructure as site activity
ramps up
• Approvals Pathway – The Clearing Permit required for the Carbon in Leach (CIL) earthworks is
progressing through the final approval process, with the key Mine Development Closure Plan (MDCP)
and Works Approval milestones already in place
• Primary Crushing Circuit – Clearing and demolition works are underway in the primary crushing area
to prepare the workfront for refurbishment and construction
• Earthworks – The bulk earthworks package has been awarded, incorporating work areas for the Run
of Mine (ROM) pad, CIL circuit and supporting site infrastructure
• Construction Water – Flow Water Services has been engaged to undertake borefield refurbishment
and upgrade program, with works progressing to reinstate the existing BSPH borefield for construction
water supply
• Accommodation – The first-stage construction camp has been operational since 3 August 2026 and
the second-stage expansion of a further 57 rooms is now complete. The contract for the permanent
60-room camp has been awarded
• Long-Lead Procurement – Procurement continues in parallel with detailed engineering, including the
pre-leach thickener and replacement SAG and ball mill motors to protect the development schedule
Managing Director and CEO Mr Grant Haywood commented:
“Progress at the BSPH has continued steadily as the project moves from approvals into execution. GR
Engineering Services has mobilised to site, demolition and earthworks are underway, the mill condition
assessments are largely complete, and long-lead procurement is advancing alongside detailed engineering,
which keeps us positioned for first gold production in H2 CY2027.”
maritanaminerals.com.au Page | 2
Project Execution and Early Works
Early Works at the BSPH continue to ramp up as the project transitions from development and approvals into
physical execution. GR Engineering Services has mobilised to site, with activities progressing across
demolition, earthworks, detailed engineering, procurement and preparation of the existing processing
infrastructure for refurbishment. The work program is being sequenced so enabling activities and existing-plant
works can progress while detailed engineering and procurement of the main processing plant modifications
continue in parallel.
Approvals
The MDCP and Works Approval milestones announced in August 2026 remain in place. The Clearing Permit
required for clearing associated with the CIL circuit is progressing through the final approval process.
Demolition
Demolition of redundant infrastructure has commenced with the safe removal and disposal of old conveyors,
transfer towers, ore bins and general structures not required. Where sections of the plant were identified as
structurally sound and reusable these will be refurbished and utilised as part of the new infrastructure build.
Figure 1 – Demolition of redundant conveyors and structures
maritanaminerals.com.au Page | 3
Bulk Earthworks
The updated ROM pad design has been completed to support the planned range of regional ore sources and
operational blending requirements. The bulk earthworks package is progressing in parallel, incorporating the
ROM pad, CIL work areas and associated supporting infrastructure. Delivery of select fill material for CIL Tank
foundations has commenced.
Figure 2 – CHS Mining Services commencement of select fill
Long-Lead Procurement
Procurement of long-lead equipment continues in parallel with detailed engineering and Early Works. Key
packages being progressed include the pre-leach thickener and replacement SAG and ball mill motors,
together with other equipment required to support the plant refurbishment and new CIL circuit.
Site Access, Security and Communications
Detailed design of the permanent site entrance, gatehouse, traffic management and controlled-access
arrangements continues as site activity increases. In parallel, the integrated communications architecture is
progressing across the processing plant, administration facilities, construction areas and accommodation
village, including data, wireless and operational radio communications.
maritanaminerals.com.au Page | 4
Borefields
The Company has engaged Flow Water Services to complete the borefield refurbishment and upgrade
program on Maritana leases. Works are progressing to reinstate the existing borefield for construction water
supply, including the supply and installation of pumps, piping, gensets and communications equipment.
Figure 3 – Borefield refurbishments in progress
Accommodation Update
The first-stage construction camp has been operational since 3 August 2026. The second-stage expansion,
comprising a further 57 rooms, is now complete. This materially increases accommodation capacity available
to support the growing construction workforce.
maritanaminerals.com.au Page | 5
Figure 4 – BSHP Construction Camp Stage 2 – 57 Rooms
Procurement of modules for the permanent 60 room BSPH camp, scalable to 120 rooms, is progressing with
long lead items, such as the kitchen ordered and scheduled for delivery during November 2026. The Company
is engaging with the preferred construction provider, and the camp is expected to be operational from January
2027.
Figure 5 – BSPH expanded Wet & Dry Mess facilities installed on site
maritanaminerals.com.au Page | 6
To cater to the increased workforce, a new wet and dry mess, laundry, outdoor BBQ and gym facilities have
been installed.
The combined construction and permanent camp accommodation supports the required manning for the plant
development schedule.
Authorised for release by the Board of Directors.
For further information, please contact:
Grant Haywood Michael Vaughan
Managing Director and CEO Investor and Media Relations – Fivemark
grant.haywood@maritanaminerals.com.au michael.vaughan@fivemark.com.au
+61 8 9386 9534 +61 422 602 720
JOIN MARITANA MINERALS INTERACTIVE HUB
Visit https://maritanaminerals.com.au/auth/signup for
Maritana Minerals’ Interactive InvestorHub
MARITANA MINERALS
Email: info@maritanaminerals.com.au
maritanaminerals.com.au Page | 7
Figure 6 - Maritana Minerals Regional Tenement Holding
Forward Looking Statements
Some statements in this report regarding estimates or future events are forward looking statements. They
include indications of, and guidance on, future earnings, cash flow, costs and financial performance. Forward
looking statements include, but are not limited to, statements preceded by words such as “planned”,
“expected”, “projected”, “estimated”, “may”, “scheduled”, “intends”, “anticipates”, “believes”, “potential”, “could”,
“nominal”, “conceptual” and similar expressions. Forward looking statements, opinions and estimates included
in this announcement are based on assumptions and contingencies which are subject to change without notice,
as are statements about market and industry trends, which are based on interpretations of current market
conditions. Forward looking statements are provided as a general guide only and should not be relied on as a
guarantee of future performance. Forward looking statements may be affected by a range of variables that
maritanaminerals.com.au Page | 8
could cause actual results to differ from estimated results and may cause the Company’s actual performance
and financial results in future periods to materially differ from any projections of future performance or results
expressed or implied by such forward looking statements. These risks and uncertainties include but are not
limited to liabilities inherent in mine development and production, geological, mining and processing technical
problems, the inability to obtain any additional mine licenses, permits and other regulatory approvals required
in connection with mining and third party processing operations, competition for among other things, capital,
acquisition of reserves, undeveloped lands and skilled personnel, incorrect assessments of the value of
acquisitions, changes in commodity prices and exchange rate, currency and interest fluctuations, various
events which could disrupt operations and/or the transportation of mineral products, including labour stoppages
and severe weather conditions, the demand for and availability of transportation services, the ability to secure
adequate financing and management’s ability to anticipate and manage the foregoing factors and risks. There
can be no assurance that forward looking statements will prove to be correct.
Statements regarding plans with respect to the Company’s mineral properties may contain forward looking
statements in relation to future matters that can only be made where the Company has a reasonable basis for
making those statements.
This announcement has been prepared in compliance with the JORC Code (2012) and the current ASX Listing
Rules.
The Company believes that it has a reasonable basis for making the forward-looking statements in the
announcement, including with respect to any production targets and financial estimates, based on the
information contained in this and previous ASX announcements.