ASX ANNOUNCEMENT
20 OCTOBER 2025
QUARTERLY ACTIVITIES REPORT FOR THE
PERIOD ENDED 30 SEPTEMBER 2025
HIGHLIGHTS
• Continued safe gold production and revenue from Boorara and Phillips Find via the
existing ore sale and toll milling agreements.
• Continued process engineering and life-of-mine studies to support mine feed planning for
the Black Swan Project.
• Ongoing resource definition drilling at the Burbanks Project.
• Post quarter-end initial gold assay results from Phase 1 of the Burbanks Drilling Program
returned for 15 holes, with highlights as follows: 1
ο 1.55m @ 99.65g/t Au from 336.3m including 0.4m @ 350.00 g/t Au from 336.7m
and 0.35m at 64.29g/t Au from 336.3m (25HBBD004)
ο 5.3m @ 3.49g/t Au from 235.7m including 0.6m @ 19.22 g/t Au from 238.7m
(25HBBD004)
ο 1.7m @ 37.18g/t Au from 71.0m (25HBBD004)
ο 3.7m @ 5.13g/t Au from 222.4m including 0.57m @ 27.52g/t Au from 224.8m
(25HBBD004)
ο 7.2m @ 3.92g/t Au from 260.3m, 2.0m @ 4.86g/t Au from 280.0m and 4.0m @
12.75g/t Au from 366.1m (25HBBD002)
ο 1.0m @ 31.63g/t Au from 106.0m (25HBBD005)
ο 1.0m @ 19.84g/t Au from 285.0m (25HBBD013)
• Acquired 100% interest in the Gordons Project located near the wholly owned Black
Swan processing facility, through the execution of a Binding Tenement Sale Agreement
with Yandal Resources Limited 2
DECEMBER QUARTER ACTIVITIES
• Acceleration of the Burbanks extensional and infill drilling program with deployment of an
additional diamond drill rig.
• Completion of the Pre-Feasibility Study to include mining and infrastructure studies, and
the refurbishment and repurposing of the Black Swan processing facility into a gold plant.
• Continued production from the Boorara and Phillips Find gold operations.
1
As announced to the ASX on 6 October 2025.
2
As announced to the ASX on 11 August 2025.
Page 2 of 29
HRZ QUARTERLY SEPTEMBER 2025
OVERVIEW
Horizon Minerals Limited (ASX: HRZ) (“Horizon” or “the Company”) is pleased to report on its
activities for the quarter ended 30 September 2025 (“the Quarter”). Horizon is a gold production
and exploration company within the Kalgoorlie and Coolgardie regions of Western Australia
(Figure 1).
Horizon Minerals’ key objective is near-term gold production and realise exploration upside within
our large tenement package of 1,309 km2. In addition to the 1.8Moz of gold resources, the
Company holds a number of multi-commodity assets including the 20.2Moz Ag Nimbus Silver-
Zinc Project.
Figure 1: Horizon’s project locations, regional geology and surrounding infrastructure including
the Gordons Project acquisition.
Activities during the Quarter focussed on continued steady state production from the Company’s
Boorara gold operation, located east of Kalgoorlie, and through the Phillips Find gold project to
the north-northwest of Coolgardie. Drilling continued at the Burbanks Gold Project, as well as
generating a long-term exploration target pipeline and increasing exploration personnel.
Additionally for the Quarter, Horizon completed a regional consolidation of assets near the wholly
owned Black Swan Processing facility. This included the acquisition of the Gordon’s Gold Project
from Yandal Resources, which comprises of several gold prospects and targets at various stages
of exploration and development as well as the Gordons Dam Deposit.
Page 3 of 29
HRZ QUARTERLY SEPTEMBER 2025
MINE DEVELOPMENT AND OPERATIONS
The Company continues to successfully execute on its strategy of bringing its extensive gold
assets into production, generating strong cashflows during record high gold prices with its
Boorara and Phillips Find Gold Projects.
Boorara Gold Project
The Boorara Gold Project is located 15 km east of Kalgoorlie-Boulder (Figure 1) adjacent to the
Super Pit, and 1 km southwest of the Nimbus Silver-Zinc Project site where established offices
are connected to mains power and existing water supplies.
The deposit is hosted in a quartz dolerite comprising a sheeted quartz vein array system with
bounding shear zones and late-stage cross faults. Mineralisation occurs as northwest dipping
sheeted and stockwork quartz-carbonate vein arrays within the quartz dolerite host rocks, and
steeply dipping zones along sheared geological contacts trending to the north-northwest.
The Mineral Resource Estimate (JORC 2012) for Boorara is shown in the Summary of Gold
Mineral Resources for Horizon Minerals on Table 5 (page 2) of this Quarterly Report.
Table 1: Quarterly production data *
Oct-Dec
24 Jan-Mar 25 Apr-Jun 25 Jul-Sep 25
Boorara Gold Project UoM Qtr. 2 Qtr. 3 Qtr. 4 Qtr. 1 FY25 Total FY26 YTD
MINING & HAULAGE
Mined
Ore Mined tonnes 112,212 195,727 298,042 268,728 605,981 268,728
Mined Grade [est.] gr/t 0.838 0.954 0.952 1.027 0.932 1.027
Gold Mined oz 3,024 6,005 9,125 8,874 18,154 8,874
Hauled
Ore Hauled tonnes 27,936 72,354 221,299 232,696 321,589 232,696
Hauled Grade [est.] gr/t 0.798 0.880 0.936 0.939 0.911 0.939
Gold Hauled oz 717 2,047 6,659 7,028 9,423 7,028
PROCESSING & REVENUE
Milled
Ore Milled tonnes 6,242 71,744 227,661 238,096 305,647 238,096
Milled Grade gr/t 0.798 0.842 0.907 1.057 0.889 1.057
Recovery % 90.0% 90.0% 92.8% 90.9% 92.1% 90.9%
Gold Produced oz 144 1,747 6,161 7,349 8,052 7,349
Sales
Gold Invoiced oz - 1,163 6,446 6,549 7,609 6,549
Average Price A$/oz - 4,608 5,048 5,472 4,981 5,472
Revenue $AM - 5.4 32.5 35.8 37.9 35.8
*
The above table of production data was unaudited as at the time of this report.
Page 4 of 29
HRZ QUARTERLY SEPTEMBER 2025
During the Quarter, mining and ore haulage from Boorara continued to progress at a steady state
with ~269k dry tonnes at 1.027 g/t Au mined for 8,874 oz and 6,549 oz of gold sold at an average
gold price of $5,472/oz, generating ~$35.8 million in revenue (Table 1). Boorara has continued
to deliver ore in accordance with the corporate plan during the Quarter.
In addition to the ore treated at and hauled to the Paddington Mill, the Company had generated
~209 kt of high-grade ore stocks on the Boorara and/or Paddington ROM pads, plus ~112 kt of
lower-grade ore stockpiled at Boorara at Quarter-end.
Figure 2: Loading ore at Boorara to transport to the Paddington Mill
Phillips Find Project
The project is centred 45km north-northwest of Coolgardie (Figure 1) covering over 10km strike
of prospective greenstone stratigraphy, and includes the Phillips Find Mining Centre (PFMC)
where approximately 33,000oz of gold was produced between 1998 and 2015 from three open‐
pit operations; Bacchus Gift, Newhaven and Newminster.
During the Quarter, continued safe steady state production was achieved from the Newhaven
and Newminster open pits (Figure 3 and Figure 4) with completion of another processing
campaign of ore from the Phillips Find JV with BML under the 200,000t Toll Milling Agreement
with FMR Investments Pty Ltd (FMR) to treat Horizon ore at the Greenfields Mill. The ore
processed from Phillips Find during the Quarter consisted of 42,645 dry tonnes at 1.67 g/t for
2,147 oz at an average price of $5,694/oz, generating ~$12.2 million in revenue to the Phillips
Find JV.
Page 5 of 29
HRZ QUARTERLY SEPTEMBER 2025
Figure 3: Ore on the Phillips Find ROM pad.
Figure 4: Mining the Newminster pit at Phillips Find
Page 6 of 29
HRZ QUARTERLY SEPTEMBER 2025
Black Swan Project PFS Update 3
During the Quarter, GR Engineering Services (GRES) progressed the Pre-Feasibility Study (PFS)
for integrating the brownfield refurbishment and upgrade of the comminution circuit with the
development of a new greenfield gravity and CIL gold recovery circuit of the Black Swan
processing plant (Figure 5). To date, process flow diagrams, mechanical equipment and electrical
load lists, single line diagrams, and various other components have been completed.
The PFS is broadly focused on two core areas: a (brownfields) upgrade of the existing
comminution circuit and the design of a new (greenfields) gravity and CIL circuit to support gold
processing. To date, the PFS has delivered process design criteria, preliminary flowsheets,
equipment lists, and layout concepts, all of which are currently under review.
GRES Undertook a critical first step to assess the implications of processing lower-competency
gold ore relative to the original high-competency nickel ore. This assessment ensured that the
optimal circuit configuration for gold processing was identified, rather than simply relying on the
existing arrangement.
GRES evaluated three comminution circuit options, with the proposed gold processing facility
designed for 1.5Mtpa throughput and equipment sized to achieve a product size of P80 106µm.
Three comminution options considered were:
1. Single stage crush plus SAG mill (SS SAG).
2. Single stage crushing plus SAG and ball mill (SABC)
3. Three-stage crushing plus ball mill (3SC + BM)
In parallel, Orway Minerals Consultants (“OMC”) conducted simulation studies on the different
feed sources through the comminution circuit, using the available ore characteristics from
multiple ore feed sources held by Horizon Minerals to the Black Swan plant. Both the OMC
simulations and GRES trade-off studies independently favoured option 1 (SS SAG) for the
1.5Mtpa rate, but also indicated that with a marginal increase in capital, refurbishing both the SS
SAG and option 2 (SABC) circuits at the start would offer a significant opportunity for future
expansion and greater long-term flexibility.
Progressing in parallel, the range of specialist consultants and engineering firms to progress
early-stage engineering, scoping studies, and technical investigations across key infrastructure
areas including power supply, water supply, site roads, haulage corridors, tailings storage,
accommodation, and communications. These groups are actively reviewing and validating
infrastructure assumptions, conducting gap analyses, and ensuring alignment with the proposed
processing plant design. This work is a key part of Horizon’s strategy to de-risk development and
ensure that infrastructure planning is technically robust and fully integrated into the broader
project.
The study is progressing well and remains on track for completion in the December 2025 quarter.
3
As announced to the ASX 27 August 2025
Page 7 of 29
HRZ QUARTERLY SEPTEMBER 2025
Figure 5: Black Swan processing plant
Mining and Infrastructure Studies 5
Mining Plus has been engaged to assist with delivering the mining studies that will provide the
ore feed to Black Swan, aiming for a minimum life of mine plan of five years. Studies are being
progressed and are on track for completion in December quarter.
Scheduling and strategic planning are currently underway to finalise the life of mine plan.
Environmental and auxiliary studies and surveys to support the operations are also underway
with planned completion in the December quarter.
The flagship Burbanks project has shown great potential to be a long-life asset that can feed
Black Swan, however areas of additional project work are required before it can be advanced to
a PFS level of study. A geotechnical gap analysis has been completed which has identified
information gaps. The data will be used to plan additional drilling which will also target
Metallurgical test work requirements. This additional drilling is planned for the December quarter.
It is anticipated that the PFS and Burbanks Scoping Study will be sufficient to make an informed
Financial Investment Decision (FID) on the mill refurbishment and conversion of Black Swan to
a gold plant. Subject to a positive FID, construction could commence during 2026.
EXPLORATION AND EVALUATION
Extensional and infill drilling commenced at Burbanks in late June 2025 and continued steadily
through the Quarter. A two-phase reverse circulation (“RC”) and diamond drill program with RC
pre-collars for a total 30,000m is planned, with Phase 1 drilling underway:
• Phase 1 comprises ~15,000m of infill drilling to enhance resource continuity and
confidence with results expected through to the March 2026 quarter
Page 8 of 29
HRZ QUARTERLY SEPTEMBER 2025
• Phase 2 comprises ~15,000m of extensional drilling, targeting along strike and down dip
of known high grade lodes with drilling commencing in early 2026
The Phase 1 infill program is targeting either side of the Main Lode, towards the Birthday Gift and
Burbanks North lodes to enhance resource continuity and resource confidence, and transition
more of the resource from the Inferred to Indicated category.
Post quarter-end the Company announced the first batch of assay results from 15 of the planned
45 Phase 1 drillholes and six holes have yielded intercepts with exceptional grades (above 20g/t)
along with visible gold in most holes. 4 Drilling confirmed mineralisation continuity both to the
north, and in the area between Burbanks North and Main Lode (Figure 6). 5
Guided by the Phase 1 results, the second phase of drilling will target down-dip and strike
extensions of known high-grade lodes, aiming to further expand and grow the resource base.
Planning and approvals for the second phase of Burbanks drilling also commenced during the
quarter as well as further refinement of the exploration target pipeline and development of the
Resource portfolio.
Figure 6: SW NE schematic long section on local grid showing the location of the Main Lode and Burbanks
North, the current MRE categories, historical pierce points and recent drill traces with pierce points >1.0g/t
ACQUISITIONS AND DIVESTMENTS
During the Quarter, the Company executed a binding Tenement Sale Agreement with Yandal
Resources (“Yandal”) to acquire the Gordons, Mt Jewell, Malone and Mulgarrie gold projects
(‘the Acquisition”) (~77km², 34 tenements) near the Company’s 100% owned Black Swan
processing facility (Figure 7) 5. Consideration for the Acquisition totalled A$2.81m, comprising of
both cash and HRZ shares.6 The Acquisition delivers the Gordons Dam deposit which has a
100% inferred MRE of 365,000t @ 1.7g/t Au for 20,000oz (> 1g/t Au lower cut-off grade) plus
4
As announced to the ASX on 6 October 2025.
5
As announced to the ASX on 11 August 2025
Page 9 of 29
HRZ QUARTERLY SEPTEMBER 2025
further exploration upside, strengthening Horizon’s regional consolidation strategy and
supporting study work toward a five-year life of mine plan at Black Swan. Exploration of the
Gordon’s project is planned to commence in 2026. Final steps in the transaction including the
transfer of tenements to Horizon Minerals is scheduled to take place in the next quarter. Horizon
Minerals is of the opinion that there is potential to identify extensions to mineralisation across
numerous gold targets and prospects.
Figure 7: Gordons Project tenements, prospects and regional geology. Historical and Yandal
Resources drilling represented as maximum downhole assays (ppm).
Page 10 of 29
HRZ QUARTERLY SEPTEMBER 2025
ENVIRONMENTAL, SOCIAL AND GOVERNANCE
The Company acknowledges the importance of Environment, Social and Governance (ESG)
factors and is committed to continuous improvement in this regard.
During the Quarter, several initiatives have been progressed to ensure we meet or exceed our
corporate license to operate. Initiatives include updates to water licences and flora and fauna
surveys in preparation for future operational requirements.
The Company previously worked with BDO Global to conduct an analysis of the business to
identify opportunities to improve the Company’s ESG performance. Materiality surveys were
completed for both internal and external stakeholders and completed a workshop to map the
opportunities and generate an initial sustainability report. The aim of the process is to develop
systems and processes to ensure we meet or exceed our social license to operate and adopt the
sustainability report covering current and future activities.
CORPORATE / FINANCE
Total cash at bank as at 30 September 2025 was A$34.4 million. In addition, the Company holds
investments in ASX listed companies with a current value of approximately A$1.6 million (Table
3). Note during the Quarter there was an additional payment of $3.65m to the mining and haulage
contractor as the Company moved from 60 to 30 day trading terms, i.e. four months mining
payments.
On 17 July 2025 the Company issued 422,823,368 ordinary shares as part of Tranche 2 of the
strategic placement announced to the market on 26 May 2025. Tranche 2 raised approximately
$18.2 million (before costs) and was approved at the General Meeting held on 10 July 2025.
As previously announced to the ASX on 19 October 2022 and 23 November 2022, the Company
executed loan agreements with Nebari LLC (“Nebari”) for a US$5 million Convertible Loan Facility
in two tranches of US$2 million and US$3 million respectively. Both tranches have been drawn
down. For further information and terms of the Loan Agreement, refer to the ASX announcements
dated 19 October 2022 and 23 November 2022.
During the Quarter, Nebari provided notice to convert USD$2.6 million of the Convertible Loan
Facility. As partial repayment of the Convertible Loan Facility, the Company issued 100,000,000
fully paid ordinary shares at a deemed issue price of $0.04 per share. As at 30 September 2025,
the remaining balance of the Convertible Loan Facility was USD$1.1 million.
On 4 September, the Company advised that Mr Daniel Coletta had been appointed as Company
Secretary and Mr Julian Tambyrajah had ceased his role as Chief Financial Officer and Company
Secretary.
On 22 September 2025, the Company announced the appointment of Mr Brendan Shalders as
Chief Financial Officer commencing in January 2026.
In accordance with ASX Listing Rule 5.3.5, approximately $42,000 was paid to related parties or
their associates during the Quarter, comprising Non-Executive Director fees.
Table 2: Issued Share Capital
Code Class of securities
On Issue at
30 September
2025
HRZ Fully Paid Ordinary Shares 2,994,680,238
HRAZO Unlisted Options (exercise price 5.19c, expiry 3 Sep 2026) 18,024,786
HRZAN Director & Employee Performance Rights 22,469,100
Page 11 of 29
HRZ QUARTERLY SEPTEMBER 2025
Expired
HRZO Listed Options (exercise price 8.7c, expiry 21 Sep 2025) 26,723,171
Table 3: Listed Company Investments
Company Number Value at 30 September 2025
Richmond Vanadium Technology 19,833,363 1 $1,328,835
Metal Hawk Limited 1,134,430 1 $153,148
Dundas Minerals Limited 3,234,327 1 $87,327
TOTAL $1,569,310
1. Liquid asset
This quarterly report has been authorised by the Board of Directors of Horizon Minerals Limited
for release.
For further information contact Horizon on:
T: + 61 8 9386 9534
Page 12 of 29
HRZ QUARTERLY SEPTEMBER 2025
APPENDICES
Table 4: TENEMENT SCHEDULE
Prospect/Tenement Notes
Percentage
interest held at
the end of the
quarter
Percentage
interest acquired
during the
quarter
Percentage interest
disposed during the quarter
WESTERN
AUSTRALIA
BINDULI
L26/261 100% - -
M26/346 100% - -
M26/499 100% - -
M26/549 100% - -
M26/621 100% - -
P26/4256 0% - 100%
P26/4579 100% - -
P26/4580 100% - -
MLA26/855 100% - -
BLACK FLAG
E26/220 100% - -
P24/5145 0% - 100%
P24/5146 0% - 100%
P24/5150 0% - 100%
P24/5155 0% - 100%
P24/5156 0% - 100%
P24/5157 0% - 100%
P24/5158 0% - 100%
P24/5160 0% - 100%
P24/5348 100% - -
P24/5415 100% - -
P24/5637 100% - -
Page 13 of 29
HRZ QUARTERLY SEPTEMBER 2025
TENEMENT SCHEDULE continued
Prospect/Teneme
nt
Notes
Percentage
interest held at
the end of the
quarter
Percentage
interest acquired
during the
quarter
Percentage interest
disposed during the
quarter
WESTERN
AUSTRALIA
BLACK FLAG
P24/5638 100% - -
P24/5639 100% - -
P24/5640 100% - -
BRIDGETOWN-GREENBUSHES
E70/5980 100% - -
E70/5981 100% - -
E70/6551 100% - -
ELA70/6552 0% - 100%
ELA70/6553 0% - 100%
E70/6554 100% - -
ELA70/6555 0% - 100%
CANNON
E25/349 100% - -
E25/543 100% - -
E25/564 100% - -
L25/48 100% - -
L25/50 100% - -
L25/51 100% - -
M25/182 100% - -
M25/327 100% - -
M25/329 100% - -
M25/330 100% - -
M25/333 100% - -
M25/357 100% - -
P25/2449 100% - -
P25/2633 100% - -
P25/2670 100% - -
P25/2733 100% - -
P25/2748 100% - -
P25/2755 100% - -
P25/2761 100% - -
CHADWIN
P16/3121 100% - -
Page 14 of 29
HRZ QUARTERLY SEPTEMBER 2025
TENEMENT SCHEDULE continued
Prospect/Tenement Notes
Percentage
interest held at the
end of the quarter
Percentage
interest acquired
during the quarter
Percentage interest
disposed during the
quarter
WESTERN
AUSTRALIA
COOLGARDIE
E16/589 100% - -
E16/590 100% - -
E16/591 100% - -
E16/592 100% - -
LA15/429 0% - 100%
LA15/430 0% - 100%
GOLDEN RIDGE (NIMBUS)
M26/41 100% - -
M26/433 100% - -
M26/534 100% - -
KALPINI
L27/88 100% - -
M27/485 100% - -
KANOWNA BELLE (NIMBUS)
P27/2380 100% - -
P27/2381 100% - -
PENNY’S FIND
G27/1 100% - -
L27/90 100% - -
L27/91 100% - -
L27/92 100% - -
L27/93 100% - -
M27/156 100% - -
ROSE HILL
M15/1204 100% - -
M15/652 100% - -
P15/6380 100% - -
Page 15 of 29
HRZ QUARTERLY SEPTEMBER 2025
TENEMENT SCHEDULE continued
Prospect/Tenement Notes
Percentage
interest held at
the end of the
quarter
Percentage
interest acquired
during the
quarter
Percentage interest
disposed during the
quarter
WESTERN
AUSTRALIA
LAKEWOOD
E26/209 100% - -
P26/4316 100% - -
P26/4317 100% - -
PLA26/4318 100% - -
P26/4319 100% - -
P26/4320 100% - -
P26/4321 100% - -
P26/4322 100% - -
P26/4323 100% - -
P26/4324 100% - -
P26/4325 100% - -
P26/4326 100% - -
P26/4327 100% - -
P26/4328 100% - -
P26/4329 100% - -
P26/4330 100% - -
P26/4331 100% - -
P26/4332 100% - -
P26/4333 100% - -
P26/4334 100% - -
P26/4335 100% - -
P26/4336 100% - -
P26/4337 100% - -
P26/4338 100% - -
P26/4339 100% - -
P26/4340 100% - -
P26/4341 100% - -
P26/4342 100% - -
P26/4343 100% - -
P26/4344 100% - -
P26/4345 100% - -
P26/4350 100% - -
Page 16 of 29
HRZ QUARTERLY SEPTEMBER 2025
TENEMENT SCHEDULE continued
Prospect/Tenement Notes
Percentage
interest held at
the end of the
quarter
Percentage
interest acquired
during the
quarter
Percentage interest
disposed during the
quarter
WESTERN
AUSTRALIA
WHITE FLAG
E26/168 100% - -
M26/616 1 100% - -
WINDANYA 9
M24/919 100% - -
M24/959 100% - -
P24/4817 100% - -
P24/5046 100% - -
P24/5464 100% - -
P24/5507 100% - -
P24/5508 100% - -
MLA24/1004 100% - -
MLA24/1020 100% - -
YARMANY
E15/1655 100% - -
E15/1723 100% - -
E16/470 100% - -
E16/471 100% - -
E16/493 100% - -
E16/494 100% - -
E16/497 100% - -
E16/503 100% - -
E16/506 100% - -
E16/507 100% - -
E16/510 100% - -
E16/519 100% - -
E16/521 100% - -
E16/525 100% - -
E16/526 100% - -
P16/3212 100% - -
P16/3213 100% - -
Page 17 of 29
HRZ QUARTERLY SEPTEMBER 2025
TENEMENT SCHEDULE continued
Prospect/Tenement Notes
Percentage
interest held at
the end of the
quarter
Percentage
interest acquired
during the
quarter
Percentage interest
disposed during the
quarter
WESTERN
AUSTRALIA
NIMBUS/BOORARA
E25/511 100% - -
L25/32 100% - -
L25/35 100% - -
L25/36 100% - -
L26/240 100% - -
L26/252 100% - -
L26/266 100% - -
L26/270 100% - -
L26/274 100% - -
L26/275 100% - -
M25/355 100% - -
M26/29 100% - -
M26/161 100% - -
M26/277 100% - -
M26/318 100% - -
M26/490 100% - -
M26/598 100% - -
P25/2450 100% - -
P25/2469 100% - -
P25/2470 100% - -
P25/2471 100% - -
P25/2472 100% - -
P25/2473 100% - -
P25/2474 100% - -
P25/2475 100% - -
P25/2526 100% - -
P25/2551 100% - -
P25/2552 100% - -
Page 18 of 29
HRZ QUARTERLY SEPTEMBER 2025
TENEMENT SCHEDULE continued
Prospect/Tenement Notes
Percentage
interest held at
the end of the
quarter
Percentage
interest acquired
during the
quarter
Percentage interest
disposed during the
quarter
WESTERN AUSTRALIA
NIMBUS/BOORARA
P25/2643 100% - -
P25/2644 100% - -
P25/2645 100% - -
P25/2646 100% - -
P25/2647 100% - -
P25/2697 100% - -
P25/2732 100% - -
P26/4199 100% - -
P26/4204 100% - -
P26/4205 100% - -
P26/4206 100% - -
P26/4207 100% - -
P26/4208 100% - -
P26/4299 100% - -
P26/4300 100% - -
P26/4301 100% - -
P26/4302 100% - -
P26/4381 100% - -
P26/4382 100% - -
P26/4383 100% - -
P26/4384 100% - -
P26/4385 100% - -
P26/4386 100% - -
P26/4405 100% - -
P26/4431 100% - -
P26/4432 100% - -
P26/4505 100% - -
P26/4509 100% - -
P26/4510 100% - -
P26/4518 100% - -
P26/4582 100% - -
Page 19 of 29
HRZ QUARTERLY SEPTEMBER 2025
TENEMENT SCHEDULE continued
Prospect/Tenement Notes
Percentage
interest held at
the end of the
quarter
Percentage
interest acquired
during the
quarter
Percentage interest
disposed during the
quarter
WESTERN
AUSTRALIA
NIMBUS/BOORARA
P27/2429 100% - -
P27/2466 100% - -
P27/2467 100% - -
BURBANKS 2
M15/161 100% - -
M15/731 100% - -
MLA15/1845 100% - -
P15/5249 100% - -
P15/5412 100% - -
P15/6314 100% - -
P15/6381 100% - -
P15/6382 100% - -
PLA15/6417 100% - -
PLA15/6549 100% - -
P15/6757 100% - -
P15/6774 100% - -
P15/6775 100% - -
PHOENIX 2
M15/119 100% - -
PHILLIPS FIND 2
M16/130 100% - -
M16/133 100% - -
M16/168 100% - -
M16/171 100% - -
M16/242 100% - -
M16/258 100% - -
M16/550 100% - -
MLA16/556 100% - -
MLA16/597 100% - -
MLA16/602 100% 100% -
MLA16/603 100% 100% -
MLA16/604 100% 100% -
MLA16/605 100% 100% -
Page 20 of 29
HRZ QUARTERLY SEPTEMBER 2025
TENEMENT SCHEDULE continued
Prospect/Tenement Notes
Percentage interest
held at the end of
the quarter
Percentage interest
acquired during the
quarter
Percentage interest
disposed during the
quarter
WESTERN
AUSTRALIA
PHILLIPS FIND 2
MLA16/606 100% 100% -
MLA16/607 100% 100% -
MLA16/608 100% 100% -
MLA16/609 100% 100% -
MLA16/610 100% 100% -
P16/2985 100% - -
P16/2986 100% - -
P16/2987 100% - -
P16/2988 100% - -
P16/2998 100% - -
P16/2999 100% - -
P16/3037 100% - -
P16/3038 100% - -
P16/3039 100% - -
P16/3040 100% - -
P16/3041 100% - -
P16/3042 100% - -
P16/3043 100% - -
P16/3084 3 85% - -
P16/3085 3 85% - -
P16/3086 3 85% - -
P16/3087 3 85% - -
P16/3088 100% - -
P16/3358 100% - -
PLA16/3525 100% - -
BLACK SWAN 4 100% - -
G27/2 100% - -
L24/219 100% - -
L24/222 100% - -
L27/57 100% - -
L27/58 100% - -
L27/59 100% - -
L27/74 100% - -
Page 21 of 29
HRZ QUARTERLY SEPTEMBER 2025
TENEMENT SCHEDULE continued
Prospect/Tenemen
t
Notes
Percentage
interest held at the
end of the quarter
Percentage
interest acquired
during the quarter
Percentage
interest disposed
during the quarter
WESTERN
AUSTRALIA
BLACK SWAN 4 100% - -
L27/75 100% - -
L27/77 100% - -
L27/78 100% - -
L27/95 100% - -
L27/96 100% - -
M27/200 100% - -
M27/214 100% - -
M27/216 100% - -
M27/39 100% - -
LAKE JOHNSTON 4
E63/2244 5 80% - -
E63/2256 5 80% - -
G63/5 100% - -
G63/8 100% - -
L63/51 100% - -
L63/52 100% - -
L63/55 100% - -
L63/57 100% - -
M63/163 100% - -
M63/282 100% - -
M63/283 100% - -
M63/284 100% - -
M63/292 100% - -
M63/293 100% - -
M63/294 100% - -
E63/2244 5 80% - -
E63/2256 5 80% - -
G63/5 100% - -
G63/8 100% - -
L63/51 100% - -
Page 22 of 29
HRZ QUARTERLY SEPTEMBER 2025
TENEMENT SCHEDULE continued
Prospect/Tenement Notes
Percentage
interest held at
the end of the
quarter
Percentage
interest acquired
during the
quarter
Percentage interest
disposed during the
quarter
WESTERN
AUSTRALIA
LAKE JOHNSTON 4
L63/52 100% - -
L63/55 100% - -
L63/57 100% - -
M63/163 100% - -
M63/282 100% - -
M63/283 100% - -
M63/284 100% - -
M63/292 100% - -
M63/293 100% - -
M63/294 100% - -
M63/522 100% - -
M63/523 100% - -
M63/524 100% - -
WINDARRA 4 100% - -
G38/21 100% - -
L38/118 100% - -
L38/119 100% - -
L38/121 100% - -
L38/122 100% - -
L38/199 100% - -
L38/218 100% - -
L38/220 100% - -
L38/225 100% - -
L39/184 100% - -
L39/221 100% - -
L39/224 100% - -
M261SA 100% - -
M38/1244 100% - -
M38/1245 100% - -
M39/1075 100% - -
Page 23 of 29
HRZ QUARTERLY SEPTEMBER 2025
TENEMENT SCHEDULE continued
Prospect/Tenement
Notes
Percentage
interest held at the
end of the quarter
Percentage
interest acquired
during the quarter
Percentage interest
disposed during the
quarter
JOINT VENTURES
WESTERN AUSTRALIA
YARMANY – GOLD TIGER RESOURCES (AUS) LIMITED
E16/492 6 25% - -
E16/499 6 25% - -
MT THIRSTY – CONICO LTD (FORMERLY AUSTRALIAN COBALT LTD)
E63/1267 7 50% - -
E63/1790 7 50% - -
GLA63/9 7 50% - -
L63/80 7 50% - -
L63/81 7 50% - -
L63/91 7 50% - -
MLA63/669 7 50% - -
P63/2045 7 50% - -
R63/4 7 50% - -
LAKE JOHNSTON – ESSENTIAL METALS
E63/1784 8 80% - -
Notes
(10) Royalty of A$1 per tonne of ore mined and treated from M26/616 is payable to Pamela Jean Buchhorn.
(10) On 18 June 2024, Horizon implemented the merger with Greenstone Resources Limited. The transaction
brought Greenstone’s complementary assets over to Horizon as listed in the above tenement schedule.
(10) Hayes Mining Pty Ltd own 15% interest in P16/3084 to P16/3087.
(10) On 19 February 2025, Horizon implemented the merger with Poseidon Nickel Limited. The transaction brought
Poseidon’s complementary assets over to Horizon as listed in the above tenement schedule.
(10) In December 2023, Poseidon entered into a farm-in agreement with Mantis Resources to earn-in up to 100%
ownership interest in the two tenements which are close proximity to the Lake Johnston Project.
(10) An earn-in JV whereby Gold Tiger Resources (Australia) Limited can earn 90% over 4 stages (4 years) by
spending A$300,000 and paying Horizon A$120,000 non-refundable cash amounts. Gold Tiger Resources
(AUS) Limited has earned a 75% interest, leaving Horizon with a 25% interest.
(10) The Mt Thirsty Cobalt-Nickel-Manganese Project is a large laterite hosted resource, held in a 50:50 joint venture
by Horizon (formerly Greenstone Resources) and Conico Ltd (ASX:CNJ). Conico Ltd is the Joint Venture
manager. The Project is located 16km from the historic mining town of Norseman, Western Australia. 150km
to the north lies Kalgoorlie, the epicentre of the West Australian mining industry and 195km to the south is the
port of Esperance. Access to the site is primarily via the sealed Coolgardie–Esperance Highway, which runs
north-south from Esperance to Kalgoorlie.
(10) E63/1784 is a joint venture between Poseidon (80%) and Essential Metals Limited (20%), Essential Metals has
been acquired by Develop Global Limited.
(10) In August 2023, Horizon entered into an option an