Quarterly Activities Report 30 September 2026
Released
Released
Announcement PDF
Maritana Minerals Limited | ABN 88 007 761 186 | maritanaminerals.com.au | info@maritanaminerals.com.au
Level 4, 1260 Hay Street, West Perth WA 6005 | PO Box 1064, West Perth WA 6872 | +61 8 9386 9534
ASX ANNOUNCEMENT
26 October 2026
QUARTERLY ACTIVITIES REPORT FOR THE PERIOD ENDED
30 SEPTEMBER 2026
HIGHLIGHTS
• All key approvals in place for the Black Swan Processing Hub (BSPH) – Native Vegetation
Clearing Permit (NVCP) granted 19 September 2026, completing the statutory approvals required for
the process plant; first gold remains targeted for H2 CY2027
• Early Works Update
o Focus Demolition has removed all redundant structures from the comminution area
o PCH Civil commenced earthworks for the CIL circuit and associated process infrastructure,
including excavation and replacement of unsuitable ground with engineered selected fill to
achieve the required foundation conditions
• Non-process infrastructure and accommodation
o Flow Water Services continued with the successful borefield refurbishment campaign
o Quick Camps completed the installation of 57-room fly camp rooms bringing the total site
accommodation to 73 rooms to support construction
• Group Mineral Resources increased to 2.15Moz Au and Ore Reserves to 235.6koz Au
o Annual Mineral Resources and Ore Reserves Statement – Gold Ore Reserves up 148% year
on year to 204koz1
o Maiden Rose Hill Underground Ore Reserve of 420kt @ 2.34g/t Au for 31.6koz2
o Burbanks Mineral Resource increased 62% to 13.7Mt @ 1.7g/t Au for 755koz3
• Burbanks Phase 2 drilling completed – 20 holes for ~6,400m; results include 0.48m @ 25.19g/t Au
from 224.63m and 0.76m @ 9.02g/t Au from 231.42m (26HBBD062)4
• Resource conversion drilling advancing
o Boorara RC program completed (119 holes for 17,246m); mineralisation extended below the
planned Pit 4, including 23m @ 1.80g/t Au from 177m and 6m @ 3.68g/t Au from 203m
(BOORD260043)5
o Resource conversion drilling commenced at Coote and Crake
• Wilsons Gold Prospect – maiden 4,000m aircore program completed ~400m from the BSPH; assays
pending
• Windarra Tailings Project – Encore made a positive Final Investment Decision; A$400,000 received
and 3% net smelter return royalty retained (1.5% on Lancefield tailings)
• Corporate
o Elizabeth Jones commenced as Chief Operating Officer on 26 August 2026
o Share registry transitioned to Automic; registered office relocated
o Cash as at 30 September 2026 of A$214.5M
1
ASX Announcement “Annual Mineral Resources and Ore Reserves Statement” 20 August 2026
2
ASX Announcement “Rose Hill Mineral Resource and Maiden Ore Reserve Update” 31 August 2026
3
ASX Announcement “High-Grade Burbanks Deposit Increases 62% to +750koz, Bringing Total Resources to +2.1Moz” 11 September 2026
4
ASX Announcement “Phase 2 Drilling Continues to Extend High-Grade Burbanks Mineralisation” 27 August 2026
5
ASX Announcement “Boorara Mineralisation Extended Below Planned Pit Supporting Potential Resource Growth” 24 September 2026
QUARTERLY REPORT SEPTEMBER 2026
maritanaminerals.com.au Page | 2
Overview
Maritana Minerals Limited (ASX: MRT) (“Maritana” or the “Company”) is pleased to report on its activities for
the quarter ended 30 September 2026.
Maritana’s key objective is near-term gold production through a refurbished BSPH and extensional and
discovery resource upside within its large tenement package of 1,335km² located within the Kalgoorlie and
Coolgardie regions of Western Australia (Figure 1). The Company holds 2.15Moz of gold Mineral Resources,
235.6koz of gold Ore Reserves and a number of multi-commodity assets including the 20.2Moz Ag Nimbus
silver-zinc project.
Figure 1 – Maritana Minerals Tenements and Projects Map
During the quarter, the BSPH progressed from design and planning into active project execution, with multiple
contractors mobilised and Early Works advancing across demolition, bulk earthworks, civil works and ground
foundation works and mill refurbishment. Detailed engineering, planning and long-lead equipment procurement
were ongoing. Significant progress was made in preparing the ROM pad, CIL circuit and associated processing
infrastructure for construction. In parallel, non-processing infrastructure continued to advance to support the
expanding construction workforce and future operations.
The Company’s Mineral Resource and Ore Reserve inventory grew materially. The Annual Mineral Resources
and Ore Reserves Statement was followed by announcements of a maiden Ore Reserve for the Rose Hill
Underground and a 62% increase in the Burbanks Mineral Resource. Drilling activity continued across the
portfolio, with Burbanks Phase 2, the Boorara RC program, the maiden Wilsons aircore program and resource
QUARTERLY REPORT SEPTEMBER 2026
maritanaminerals.com.au Page | 3
conversion drilling commencing at Coote and Crake. Encore’s positive Final Investment Decision on the
Windarra Tailings Project delivered a further cash payment and an ongoing royalty interest.
Black Swan Processing Hub Project Update
Early Works
Construction activities at the BSPH gained momentum during the September quarter, with multiple work fronts
established across the processing plant and associated infrastructure. Under the GR Engineering Services
(GRES) managed Early Works program, site activities focused on demolition, bulk earthworks, ground
foundation improvement and preparation for the refurbishment and construction of the processing facilities.
Civil Works and Ground Improvement
Bulk earthworks commenced across the new CIL circuit, ROM pad expansion and associated infrastructure
areas. Works undertaken by PCH included excavation, preparation of foundation areas and ground
improvement through the removal of unsuitable material and replacement with engineered select fill. These
activities are establishing the foundation conditions required for construction of the new processing facilities.
The revised ROM pad design was also completed, incorporating greater flexibility for receiving, stockpiling and
blending ore from multiple regional mining operations.
Demolition and Plant Refurbishment
Significant progress was made in removing redundant infrastructure to prepare the existing processing plant
for refurbishment and integration with the new facilities. Focus Demolition advanced with the dismantling of
conveyors, transfer towers, ore bins and associated structures, progressively opening up work areas for
subsequent construction activities.
Assessment of the existing milling circuit also progressed, with mechanical inspections and non-destructive
testing undertaken to establish the scope of refurbishment required. The SAG mill was successfully rotated for
the first time in approximately 17 years, representing an important milestone in assessing the condition of the
existing equipment.
Engineering and Procurement
Detailed engineering continued in parallel with site construction activities, with a focus on finalising equipment
requirements, resolving interfaces between new and existing infrastructure and advancing construction-ready
design packages.
Procurement of critical long-lead equipment progressed. Equipment delivery requirements and construction
sequencing continue to be coordinated to support the overall project schedule.
Project Delivery and Contracting
The Early Works program represents approximately A$31.5 million in committed expenditure, including
engineering, construction management, procurement and site execution activities.
Development of the main EPC and reimbursable contracting arrangements continues, alongside refinement of
the capital cost estimate, project schedule and execution strategy.
QUARTERLY REPORT SEPTEMBER 2026
maritanaminerals.com.au Page | 4
Figure 2 – BSPH – demolition of redundant conveyors and structures
Figure 3 – BSPH – Earthworks underway in the Processing area
QUARTERLY REPORT SEPTEMBER 2026
maritanaminerals.com.au Page | 5
Approvals
All statutory approvals required for the construction of the process plant were in place by the end of the quarter:
Table 1 – Statutory Approvals
Approval Regulator Date granted
Mining Development and Closure Proposal (processing facility) DMPE 27 July 2026
Works Approval (CIL circuit) DWER 5 August 2026
Native Vegetation Clearing Permit DMPE 19 September 2026
A further Works Approval covering the tailings storage facility is being prepared, with submission scheduled
for later in 2026.
Non-Process Infrastructure
Development of the supporting infrastructure required for construction and future operation of the BSPH
continued during the quarter, with progress across water supply, power, road access, security and
communications.
• Power Supply: Evaluation of the long-term power supply strategy progressed, with particular focus
on reliability, capacity, capital and operating costs, and delivery timeframes. The assessment includes
dedicated on-site gas generation, existing Goldfields grid connections and hybrid renewable solutions.
Regional grid reliability and available capacity remain important considerations, with on-site generation
being evaluated to provide a reliable and cost-effective long-term supply. Temporary diesel generation
remains under consideration to support commissioning and initial operations, if required.
• Construction Water: Flow Water Services advanced the A$1.3 million refurbishment and upgrade of
the existing borefield infrastructure, including pump, pipeline, power supply and control system works.
Refurbishment, testing and commissioning activities progressed during the quarter to establish a
reliable construction water supply and reduce reliance on water cartage.
• Potable and Process Water: Arrangements for the delivery of potable water to site progressed to
support the expanding construction workforce and accommodation facilities. In parallel, investigations
continued into additional groundwater resources to meet the longer-term process water requirements
of the BSPH. Potential supply areas north of the processing plant and south of the existing borefield
remain under evaluation, together with the infrastructure required to develop and transfer additional
water to site.
• Road Infrastructure: Planning continued for upgrades to the 18km unsealed section of Yarri Road
servicing the BSPH. The proposed approach prioritises improvements to road formation, pavement
condition, drainage and heavy-vehicle access without requiring full bitumen sealing. Engagement with
the City of Kalgoorlie-Boulder continued to progress the scope and delivery arrangements, with
consideration given to increasing construction traffic and future operational haulage requirements.
• Site Access, Security and Communications: Development of the permanent site access
arrangements progressed, including the entrance intersection, security gatehouse and management
of construction and operational traffic. ESN Group continued design of the integrated communications
infrastructure to support the processing plant, administration facilities and accommodation village,
including network connectivity, wireless communications and system reliability.
Accommodation
Accommodation infrastructure expanded significantly during the September quarter, supporting the increasing
construction workforce at the BSPH, while planning and procurement advanced for the Company's longer-
term operational accommodation requirements.
• Construction Accommodation: The expansion of the temporary construction village was completed
during the quarter, increasing installed accommodation capacity to 73 rooms across two stages. The
expansion also included additional supporting facilities comprising wet and dry mess areas, laundry
and recreational amenities, including a gymnasium. The increased capacity provides accommodation
for the growing site workforce as construction activities accelerate.
QUARTERLY REPORT SEPTEMBER 2026
maritanaminerals.com.au Page | 6
• Main Accommodation Village: Development of the permanent accommodation village progressed,
with the initial 60-room facility designed to accommodate future expansion to 120 rooms as operational
requirements increase. OTOC Australia was awarded the construction contract, with accommodation
and kitchen modules sourced from McNally and ATCO. Procurement and delivery planning continued
during the quarter, with major components scheduled to arrive in November 2026 and the village
targeted to become operational from January 2027.
• Kalgoorlie Accommodation: The Company's regional accommodation strategy also progressed
following the acquisition of a property in central Kalgoorlie with existing development approval for a
50-room accommodation facility. The proposed development will support the planned commencement
of mining operations at Boorara, Coote and Crake, providing a centrally located accommodation base
for personnel working across the Company's satellite mining operations. Development is planned to
commence during H1 CY2027.
Mine Development and Operations
MineBuild Global continues to oversee preparation for the restart of mining at the planned initial ore sources
for the BSPH. Contract tendering processes for open pit mining, underground mining and haulage services
are progressing, with contract awards targeted for late 2026 ahead of the planned restart of mining at Boorara
in mid-CY2027.
Cannon Underground Gold Project
The Cannon Underground Gold Project is within Maritana Minerals’ Bulong South gold project located 30km
east-southeast of Kalgoorlie in the Eastern Goldfields region of Western Australia, in granted mining lease
M25/333 (Figure 1). The project forms part of the five year Life of Mine8 plan through the BSPH and is currently
on care and maintenance.
Boorara Gold Project
The Boorara Gold Project is located 17km east of Kalgoorlie-Boulder, adjacent to the Super Pit (Figure 1). The
project remains on care and maintenance following the completion of mining in December 2025. Mining is
targeted to restart in mid-CY2027, ahead of BSPH commissioning and first processing during H2 CY2027.
Stockpiles totalling 460kt at 0.95g/t Au for approximately 14,200oz remain on site and will provide the initial
feed for BSPH commissioning and ramp-up. Resource definition drilling activities during the quarter continued
with assay results pending for remaining drillholes. Results from this drilling will inform the Mineral Resource
update for future Ore Reserve calculations.
Rose Hill Gold Project
Rose Hill is located 0.5km southeast of Coolgardie, approximately 85km from the BSPH. During the quarter
the Company declared a maiden Ore Reserve for the Rose Hill Underground of 420kt at 2.34g/t Au for
31.6koz6, supported by a Pre-Feasibility Study completed by Mining Plus in July 2026 (refer to Mineral
Resources and Ore Reserves section).
Phillips Find Project
The Phillips Find JV completed all five toll treatment campaigns, with the final cash distribution to the Company
currently being calculated.
Exploration and Evaluation
Three drill rigs were operating across the Company's Kalgoorlie and Coolgardie projects in September 2026,
with additional rigs planned to accelerate drilling in the December quarter.
Burbanks – Phase 2 Drilling
Phase 2 drilling at the 100% owned Burbanks Gold Project, located 9km south of Coolgardie, was completed
during the quarter. The program comprised 20 diamond holes for approximately 6,400m, testing extensions of
6
ASX Announcement “Rose Hill Mineral Resource and Maiden Ore Reserve Update” 31 August 2026
QUARTERLY REPORT SEPTEMBER 2026
maritanaminerals.com.au Page | 7
the Burbanks Underground mineralisation beneath the Main Lode and infilling the existing Mineral Resource.
Most holes were collared from neighbouring tenements held by Auric Mining Ltd, by agreement, to improve
intercept angles.
Assay results for the first 11 holes were reported on 27 August 2026. Significant intercepts include7:
• 0.48m @ 25.19g/t Au from 224.63m (26HBBD062)
• 0.76m @ 9.02g/t Au from 231.42m, including 0.38m @ 16.41g/t Au from 231.42m (26HBBD062)
• 2.10m @ 3.33g/t Au from 215.00m (26HBBD054)
• 3.89m @ 2.25g/t Au from 299.11m, including 2.00m @ 3.69g/t Au from 301.00m (26HBBD056)
Intercepts are stated as downhole intervals and, due to the vertical nature of the orebody and restricted collar locations, are commonly,
but not consistently, at a low angle to the mineralisation.
Burbanks Underground is not included in the current BSPH life-of-mine plan8 and represents the Company’s
highest-potential source of life-of-mine extension. Results for the remaining nine holes are pending and will be
incorporated in a further Mineral Resource update in the March 2027 quarter. An RC program testing the
Burbanks South mineralisation is planned for the December 2026 quarter.
Boorara – Resource Definition Drilling
The Boorara RC program, forming part of the approximately 60,000m resource conversion campaign, was
completed during the quarter, comprising 119 holes for 17,246m. Assays for the first 67 holes were reported
on 24 September 2026 and confirm that mineralisation continues below the floor of the planned Pit 4 and
remains open at depth. Significant intercepts include9:
• 23m @ 1.80g/t Au from 177m, including 1m @ 6.88g/t Au from 181m (BOORD260043)
• 6m @ 3.68g/t Au from 203m, including 1m @ 13.87g/t Au from 205m (BOORD260043)
In-fill drill results also support planned mining activities, with significant results including:
• 24m @ 2.38g/t Au from 122m, including 3m @ 4.91g/t Au from 139m (BOORD260058)
• 19m @ 2.32g/t Au from 142m, including 1m @ 4.80g/t Au from 158m (BOORD260042)
• 25m @ 1.88g/t Au from 150m, including 2m @ 10.91g/t Au from 160m (BOORD260045)
• 4m @ 8.52g/t Au from 141m, including 1m @ 29.14g/t Au from 143m (BOORD260039)
• 1m @ 145.07g/t Au from 105m (BOORD260024)
The remaining assays are expected in H2 CY2026 and will be incorporated into an updated Boorara Mineral
Resource Estimate, scheduled for completion in H1 CY2027, with pit optimisation below the current design to
follow.
Coote and Crake – Resource Conversion Drilling
RC and diamond drilling commenced during the quarter at the Coote and Crake gold deposits, located within
the Binduli project area approximately 10km west of Kalgoorlie. Coote and Crake are two of the four initial ore
sources for the BSPH. Drilling is designed to convert Inferred Mineral Resources to the Indicated category to
support Ore Reserve updates and an updated life-of-mine plan and will continue through H2 CY2026.
7
ASX Announcement “Phase 2 Drilling Continues to Extend High-Grade Burbanks Mineralisation” 27 August 2026
8
ASX Announcement “Studies Support Standalone Gold Development in WA Goldfields” 17 February 2026
9
ASX Announcement “Boorara Mineralisation Extended Below Planned Pit Supporting Potential Resource Growth” 24 September 2026
QUARTERLY REPORT SEPTEMBER 2026
maritanaminerals.com.au Page | 8
Figure 4 – Coote and Crake Project diamond drilling
Wilsons Gold Prospect
On 7 August 2026 the Company commenced a 4,000m aircore program at the Wilsons Gold Prospect, located
on a granted Mining Lease approximately 400m from the BSPH. The program is the first dedicated drilling of
a gold-in-soil anomaly of more than 2.5km x 1.5km defined in 202410 over the ground which was historically
explored almost exclusively for nickel. The program was completed safely and samples have been submitted
for assay. The northern extension of the anomaly onto tenure acquired from Nano Metals will be assessed for
subsequent programs based on results returned from the Wilsons drilling.
Acquisitions and Divestments
Windarra Tailings Project – Final Investment Decision
Encore Minerals Pty Ltd (Encore) notified the Company’s wholly owned subsidiary, Poseidon Nickel Pty
Limited (Poseidon), that it had made a positive Final Investment Decision on the Windarra Tailings Project and
exercised its option to proceed to the Development Period under the Heads of Agreement dated 31 July 2024.
Under the agreement:
• Poseidon received a non-refundable payment of A$400,000;
• Encore is responsible for all funding, development, operation, closure and rehabilitation of the project,
using Draslovka’s proprietary glycine leaching technology;
• Maritana is entitled to a 3% net smelter return royalty on production (1.5% on Lancefield tailings); and
• the A$1.6 million Encore rehabilitation bond contribution will be paid on execution of the full form
agreement.
The Company continues to assess the gold prospectivity of the broader Windarra tenure.
Tenement Acquisitions from Nano Metals and Accelerate Resources
The acquisition of 10 (9 granted and 1 in application) tenements surrounding the BSPH from Nano Metals
(A$345,000 cash plus 509,259 shares) was completed, and transferring of the tenements to the Company is
in progress. The 509,259 shares issued to Nano Metals are subject to voluntary escrow until 15 November
2026 (254,629 shares) and 15 February 2027 (254,630 shares).
10
ASX Announcement “Black Swan Gold Targets Expanded and Remain Open” 11 November 2024 (Poseidon Nickel Limited, ASX: POS)
QUARTERLY REPORT SEPTEMBER 2026
maritanaminerals.com.au Page | 9
Mineral Resources and Ore Reserves
As at 30 September 2026, the Group’s gold Mineral Resources total 41.8Mt at 1.60g/t Au for 2.15Moz and
gold Ore Reserves total 4.31Mt at 1.72g/t Au for 235.6koz (refer to Appendices). The movement from the June
2026 quarter reflects three announcements made during the quarter:
Table 2 – Mineral Resources and Ore Reserves ASX Announcements
Announcement Date Outcome
Annual Mineral Resources and Ore
Reserves Statement
20 August 2026
Gold Mineral Resources of 1.86Moz (up 6.3% after depletion); Gold Ore
Reserves of 204koz (up 148%), driven by maiden Crake and Kalpini Ore
Reserves and the updated Boorara Ore Reserve; Lake Johnston divestment
reflected
Rose Hill Mineral Resource and Maiden
Ore Reserve Update
31 August 2026
Rose Hill Underground Mineral Resource re-reported at 1.0g/t Au cut-off:
524kt at 4.49g/t Au for 76koz. Maiden Underground Ore Reserve of 420kt at
2.34g/t Au for 31.6koz. Group Ore Reserves increased to 235.6koz
Burbanks Mineral Resource Update 11 September 2026
Burbanks Mineral Resource of 13.7Mt at 1.7g/t Au for 755koz, an increase
of 290koz (62%); open pit 10.6Mt at 1.45g/t Au for 496koz and underground
3.1Mt at 2.63g/t Au for 259koz. Group Mineral Resources increased to
2.15Moz
Annual Statement11
The annual statement reported Mineral Resources and Ore Reserves for the 12 months ended 30 June 2026.
Material changes from the prior year were mining depletion at Boorara and Phillips Find; the review of
reasonable prospects for eventual economic extraction at Kalpini, Crake, Coote, Golden Ridge North, Jacques-
Peyes and Gordons Dam (re-reported at a 0.5g/t Au cut-off); maiden Ore Reserves for the Crake and Kalpini
open pits and an updated Boorara open pit Ore Reserve; and the divestment of the Lake Johnston Nickel
Project.
Rose Hill
The maiden Rose Hill Underground Ore Reserve (1.0g/t Au cut-off) comprises Proved 70kt at 2.14g/t Au for
4.7koz and Probable 350kt at 2.37g/t Au for 26.8koz, underpinned by a Pre-Feasibility Study completed by
Mining Plus in July 2026. A further 194kt at 4.53g/t Au for 28koz of Inferred Mineral Resource was excluded
from the Ore Reserve and offers upside at depth. The open pit Mineral Resource is unchanged at 287kt at
1.99g/t Au for 18koz.
Burbanks
The updated Burbanks Mineral Resource incorporates the 53-hole, 15,798m Phase 1 program and the
Burbanks North drilling. It is reported at a 0.5g/t Au cut-off above 180mRL (open pit) and 1.0g/t Au below
180mRL (underground). Growth was tonnage-driven and almost entirely within Burbanks North, which
increased to 11.1Mt at 1.47g/t Au for 523koz, with a further 10koz from the new Galaxias open pit area (Figure
5). Indicated material now represents 29% of contained gold. Mineralisation is defined to approximately 450m
below surface at Main Lode and Birthday Gift and remains open at depth and along strike. No Ore Reserve
has been declared for Burbanks. Ore Reserve studies will now follow.
11
ASX Announcement “Annual Mineral Resources and Ore Reserves Statement” 20 August 2026
QUARTERLY REPORT SEPTEMBER 2026
maritanaminerals.com.au Page | 10
Figure 5 – Burbanks Mineral Resource bridge, 2023 to 2026 (contained gold)12
Corporate/Finance
The Company remains well funded, with total cash at bank as at 30 September 2026 of A$214.5M (30 June
2026: A$229.5M).
During the quarter the Company received a non-refundable payment of A$400,000 from Encore in respect of
the Windarra Tailings Project.
Exploration and evaluation expenditure during the quarter was A$5.5M, comprising drilling at Burbanks,
Boorara, Coote, Crake and Wilsons, assaying and associated costs.
Mine development and BSPH expenditure during the quarter was A$5.3M, comprising Early Works, long-lead
procurement, non-process infrastructure and accommodation.
A$493,045 was paid to related parties or their associates during the quarter comprising Directors’ remuneration
and payments to entities associated with Mr Ashok Parekh for office rental and accommodation.
The Company’s capital structure and Listed Company Investments at 30 September 2026 are set out in Table
3 and Table 4 respectively.
Table 3 – Capital Structure at 30 September 2026
ASX Code Class of Securities On issue 30 September 2026
MRT Fully Paid Ordinary Shares 372,883,195
MRTAN Performance Rights 3,166,861
MRTAA Unlisted Options Expiring 30 Sep 2028 Exercisable at A$1.80 400,002
Table 4 – Listed Company Investments
Company Number Value 30 September 2026
Richmond Vanadium Technology 19,833,363 ¹ A$1,983,336
Metal Hawk Limited 1,134,430 ¹ A$153,148
Dundas Minerals Limited 3,234,327 ¹ A$161,717
TOTAL A$2,298,201
¹ Liquid asset
12
ASX Announcement “High-Grade Burbanks Deposit Increases 62% to +750koz, Bringing Total Resources to +2.1Moz” 11 September 2026
QUARTERLY REPORT SEPTEMBER 2026
maritanaminerals.com.au Page | 11
Share Registry
Effective 20 July 2026, the Company changed its share registry provider from Computershare to Automic Pty
Ltd. Shareholders can manage their holdings via https://investor.automic.com.au or contact Automic on 1300
288 664 (within Australia) or +61 2 9698 5414 (outside Australia).
Change of Registered Office and Principal Place of Business
Effective 21 September 2026, the Company’s registered office and principal place of business changed to
Westcentre, Level 4, 1260 Hay Street, West Perth WA 6005. The Company’s telephone number is unchanged.
Chief Operating Officer
Elizabeth “Liz” Jones commenced as Chief Operating Officer on 26 August 2026, following her appointment
announced on 4 June 2026. Ms Jones brings over 30 years’ experience in underground and open pit mining
operations and will lead the Company’s transition to gold producer.
Annual Report
The Company released its 2026 Annual Report, including the audited financial statements for the year ended
30 June 2026, and its Appendix 4G and Corporate Governance Statement on 24 September 2026. The Annual
General Meeting will be held on 27 November 2026.
Authorised for release by the Board of Directors.
For further information, please contact:
Grant Haywood
Managing Director and CEO
grant.haywood@maritanaminerals.com.au
+61 8 9386 9534
Michael Vaughan
Investor and Media Relations – Fivemark
michael.vaughan@fivemark.com.au
+61 422 602 720
QUARTERLY REPORT SEPTEMBER 2026
maritanaminerals.com.au Page | 12
Forward Looking and Cautionary Statements
Some statements in this report regarding estimates or future events are forward looking statements. They
include indications of, and guidance on, future earnings, cash flow, costs and financial performance. Forward
looking statements include, but are not limited to, statements preceded by words such as “planned”,
“expected”, “projected”, “estimated”, “may”, “scheduled”, “intends”, “anticipates”, “believes”, “potential”, “could”,
“nominal”, “conceptual” and similar expressions. Forward looking statements, opinions and estimates included
in this announcement are based on assumptions and contingencies which are subject to change without notice,
as are statements about market and industry trends, which are based on interpretations of current market
conditions. Forward looking statements are provided as a general guide only and should not be relied on as a
guarantee of future performance. Forward looking statements may be affected by a range of variables that
could cause actual results to differ from estimated results and may cause the Company’s actual performance
and financial results in future periods to materially differ from any projections of future performance or results
expressed or implied by such forward looking statements. These risks and uncertainties include but are not
limited to liabilities inherent in mine development and production, geological, mining and processing technical
problems, the inability to obtain any additional mine licenses, permits and other regulatory approvals required
in connection with mining and third party processing operations, competition for among other things, capital,
acquisition of reserves, undeveloped lands and skilled personnel, incorrect assessments of the value of
acquisitions, changes in commodity prices and exchange rate, currency and interest fluctuations, various
events which could disrupt operations and/or the transportation of mineral products, including labour stoppages
and severe weather conditions, the demand for and availability of transportation services, the ability to secure
adequate financing and management’s ability to anticipate and manage the foregoing factors and risks. There
can be no assurance that forward looking statements will prove to be correct.
Statements regarding plans with respect to the Company’s mineral properties may contain forward looking
statements in relation to future matters that can only be made where the Company has a reasonable basis for
making those statements.
This announcement has been prepar
Share your feedback