Black Swan Processing Hub Construction on Track
Released
Released
Announcement PDF
Maritana Minerals Limited | ABN 88 007 761 186 | maritanaminerals.com.au
PO Box 1064, West Perth WA 6872 | +61 8 9386 9534 | info@maritanaminerals.com.au
ASX: MRT
ASX ANNOUNCEMENT
11 November 2026
BLACK SWAN PROCESSING HUB CONSTRUCTION ON TRACK
Maritana Minerals Limited (ASX: MRT) (“Maritana” or “the Company”) is pleased to provide an update on
construction activities at its 2.5Mtpa Black Swan Processing Hub (“BSPH”), located approximately 50km
northeast of Kalgoorlie in the Western Australian Goldfields.
HIGHLIGHTS
• Early Works – the early works agreement with GR Engineering Services (GRES) has been extended
to sustain site execution and procurement while the Engineering, Procurement and Construction
(EPC) and Reimbursable Contract is finalised
• Demolition – demolition of the coarse ore handling system has been completed
• Carbon in Leach (CIL) Circuit – construction of the first CIL tank ring-beam foundations have
progressed to concrete placement with the tank strakes being canned up in the laydown area
o Approvals & permits – all statutory approvals required for construction of the BSPH process
plant are in place
o Grinding Circuit – SAG mill liner removal and preparation for refurbishment are progressing
well alongside the primary crusher dismantling and existing-plant works
o ROM Pad – bulk earthworks, cut-to-fill operations and access works are underway on the
ROM pad expansion
• Long lead items – orders for the regeneration kiln, electrowinning cells and slurry samplers were
progressed during October 2026; with procurement negotiations well advanced for elution columns,
bolted CIL tanks, intertank screens and platework
• Tailings Facilities – a planned lift of the existing tailings storage facility is designed to provide
approximately three years of processing capacity, allowing a new facility to be developed in parallel
• Key Operational Appointment – Chris Mardon (ex-Mineral Mining Services, Focus Minerals and
Mineral Resources) has been appointed General Manager Operations to lead operational readiness
and the transition from project delivery through to commissioning and into operations
• Mining – mining restart at Boorara is targeted for mid-2027, with the 60,000 metre resource conversion
campaign continuing across the Kalgoorlie Eastern Hub deposits
maritanaminerals.com.au Page | 2
Managing Director and CEO comment
Mr Grant Haywood, Managing Director and CEO:
“The commencement of concrete works for the new CIL circuit is another visible step forward at the BSPH.
With the principal demolition program complete, SAG mill liner removal underway and the ROM pad expansion
progressing, the site is moving steadily from preparation into construction. Extending the early works
agreement with GRES maintains that momentum while we finalise the EPC contract, and long-lead
procurement continues to advance.”
“Our staged tailings strategy, built on a lift of the existing TSF4, is planned to provide around three years of
processing capacity and de-risks the path to first gold, while the appointment of Chris Mardon as General
Manager Operations strengthens our readiness to move from construction into operations. This is more than
a plant refurbishment: we are building a regional gold processing hub for multiple Kalgoorlie ore sources,
targeting first gold in H2 CY2027.”
Figure 1 – Overall Site Layout and Progress
CIL Circuit (new)
Grinding Circuit
Existing Process Plant
ROM Pad & Primary Crusher Area
maritanaminerals.com.au Page | 3
Early Works Extension and Long-Lead Items
The early works agreement with GRES, announced on 20 July 2026 with a committed expenditure of A$31.5
million to 31 October 2026, has been extended to 31 December 2026. The extension, at an additional
committed cost of A$19.9 million, maintains continuity of detailed engineering, long-lead time procurement
items and bulk earthworks on site while the EPC contract for the process plant is finalised. Long-lead
procurement is advancing, including the CIL bolted tanks, intertank screens, regeneration kiln, structural and
platework packages, concrete and electrical packages including VSDs, MV switchgear, switchrooms,
transformers and Motor Control Centres.
BSPH Update
CIL Circuit Construction
Construction of the CIL foundations follows the bulk earthworks and ground-improvement program undertaken
to establish suitable foundation conditions for the new processing infrastructure. Progressive release of the
CIL area work fronts is enabling concrete construction to overlap with fabrication and preparation for tank
erection, moving a major new component of the gold processing circuit into physical construction.
Civitech commenced construction of the new CIL tank ring-beam foundations during October 2026, completing
reinforcement and formwork for the first ring beam and commencing concrete placement. Further tank-
foundation works and CIL tank erection are being prepared as construction fronts become available.
Figure 2 – CIL tank ring-beam foundation concrete and formwork
maritanaminerals.com.au Page | 4
Figure 3 – Overhead aerial view of CIL progress
Figure 4 – CIL relation to the existing processing facility
maritanaminerals.com.au Page | 5
Demolition and Process Plant Refurbishment
The principal demolition scope for redundant front-end infrastructure was completed during October 2026, with
Focus Demolition demobilising by end of month. Completion of demolition has released areas for the new
conveyors, regrind circuit and supporting infrastructure. GRES continues removal and refurbishment activities
in the existing processing plant, including dismantling of the primary crusher, removal of redundant equipment
and electrical infrastructure, and preparation of the mill building.
Figure 5 – Demolition of redundant front-end infrastructure in preparation for new ore handling systems
SAG Mill liner removal
Specialised Reline Services commenced SAG mill liner removal in October using dedicated relining
equipment. A Letter of Award has been issued to Hofmann Engineering for specialist SAG mill refurbishment
works. Planning for refurbishment of the grinding circuit continues alongside design and construction of the
new gold processing circuits.
The existing SAG mill was successfully rotated earlier in the assessment program for the first time in
approximately 17 years, marking an important mechanical milestone. Liner removal and further inspection are
now enabling the detailed refurbishment scope to be progressed, while redundant cabling, equipment and grid
mesh within the mill building are being removed or replaced to prepare the area for follow-on works.
maritanaminerals.com.au Page | 6
Figure 6 – Grinding Circuit – Ball and SAG mill preparation
ROM Pad and Bulk Earthworks
PCH Civil is progressing the ROM pad extension and associated access works, including bulk cut-to-fill, rock
placement and engineered fill across the process plant areas.
The revised ROM pad design supports the planned hub-and-spoke operating model, providing for the receipt,
separate stockpiling and blending of ore from multiple regional mining operations. The expansion is an
important part of preparing Black Swan for a range of ore sources from its satellite deposits.
Figure 7 – ROM Pad extension work progress
maritanaminerals.com.au Page | 7
Tailings Storage – Staged Development Strategy
An additional lift of the existing BSPH tailings storage facility TSF4 is about to go out to tender. Leveraging this
established and permitted infrastructure de-risks the commencement of gold processing. Once completed, the
lift is planned to provide sufficient tailings storage capacity for approximately three years of processing at the
BSPH.
This staged approach reduces the project’s near-term dependence on the design, permitting and construction
of a new tailings storage facility. It provides a practical operating window in which the next tailings facility, TSF5,
can be designed, progressed through the required approvals and constructed to support the longer-term
operating life of the BSPH.
Figure 8 – Tailings Storage Facility 4
maritanaminerals.com.au Page | 8
Authorised for release by the Board of Directors.
For further information, please contact:
Grant Haywood Michael Vaughan
Managing Director and CEO Investor and Media Relations – Fivemark
grant.haywood@maritanaminerals.com.au michael.vaughan@fivemark.com.au
+61 8 9386 9534 +61 422 602 720
JOIN MARITANA MINERALS INTERACTIVE HUB
Visit https://maritanaminerals.com.au/auth/signup for
Maritana Minerals’ Interactive InvestorHub
MARITANA MINERALS
Email: info@maritanaminerals.com.au
maritanaminerals.com.au Page | 9
Figure 9 – Maritana Minerals Production Hub and project locations, regional geology and surrounding
infrastructure1
1
Refer ASX Announcement “Annual Mineral Resources and Reserves” 20 August 2026 and “Amended Rose Hill Mineral Resource and
Maiden Reserve Update” dated 3 November 2026
maritanaminerals.com.au Page | 10
Forward Looking and Cautionary Statements
Some statements in this report regarding estimates or future events are forward looking statements. They
include indications of, and guidance on, future earnings, cash flow, costs and financial performance. Forward
looking statements include, but are not limited to, statements preceded by words such as “planned”,
“expected”, “projected”, “estimated”, “may”, “scheduled”, “intends”, “anticipates”, “believes”, “potential”, “could”,
“nominal”, “conceptual” and similar expressions. Forward looking statements, opinions and estimates included
in this announcement are based on assumptions and contingencies which are subject to change without notice,
as are statements about market and industry trends, which are based on interpretations of current market
conditions. Forward looking statements are provided as a general guide only and should not be relied on as a
guarantee of future performance. Forward looking statements may be affected by a range of variables that
could cause actual results to differ from estimated results and may cause the Company’s actual performance
and financial results in future periods to materially differ from any projections of future performance or results
expressed or implied by such forward looking statements. These risks and uncertainties include but are not
limited to liabilities inherent in mine development and production, geological, mining and processing technical
problems, the inability to obtain any additional mine licences, permits and other regulatory approvals required
in connection with mining and third party processing operations, competition for, among other things, capital,
acquisition of reserves, undeveloped lands and skilled personnel, incorrect assessments of the value of
acquisitions, changes in commodity prices and exchange rate, currency and interest fluctuations, various
events which could disrupt operations and/or the transportation of mineral products, including labour stoppages
and severe weather conditions, the demand for and availability of transportation services, the ability to secure
adequate financing and management’s ability to anticipate and manage the foregoing factors and risks. There
can be no assurance that forward looking statements will prove to be correct.
Statements regarding plans with respect to the Company’s mineral properties may contain forward looking
statements in relation to future matters that can only be made where the Company has a reasonable basis for
making those statements.
This announcement has been prepared in compliance with the JORC Code (2012) and the current ASX Listing
Rules.
The Company believes that it has a reasonable basis for making the forward-looking statements in the
announcement, including with respect to any production targets and financial estimates, based on the
information contained in this and previous ASX announcements.