Pennys Find Pre-Feasibility Study and Ore Reserve
Released
Released
Announcement PDF
ASX: HRZ
ASX ANNOUNCEMENT
18 DECEMBER 2024
PENNYS FIND PREFEASIBILITY STUDY AND ORE RESERVE
HIGHLIGHTS
•
Prefeasibility Study (PFS) for Pennys Find completed and shows a financially viable project
highlighted by the following:
o
Underground mine design and schedule producing 329.9kt at a fully diluted grade of
3.2g/t Au for 33.5koz over an approximate 23 month mine life
o
Metallurgical recovery of 88.9% produces 29.8koz recovered under an assumed third
party toll milling arrangement in the region
o
Project generates $24.0M in free cash flow (after capital) at a gold price of A$3,600/oz
•
A maiden Ore Reserve, which constitutes 99.7% of the ounces in the production target in the
PFS, stands at 328.3kt at 3.2g/t Au for 33.4koz
•
Pennys Find is fully permitted with all statutory approvals in place
•
PFS assumes contract mining and haulage, with management and technical services
provided by Horizon
•
Pennys Find is one of several near-term development projects held by Horizon and will be
ranked and assessed alongside the Cannon and Kalpini projects for potential processing
through third party infrastructure or the wholly owned processing infrastructure to be acquired
under the proposed merger with Poseidon 1,2
Commenting on the PFS and Ore Reserve, Managing Director and CEO Mr Grant Haywood said: 2
“We are very pleased to have the study work completed on another development ready project. The
Pennys Find underground PFS shows robust cashflows from a high-grade gold asset that is fully
permitted that we can develop when we are ready.
“Horizon has strong optionality within its large pipeline of projects, with mining currently underway at
Boorara and Phillips Find, with Cannon and now Pennys Find studies completed allowing the
potential to generate more cash in this strong gold price environment.”
Cautionary Statement
The Prefeasibility Study (PFS) referred to in this announcement is based on Proven and Probable Ore Reserves derived from
Measured and Indicated Mineral Resources. No inferred Resource material has been included in the estimation of Ore Reserves.
The Company advises that Proven and Probable Ore Reserves provide 99.5% of the total tonnage and 99.7% of the total gold metal
underpinning the forecast production target and financial projections. There is 0.5% of the tonnage and 0.3% of the total gold metal
that make up the Production Target that are Inferred Mineral Resources in the PFS. There is a low level of geological confidence
associated with inferred mineral resources and there is no certainty that further exploration work will result in the determination of
indicated mineral resources or that the production target itself will be realised (refer Appendix 1 and Forward Looking and Cautionary
Statements on Pages 18-19).
Horizon has concluded it has reasonable basis for providing the forward looking statements included in this announcement (see
pages 18-19). The detailed reasons for that conclusion are outlined throughout this announcement and Material Assumptions are
disclosed in Appendix 1. This announcement has been prepared in accordance with the JORC Code. (2012) and the ASX Listing
Rules.
1
As announced to the ASX on 25 August 2024. 2 See Forward Looking and Cautionary Statements on Page 18 and JORC tables on
Page 19 and ASX disclosures on page 8.
Level 2, 16 Ord Street
West Perth WA 6005
PO Box 1064
West Perth WA 6872
T: +61 8 9386 9534
E: info@horizonminerals.com.au
horizonminerals.com.au
ACN 007 761 186
ABN 88 007 761 186
ASX ANNOUNCEMENT
Overview
Horizon Minerals Limited (ASX: HRZ) (“Horizon” or the “Company”) is pleased to announce the
results of the Prefeasibility Study (“PFS” or “Study for the Company’s 100% owned Pennys Find
project, located in the heart of the Western Australian goldfields (Figure 1).
Figure 1: Horizon’s project locations and mineral resources, regional geology and
surrounding infrastructure
Pennys Find Overview
The Pennys Find Gold Project is located 50km northeast of Kalgoorlie-Boulder (Figure 1) and is
accessed via public roads.
The high-grade gold mineralisation at Pennys Find is hosted in thin quartz veins at the contact
between footwall sediments including black shale and siltstone and a hangingwall basalt. The quartz
veins dip about 60° to the northeast, and collectively average 1m to 5m true width.
Open cut mining to 85m depth (242mRL) was completed by Empire Resources in 2018 with toll
treatment processing at Lakewood (Kalgoorlie) and Burbanks (Coolgardie). Production from the
open pit totalled more than 18,300oz at 4.47g/t Au (as announced to the ASX by Empire (ASX: ERL)
on 25 July 2018).
Page 2 of 41
ASX ANNOUNCEMENT
Metallurgical test work and toll milling data has shown fresh mineralisation to be free milling with a
high gravity recoverable gold component and a total gold recovery which has historically exceeded
90%. Horizon has used a metallurgical recovery of 88.9% for this study.
The Mineral Resource Estimate (JORC 2012) for Pennys Find is shown below: 1
Table 1: Pennys Underground (<260mRL) Mineral Resource Estimate, 1.5g/t Au cut off
Pennys Find at 0.5g/t Au lower cut-off grade
Resource category
Tonnes (kt)
Grade (g/t Au)
Gold Metal (koz)
Indicated
305
5.19
51
Inferred
123
3.02
12
Total
429
4.57
63
The Mineral Resource has three domains (Figure 2). Domain 1 contains most of the Mineral
Resource with good drilling support. Domain 2 is a subparallel lode, possibly a splay, that to date is
only represented in limited drilling. Domain 3 is similarly a subparallel lode, but with minimal drilling
support.
Figure 2: Pennys Find long section of Pennys Find deposit (azimuth 262˚) showing
mineralised domains, topography and pit void.
Due to the confidence and classification of Domain 2 as Inferred Mineral Resources and small nature
of Domain 3, only Domain 1 was used for the PFS.
1
As announced to the ASX on 1 August 2024 and see JORC tables on Page 19.
Page 3 of 41
ASX ANNOUNCEMENT
Pennys Find Prefeasibility Study
The Study was undertaken by a combination of in-house personnel and independent consultants.
Advanced Mining Production Systems (AMPS) was engaged by Horizon to carry out works for
inclusion in a Mining PFS for the Pennys Find Underground project inclusive of mine optimisation
and design, scheduling and economic analysis. MineGeoTech carried out a geotechnical Feasibility
Study to establish the structural environment and rock mass quality of the project, and utilising this
data, ground support requirements, stope stability and numerical modelling was completed. Various
metallurgical studies have been undertaken by previous owners and more recently via Independent
Metallurgical Operations under Horizon. Soil Water Group carried out Hydrology and Hydrogeology
work and environmental study work carried out by Botanica Consulting.
All remaining study work was undertaken and overseen by Horizon and is based on the following
key parameters:
•
Gold price of A$3,600/oz
•
Underground mining and road haulage conducted by contractors with management and
technical oversight by Horizon
•
Ore processing through a standard Carbon in Leach (CIL) third party processing plant in the
Kalgoorlie region, within 100km of Pennys Find
•
There is no material financing required for capital development of the project at this stage as
the Company is mining its Boorara and Phillips Find open pit projects, and it is anticipated
that current cash and cashflows from those projects shall fund this development
The key Study outcomes for the project are included in Table 2 below: The estimated Ore Reserve,
which constitutes 99.7% of the production target, has been prepared by Competent Persons in
accordance with JORC Code 2012.1
Table 2: Summary of Prefeasibility Study key outcomes 1
1
Measure
Lateral development (m)
Outcome
4,775
Vertical development (m)
1,847
Development ore (kt)
99.5
Stoping ore (kt)
230.4
Total ore mined (kt)
329.9
Gold grade (g/t Au)
3.2
Milling recovery (%)
88.9%
Recovered gold (oz Au)
29,812
Total revenue (A$M at A$3,600/oz)
Capital costs (A$M including
development)
Operating costs (A$M)
107.3
All in sustaining costs (A$/oz recovered)
2,794
Free cashflow (A$M at A$3,600/oz)
24.0
NPV (A$M at 5% discount rate)
21.4
23.8
59.5
See Forward Looking and Cautionary Statements on Page 18 and JORC tables on Page 19 and ASX disclosures on page 8.
Page 4 of 41
ASX ANNOUNCEMENT
Horizon conducted the Study as of 17 December 2024. The Study, prepared with an accuracy
of ±15%, considered all relevant mining modifying factors, allowing an Ore Reserve to be
estimated in accordance with the JORC Code. Classification of the estimate is shown in Table 3.
Table 3: Ore Reserve Statement (see Appendix 1) 1
Reserve Category
Tonnes (kt)
Grade (g/t Au)
Gold Metal (koz)
Proven
0
0
0
Probable
328.3
3.2
33.4
Total
328.3
3.2
33.4
All Inferred Resources were excluded from the stope optimisation process and in the financial
modelling and the estimation of Ore Reserves. The Pennys Find Indicated and Inferred Mineral
Resources are inclusive of those Mineral Resources modified to produce the Pennys Find PFS that
can be economically mined by underground methods. The Ore Reserves make up 99.7% of the
production ounces in the PFS.
The information presented in this announcement is based on, and fairly represents, information and
supporting documentation prepared by Mr Grant Haywood. Mr Haywood continues to be the
Competent Person for the 18 December 2024 Pennys Find Ore Reserve estimate, and supervised
and reviewed preparation of the estimate with assistance from specialists in each area of the
estimate. Mr Haywood is a Fellow of the Australasian Institute of Mining and Metallurgy and is
employed by Horizon. He has sufficient experience relevant to the style of mineralisation, type of
deposit under consideration, and in underground mining activities, to qualify as a Competent Person
as defined in the JORC Code. Mr Haywood consents to the inclusion of this information in the form
and context in which it appears.
The Probable Ore Reserve estimate is based on Mineral Resources classified as Indicated, after
consideration of all mining, metallurgical, social, environmental, statutory and financial aspects of
the project.
Financial analysis undertaken in December 2024 shows that, at 17 December 2024, the future
revenues to be derived and costs incurred to access those revenues produce a viable project using
the assumptions presented in this estimate.
A sensitivity analysis was conducted as part of the assessment for the reserve, the results are
displayed in Figure 3.
1
See Forward Looking and Cautionary Statements on Page 18 and JORC tables on Page 19 and ASX disclosures on page 8.
Page 5 of 41
ASX ANNOUNCEMENT
Variance in undiscounted Cashflow
50.00
45.00
40.00
Net Cashflow
35.00
30.00
25.00
20.00
15.00
10.00
5.00
-20%
-10%
0
10%
20%
Percentage Change in Variable
Capex
Opex
Gold Price
Figure 3: Sensitivity analysis on input variables against net cashflow
Operational activities shall be undertaken by a mining contractor with technical and managerial
oversight provided by Horizon. Mining will be underground with access via a portal within the pit to
develop a decline to the base of the mine, with lateral ore drives developed from the decline. The
mining method will be a bottom-up method using longhole stoping via a modified Avoca method with
Cemented Rockfill (CRF). Ore and waste shall be loaded out by conventional diesel-powered LoadHaul-Dump (LHD) loaders and low profile trucks. Development will be undertaken with Jumbo Drills
and stoping with Longhole drills.
Following pre-production activities, which includes dewatering the existing open pit for a period of
five months, the portal shall be established in the south-eastern quadrant of the open pit.
Development will occur over a period of 13 months, with ore development commencing in month
three and stoping operations commencing in month five.
The stope outlines can be seen in Figure 4 below.
Page 6 of 41
ASX ANNOUNCEMENT
Figure 4: Horizon’s Pennys Find Finalised Stopes
Authorised for release by the Board of Directors
For further information, please contact:
Grant Haywood
Managing Director and CEO
Tel: +61 8 9386 9534
grant.haywood@horizonminerals.com.au
Michael Vaughan
Media Relations – Fivemark Partners
Tel: +61 422 602 720
michael.vaughan@fivemark.com.au
Page 7 of 41
ASX ANNOUNCEMENT
Listing Rule 5.9 Disclosures
Pennys Find Gold Project
Material Assumptions and Outcomes
The PFS was completed with the following material assumptions:
Underground mining operations and road haulage conducted by contractors
•
Ore processing via toll milling and ore haulage within 100km of the project
•
Project implementation and oversight by Horizon management and technical team in
conjunction with contractors
•
Mining and surface ore haulage costs were sourced from reputable contractors
•
Processing costs based on toll treatment rates as provided in the Toll Milling and Ore
Purchase Agreements the Company has with a third party with milling infrastructure in
close proximity to Pennys Find.
•
Detailed metallurgical test work from samples collected from drilling representing ore
domains within the project, and open pit ore treated at Golden Mile Milling’s Lakewood
Plant in 2017. In relation to metallurgical recovery, a tail grade of 0.35g/t was used,
which on the head grade of 3.2g/t is 88.9%, which is conservative compared to the
testwork and previous treatment campaigns
•
Mineable stope shapes were designed, producing stopes. Dilution modelling is based
on the geotechnical recommendations of 0.5m overbreak Equivalent Linear Overbreak
Slough (ELOS) on both the footwall (FW) and hanging wall (HW). Average dilution for
the stoping set is approximately 43% which has a significant effect on recovered grade
based on a minimum mining width of 2.0m and the HW and FW dilution applied.
•
All Inferred Resources were excluded from the stope optimisation process in the
financial modelling and the estimation of Ore Reserves
•
An Australian dollar gold price of $3,600 per ounce was applied. WA state and private
royalties were subtracted from the gold price as part of the optimisation process.
Royalties are payable to Empire Resources that include a 5% NSR on the first 50,000oz
of Au produced and thereafter a 2.5% NSR royalty for life of mine.
•
Bulk densities were derived from test work
•
A lower cut-off grade of 2.65g/t was applied to determine economic stopes in the design
•
A discount factor of 5% has been used due to the short life of the project
The cost estimate can be considered to align with an expected estimation accuracy of ±15%,
primarily due to the use of the use of contractor quotes. Financial modelling activities were
undertaken inhouse by Horizon and quoted as a modifying factor in support of the Ore Reserve
statement.
Project financing was considered by Horizon, with this project planned to be developed from current
operational cashflows from mining of the Boorara and Phillips Find projects currently in production.
Page 8 of 41
ASX ANNOUNCEMENT
As reported in the quarterly reports for the period end 30 September 2024, the Company had ~$1.5M
on hand plus $7.6M in listed investments which will be released from escrow at various dates over
the next month. Subsequent to the September 2024 quarterly report, the Company raised $14M as
announced on 25 October 2024, and aims to generate $30M in free cashflow at A$3,600/oz from its
Boorara asset over the course of the next 18 months as announced on 29 July 2024.
In summary the Company is satisfied, that the level of work (including the project financial model),
can be considered appropriate, to support the quotation of the Ore Reserve statement, with quoted
level of accuracy in the supporting technical and financial studies, of ±15%.
Key outcomes of the study are shown in Table 2 above and Figure 5.
Free Cash Flow - Monthly & Cumulative
30
25
20
AUD $M)
15
10
5
-
(5)
(10)
(15)
(20)
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
Production Period
Free Cash Flow (M)
Cumulative Free Cash Flow (M)
Figure 5: Monthly and Cumulative cashflows by month
Criteria for Classification
The Competent Person has reviewed the modelling methodology and Mineral Resource Estimate
that was applied to the block model developed in 2023.
No Measured Resources were available for conversion to Proven Reserves. Indicated Mineral
Resources have been converted to Probable Ore Reserves. The Ore Reserves consist of 100%
Probable Reserves.
The Competent Person is satisfied that the stated Ore Reserve classification reflects the outcome of
technical and economic studies.
The confidence in the Ore Reserve is reflected by the classifications shown above. In general, the
project’s geology is well understood and confidence in the Mineral Resource interpretation is good.
Mining Method and Assumptions
A number of methods were assessed using the UBC selection method (Miller-Tait et al, 1995), with
the primary mining method chosen for the underground resource at Pennys Find being Avoca
stoping with unconsolidated rockfill and in poorer ground conditions a modified Avoca method will
Page 9 of 41
ASX ANNOUNCEMENT
be deployed utilising a combination of rock fill and Cemented Rock Fill (CRF), which is consistent
with the geotechnical study on managing ground conditions at Pennys Find.
The following cement content values were used in the schedule for CRF placement:
•
2.5% cement content for stope widths less than 5m
•
5.0% cement content for stope widths 5m or greater
•
8.0% cement content for CRF sill pillars
Waste development excavations are given a 10% overbreak. No further dilution factors or mining
recovery factors have been applied to development ore. For stoping dilution, the final stope set was
assessed against the Equivalent Linear Overbreak Slough (ELOS) modelling as highlighted above,
and strike length adjusted based on recommendations. Minimum and maximum strike lengths for
the stope set are 10m and 25m, respectively.
The sublevel spacing is 20m floor to floor which is considered appropriate for the orebody geometry,
average dip, and width. Figure 6 shows the methodology of applying the dilution with the ELOS.
The final stope sets with diluted grades can be seen in Figure 7. The mined ounces and feed grade
for the project can be seen in Figure 8.
Figure 6: Dilution Methodology
Page 10 of 41
ASX ANNOUNCEMENT
Figure 7: Set showing Diluted Grade
Period (Month)
Figure 8: Mined Ounces and Feed Grade
Page 11 of 41
ASX ANNOUNCEMENT
Processing Method and Assumptions
Pennys Find ore will be processed offsite through similar toll milling or ore purchase agreements that
the Company has currently in place. The ore will be processed by standard Carbon in Leach (CIL)
processes.
Ore Reserves are based on a metallurgical recovery using a tail grade of 0.35g/t, which equates to
88.9%, which is consistent with historical performance of the Pennys Find open pit fresh ore during
2017 at the Lakewood Mill. There are black shales adjacent to some sections of the orebody.
Testwork by Horizon in 2021 showed that it was not significantly preg-robbing with no material
deleterious affects. Any potential impact has been built into the recovery factors used.
Cut-off grades or quality parameters
A cut-off grade has been calculated and applied based on forecast costs and modifying factors for
the Life-of-Mine plan. A conservative gold price of A$2,900/oz was utilised by AMPS Pty Ltd in this
cut-off calculation to determine viable ore with A$3,600/oz used in financial modelling.
The three COG calculations are used to finalise the stoping set and development to be used in the
mine design. A fully costed COG is also calculated based on the results of the cost model output.
Economic Stope Design Au Cut-off Recovered grade:
2.65g/t Au
Incremental Stope Design Au Cut-off Recovered grade
2.10g/t Au
Incremental Development Cut-off Recovered grade
0.88g/t Au
Dilution refers to the contamination of ore with waste rock, or other undesired materials, that are
unintentionally extracted along with the desired ore during the mining process. Calculations for
dilution were based on modelling and recommendations from the geotechnical report (MineGeotech,
2022) with a dilutant grade of 0g/t Au applied.
Estimation Methodology
The study carried out as part of this Pennys Find Ore Reserve is to a Pre-Feasibility Study level.
The relative accuracy of the estimate is reflected in the reporting of the Ore Reserves as per the
guidelines regarding modifying factors, study levels and Competent Persons contained in the JORC
2012 Code. The Ore Reserve estimate has only utilised the Indicated portion of this Resource based
on the applicable cut-off grades and has applied the modifying factors based on the various dilution
parameters determined by the underground geotechnical work, the applicable mining method and
recovery factors, to generate the final diluted and recovered Ore Reserve.
Material Modifying parameters
The Pennys Find gold project is located approximately 50km northeast of Kalgoorlie-Boulder.
Access to site is via existing public roads, utilising the sealed/unsealed Yarri Road from KalgoorlieBoulder and the unsealed Kurnalpi-Pinjin Road which passes directly by the project. Transportation
of ore shall be via the same road network and other public roads that access the milling infrastructure
in the region.
Mining shall be undertaken under the Mining Act 1978 on granted mining lease M27/156, an
approved clearing permit, mining proposal and mine closure plan from DEMIRS.
Page 12 of 41
ASX ANNOUNCEMENT
The Pennys Find Open pit is currently held to an existing approved Mine Closure Plan (MCP Reg ID
75697), with rehabilitation completed on all areas not considered for used by the Underground
operations. A Mining Proposal inclusive of Flora and Fauna, waste rock characterisation, additional
waste rock placement on the existing waste rock landform and for underground fill has been
approved by DEMIRS in consideration of the underground operation (Reg ID 82163).
The underground operation accesses the workings via the existing open pit which requires
dewatering during the pre-production phase. A groundwater licence is in place for water extraction
and operating strategy allowing 1,300,000kL per annum of water extraction for dewatering at Pennys
Find. The project has a prescribed premise licence to discharge mine dewater to Lake Penny to the
south of the project at 1,261,440 tonnes per annum.
The site has an Explosives Storage Licence (ETS002823) for two surface magazines currently on
site in a constructed magazine compound, one licenced to hold blasting explosives, and the other
detonators.
From previous open pit mining, much of the current infrastructure is in place, such as the ROM pad,
water storage dam, pipe infrastructure from the pit to Lake Penny, and internal roads. The site
offices have been removed, however, offices and workshop facilities can be easily reestablished for
the underground project. Site establishment and minor site road upgrades will be undertaken by the
mining contractor, inclusive of offices, hard-stand area and a workshop facility. Due to the proximity
of Kalgoorlie-Boulder, all external providers and staff shall come from the nearby city, with top up
FIFO personnel expected to support the operation housed in motel accommodation in the city.
Page 13 of 41
ASX ANNOUNCEMENT
Horizon Minerals Limited – Summary of Gold Mineral Resources
Cutoff
Measured
Au g/t
Mt
Au
g/t
Oz
Mt
Au g/t
Oz
Mt
Au g/t
Oz
Mt
Au g/t
Oz
Pennys Find OP
0.5
1.12
1.22
44,000
6.85
1.28
281,000
2.56
1.26
103,000
10.53
1.27
428,000
Burbanks OP
0.5
1.43
2.00
92,780
3.43
1.90
204,870
4.86
1.90
297,650
Burbanks UG
2.5/2.0*
0.12
4.30
16,730
1.07
4.40
151,190
1.19
4.40
167,920
Phillips Find OP
0.5
0.54
2.40
41,650
0.19
2.10
12,700
0.73
2.30
54,360
Phillips Find UG
2
0.03
2.30
210
0.03
2.30
210
Golden Ridge
1
0.47
1.83
27,920
0.10
1.70
2,800
0.52
1.82
30,720
Golden Ridge
North
0.8
0.65
1.15
24,260
0.77
1.30
32,340
1.42
1.23
56,600
Cannon UG
1
0.19
4.80
28,620
0.10
2.30
3,450
0.23
4.29
32,070
Monument
0.5
0.92
1.11
0.92
1.11
33,000
Pinner
0.5
0.06
1.02
2091
0.27
1.25
10,753
0.33
1.21
12,844
Pennys Find
1.5
0.30
5.19
51,000
0.12
3.00
12,000
0.43
4.57
63,000
Kalpini
0.8
1.40
2.43
108,000
0.50
2.00
31,000
1.87
2.33
139,000
Rose Hill UG
2
0.33
4.50
47,100
0.20
4.80
27,800
0.51
4.60
74,900
Rose Hill OP
0.5
0.09
2.00
6,100
0.29
2.00
18,400
Jacques-Peyes
0.8
0.97
2.59
81,000
0.80
2.00
49,000
1.74
2.32
130,000
Teal
1
1.01
1.96
63,680
0.80
2.50
64,460
1.81
2.20
128,140
Crake
0.8
1.33
1.47
63,150
0.10
1.30
3,300
1.42
1.46
66,450
Coote
1
0.40
1.50
21,000
0.42
1.54
21,000
Capricorn
0.5
0.70
1.20
25,500
0.70
1.20
25,500
Baden Powell
0.5
0.60
1.20
23,000
0.60
1.20
23,000
13.66
1.85
811,373
30.55
1.84
1,802,764
Project
Total
0.19
1.31
2.00
1.34
Indicated
12,300
56,300
15.74
1.85
Inferred
935,081
Total
33,000
Confirmation
The information in this report that relates to Horizon’s Mineral Resources estimates is extracted
from and was originally reported in Horizon’s ASX announcements:
•
•
•
•
•
•
•
“Updated Boorara Mineral Resource Delivers a 34% Increase in Gold Grade”
(Boorara) 27 April 2021,
Group Mineral Resource Statement – Amended”,”. (Burbanks, Phillips Find)
1 August 2024,
“High Grade Drill results and Resource Update for Rose Hill”, (Rose Hill, Golden
Ridge) 4 February 2020,
“Maiden Resources for Monument and Golden Ridge North” (Golden Ridge
North), 19 July 2023,
“Investor Presentation June 2022”, (Cannon) 31 May 2022,
“Group Mineral Resource Statement – Amended”,”. (Monument, Pinner) 1 August
2024,
“Pennys Find Resource Update”, (Pennys Find) 29 December 2023,
Page 14 of 41
ASX ANNOUNCEMENT
•
•
•
•
•
“Kalpini Gold Project Mineral Resource Update” (Kalpini) 28 September 2021,
“Jacques Find- Peyes Farm Mineral Resource update” (Jaques-Peyes) 15
September 2021,
“Intermin’s Mineral Resources Grow 30% to over 560,000 Ounces”, (ASX:IRC)
(Teal) dated 19 September 2018,
“Updated Crake Resource improves in quality” (Crake) 7 September 2021,
“Gold resources increase to 1.24moz” (Coote, Capricorn, Baden Powell) dated 28
September 2022,
The Company confirms that it is not aware of any new information or data that materially affects
the information included in the original market announcements and that all material assumptions
and technical parameters underpinning the estimates in those announcements continue to apply
and have not materially changed. The Company confirms that the form and context of the
Competent Person’s findings in relation to those Mineral Resources estimates or Ore Reserves
estimates have not been materially modified from the original market announcements.
Competent Persons Statement – Pennys Find
The information in this announcement which relates to Exploration Results, geological
interpretation and the Mineral Resource Estimation at Pennys Find is based on information
compiled by Horizon Minerals Limited under the supervision and review of Mr Stephen Godfrey
Resource Development Manager at Horizon Minerals Ltd, who is a Fellow of the Australasian
Institute of Mining and Metallurgy (FAusImm 110542) and a Member of the Australian Institute
of Geoscientists (MAIG 3993). Mr Godfrey consents to the inclusion in the announcement of the
matters based on their information in the form and context in which it appears. Mr Godfrey has
sufficient experience relevant to the style of mineralisation and deposit type under consideration
and to the activities being undertaken to qualify as a Competent Person as defined in the 2012
Edition of the “Australasian Code for Reporting of Exploration Results, Mineral Resources and
Ore Reserves”. Mr Godfrey consents to the inclusion in the report of matters based on his
information in the form and context in which it appears
Page 15 of 41
ASX ANNOUNCEMENT
Ore Reserve Statement
Location
Boorara Open Pit
Cannon Underground
Pennys Find
Underground
Total Ore Reserves
Reserve Category
Tonnes (kt)
Grade (g/t Au)
Gold Metal (kOz)
Proved
636.8
1.25
25.7
Probable
602.3
1.23
23.8
Total
1,239.1
1.24
49.5
Proved
0
0.00
0
Probable
135.0
4.1
17.68
Total
135.0
4.1
17.68
Proved
0
0.00
0
Probable
328.3
3.2
33.4
Total
328.3
3.2
33.4
TOTAL
1,702.4
1.84
100.6
Confirmation
The information in this report that relates to Horizon’s Mineral Ore Reserves is extracted from
and was originally reported in Horizon’s ASX announcements “Positive Results for Cannon
Underground Gold Project and Feasibility Study Update”, (ASX: HRZ) (Cannon) dated 29 March
2022, “Boorara Ore Reserve Supports Development - Amended” (Boorara) dated 1 August
2024, “Pennys Find Prefeasibility Study and Ore Reserve” (Pennys Find) dated 18 December
2024. The Company confirms that it is not aware of any new information or data that materially
affects the information included in the original market announcements and that all material
assumptions and technical parameters underpinning the estimates in those announcements
continue to apply and have not materially changed. The Company confirms that the form and
context of the Competent Person’s findings in relation to those Mineral Resources estimates or
Ore Reserves estimates have not been materially modified from the original market
announcements.
Boorara
Mr Adrian Jones is the Competent Person for the July 2024 Boorara Ore Reserve estimate, and
supervised preparation of the estimate with assistance from specialists in each a